DAFTAR KUANTITAS DAN HARGA

Pekerjaan : PEMBANGUNAN GEREJA

HARGA JUMLAH
No. URAIAN PEKERJAAN SATUAN KUANTITAS SATUAN HARGA
(Rp) (Rupiah)

I PEKERJAAN TANAH
1 Pek. Galian tanah Pondasi Tapak 130x120x120 M3 8.25 200,000.00 1,650,000.00
2 Pek. Tanah Kembali Pondasi M3 3.67 80,000.00 293,600.00
1,943,600.00

II PEKERJAAN STRUKTUR BANGUNAN LANTAI 1


1 Pek. Cor Pondasi Tapak 130x120x30 M3 4.68 5,300,000.00 24,804,000.00
2 Pek. Cor Sloof 20/30 Beton Bertulang M3 3.60 5,300,000.00 19,080,000.00
3 Pek. Kolom Praktis 15/15 Beton Bertulang. Mutu K225 M3 0.45 5,300,000.00 2,385,000.00
4 Pek. Cor Balok Latei 15/20 Atas Pintu / Jendela M3 0.31 5,300,000.00 1,643,000.00
5 Pek. Cor Kolom Utama Lt. 1 20/30 Besi 12mm SNI ( Mutu K225 ) M3 3.15 5,300,000.00 16,695,000.00
6 Pek. Cor Plat Lantai 2 Tebal 10cm ( Besi 10mm Sni K225 ) M3 14.40 5,300,000.00 76,320,000.00
7 Pek. Cor Tangga Besi 12mm M3 3.00 5,300,000.00 15,900,000.00
8 Balok Utama M3 5.76 5,300,000.00 30,528,000.00
187,355,000.00

IV PEKERJAAN DINDING LANTAI 1


1 Pek. Dinding Bata Camp 1PC : 4PS M2 49.27 120,000.00 5,912,400.00
2 Pek. Plaster Dinding 1PC : 3PC M2 148.00 70,000.00 10,360,000.00
3 Pek. Acian Dinding 1PC : 3PC M2 148.00 30,000.00 4,440,000.00
20,712,400.00

VII PEKERJAAN PLAFOND LANTAI 1


1 Pek. Plafon Gypsum ( Rangka Furing 0,3mm + Gypsum 9mm ) 120.00 140,000.00 16,800,000.00
16,800,000.00

IX PEKERJAAN PINTU DAN JENDELA LANTAI 1


1 Pintu Utama ( Kusen + Daun Pintu Kayu Solid ) Unit 1.00 5,000,000.00 5,000,000.00
2 Pek. Jendela ( Aluminium Hitam + Kaca Polos 5mm ) Unit 2.00 3,000,000.00 6,000,000.00
3 Pintu kamar Unit 1.00 2,500,000.00 2,500,000.00
4 Pintu kamar mandi Unit 1.00 750,000.00 750,000.00
14,250,000.00

XI PEKERJAAN KERAMIK & GERANITE LANTAI 1


1 Pek. Lantai Keramik 40x40 M2 144.00 250,000.00 36,000,000.00
2 Pek. Lantai Keramik 40x40 Tangga M2 8.55 270,000.00 2,308,500.00
38,308,500.00
XIII PEKERJAAN ELEKTRIKAL LANTAI 1
1 Pek. Downlight Phillips 12 watt Titik 21.00 250,000.00 5,250,000.00
2 Pek. Lampu Spotlighrt Dinding Titik 6.00 300,000.00 1,800,000.00
3 Saklar Triple Titik 7.00 125,000.00 875,000.00
4 Stop Kontak Titik 10.00 100,000.00 1,000,000.00
5 Instalasi MCB 10 Ampere Unit 4.00 100,000.00 400,000.00
6 Box Panel 40x60 Set 1.00 250,000.00 250,000.00
9,575,000.00
XIV INSTALASI KABE LELEKTRIKAL
1 Kabel NYA 1,5mm @ 100m Roll 6.00 550,000.00 3,300,000.00
2 Kabel NYA 1,5mm @ 100m Roll 4.00 550,000.00 2,200,000.00
5,500,000.00

XVII PEKERJAAN PENGECATAN


1 Cat. Eksterior Jotun Shield + 2x Timpa Cat Utama M2 224.00 30,000.00 6,720,000.00
2 Cat. Interior Jotun Easywipe + 2x Timpa Cat Utama M2 224.00 30,000.00 6,720,000.00
13,440,000.00

XIX INSTALASI PIPA AIR BERSIH DAN KOTOR


1 Pipa 4 inchi m' 24.00 40,000.00 960,000.00
2 pipa 1/2 inchi m' 24.00 10,000.00 240,000.00
3 Wastafel set 1.00 1,500,000.00 1,500,000.00
4 Kloset duduk set 1.00 2,000,000.00 2,000,000.00
4,700,000.00

TOTAL 312,584,500.00
Dibulatkan