Professional Documents
Culture Documents
CCBPI CANTEEN - Rehabilitation Work_rev.1_1(Old)
CCBPI CANTEEN - Rehabilitation Work_rev.1_1(Old)
CCBPI CANTEEN - Rehabilitation Work_rev.1_1(Old)
Note:
I. Canteen Building
1 Repainting of existing columns and parapet walls are considered.
2 Total replacement of existing roof panel. - DELETED
3 All indoor/outdoor units and all related works for airconditioning works. - DELETED
4 Landscaping work. - DELETED
5 Parking and Tensile Tents. - DELETED
II. General
1 All previously proposed items specified with American brands will be subject to cost verification,
value engineering, and will otherwise be specified with approved equal specs in reference to the
awarded project cost.
REVIEWED &
: ARCH. GEEFY EVANGELISTA, UAP
APPROVED BY
SIGNATURE