ETHANELI

PAINTS – COATINGS AND WATERPROOFING SERVICES


134 Stockholm St. PGPV Pasig City
Tel. 5720135/Fax.3692893
Email: ethanelipcwservices@yahoo.com
__________________________________________________________________________________

August 2, 2013

DYNAMIC PLANNERS & CONSTRUCTION CORPORATION


#22, Rolex St., West Fairview, Quezon City, Philippines

Attention: Arch. Nio A. Guzman

Project: SUNTRUST TREETOP VILLAS

Location: Coronado St. Mandaluyong City

Subject: Waterproofing Proposal

Area 1: Area 6:
T&B For Precast joint
CLUSTER 1 : 822.90 sqm.
CLUSTER 2 : 619.63 sqm.
CLUSTER 3 : 666.93 sqm.
CLUSTER 4 : 1,051.17 sqm.

Area 2:
PODIUM DECK : 3,010.66 sqm.

Area 3:
ROOF DECK
CLUSTER 1 : 231.08 sqm.
CLUSTER 2 : 11.40 sqm.
CLUSTER 3 : 18.64 sqm.

Area 4:
EE ROOM : 29.16 sqm.

Area 5:
Fire Tank : 1,164.24 sqm.
Water Tank : 1,471.89 sqm.
Pump Room : 385.07 sqm.
Cental STP : 554.31 sqm.
Gentlemen,

In connection with the above subject, we are pleased to offer you the following for your consideration.

I. SCOPE OF WORK
1. Mobilization and preparation of materials, equipments, tools including consumables
and manpower to the job site.
2. Surface Preparation:
a) Preparation of entire surface to be coated by means of power or hand
tool method to remove dirt and loose materials.
b) Cleaning of surface by industrial chemical or light sanding to remove
contaminants, traces of oils and other foreign matters to prepare the
surface for a maximum adhesion of waterproofing to be applied.
c) Allow the surface to dry until no moisture is present to prior start of tank
lining.
3. System Application for Area 1 to 4:
a) Application of one (1) coat Bondflex Elastomeric Membrane Primer.
b) Laying of Fiber Mesh
c) Application of one (1) coat Bondflex Elastomeric Membrane midcoat.
d) Application of three (3) coats, Bondflex Elastomeric Waterproofing
Membrane as topcoat.
System Application for Area 5:
a) Clogging of leak prior to application of Cementitious Waterproofing.
b) Application of two (2) coats Sealproof Cementitious Waterproofing.
c) Application of two (2) coats Sealbond Epoxy Tanklining. ( For Water
Tank only )
System Application for Precast:
a) Application of Cementitious grouting.
b) Application of Elastomeric membrane as primer.
c) Installation of fiber mesh.
d) Application of Elastomeric Membrane.
4. Clean up and project turnover.
II. COST OF OUR PROPOSAL: (Labor & Materials)

Area 1:
T&B
CLUSTER 1 : 822.90 sqm. x P360/sqm = P 296,244.00
CLUSTER 2 : 619.63 sqm. x P360/sqm = P 223,066.80
CLUSTER 3 : 666.93 sqm. x P360/sqm = P 240,094.80
CLUSTER 4 : 1,051.17 sqm. x P360/sqm = P 378,421.20

Area 2:
PODIUM DECK : 3,010.6 sqm. x P360/sqm = P 1,083,816.00

Area 3:
ROOF DECK
CLUSTER 1 : 231.08 sqm. x P360/sqm = P 83,188.80
CLUSTER 2 : 11.40 sqm. x P360/sqm = P 4,104.00
CLUSTER 3 : 18.64 sqm. x P360/sqm = P 6,710.40

Area 4:
EE ROOM : 29.16 sqm. x P550/sqm = P 16,038.00

Area 5:
Fire Tank : 1,164.24 sqm. x P350/sqm = P 407,484.00
Water Tank : 1,471.89 sqm. x P550/sqm =P 809,539.50
Pump Room : 385.07 sqm. x P350 = P 134,774.50
Central STP : 554.31 x P350 = P 194,008.50

Area 6:
P 200/lm.
Total Amount: P 3,877,490.50

III. CONDITIONS OF OUR PROPOSAL:

1 ETHANELI shall supply the following to undertake the above scope of work:
a. Skilled manpower and technical supervision;
b. Waterproofing materials, tools and equipment;
2 CLIENT shall provide the following to ETHANELI during execution of work free
of charge:
a. Water, power and lighting facilities;
b. Necessary permits and gate passes to ETHANELI personnel and
equipment;
c. Space for safe storage of tools and equipment;
3 ETHANELI shall be allowed to work overtime if necessary.
4 ETHANELI shall not be responsible of any delays caused by CLIENT or other
contractor/s during the execution of work
5 CLIENT shall provide a designated area within their premises for waste, dirt and
debris for disposal free of charge.
IV. START-UP / COMPLETION:

ETHANELI shall be given a lead-time of three to five (3 - 5) days to start to work


after award of contract and receipt of down payment for mobilization and preparation
of equipment to the jobsite.
Completion as per ETHANELI and CLIENT agreed schedule.

V. TERMS OF PAYMENT:

Thirty percent (30%) down payment after receipt of confirmed purchase order;
balance of Seventy percent (70%) based on actual painted finished area.

VI. WARRANTY:

ETHANELI shall guarantee the workmanship for the application of the above
materials for a period of ten (10) years from the date of completion against leaks
under normal conditions. However, damaged done by a third party, act of God, or
other contractor/s or damaged due to high impact, metal abrasion, burns and force
majeure that are beyond our control are not covered by this warranty. This warranty
shall be limited only to the supply of labor necessary to retouch/rework the areas
found to be defective. No other warranties shall be availed to the client including but
not limited loss of time, profit and other incidentals whether express or implied.

Thank you very much and we look forward in providing you our services soon.

Very Truly Yours,

Engr. Antonio G. Masinda, Jr.


09217149266/5720135