Overview on Technical Requirement for Supply Application

1
Overview on Technical Requirement for Supply Application

At the end of the session, participants are able:

To comprehend high level process of supply application > 100A and its critical milestones

To understand roles of electrical consultant engineer and TNB in supply application > 100A

To refer to guidelines e.g.: ESAH 3.1 and Substation Design Booklet Edition 2.0
(2024) in complying technical requirement for supply application

22
Overview on Technical Requirement for Supply Application
High Level Process for Supply Application > 100A

Pre-Requisite for work commencement Commissioning


Estimation i. Connection Charge Payment &
Application CCC supporting
& ii. Site Readiness
Submission iii. Permit & Wayleave Approval letter
Connection Charge
Issuance iv. Substation handover

1 2 3 4 5 6 7 8

Kick Off Construction SD Payment


Technical Document &
Review Meeting Work
Meter
Installation

Roles of
TNB &
electrical
consultant
Engineer
for each
process

33
Overview on Technical Requirement for Supply Application
Application Submission – Consultant Engineer to submit required documents to TNB local office as
1 initiation of supply application journey

Reference in
No. Documents
ESAH 3.1
1. Consultant Appointment Letter Appendix 5
2. Developer/Project Owner Company Registration Certificate

3.
Map A – Basic Information (Developer/Consultant/Project Info – generated from Registration in MyTNB
MyTNB SSP)
Portal
3(i) Latest Development Order Plan Approved by Local Authority
Appendix 4
Site Plan & Contour Plan with Proposed Sub-station Sites (Top view & Side-Section (Electricity Supply
3(ii)
Plan) Application
3(iii) Layout Plan of Sub-station Building Exceeding 100A
Checklist for
3(iv) Location plan on meter panel / room or front elevation of building requiring supply Consultant
3(v) Location & Layout Plan of Main Switch Room Engineer)

3(vi) Single Line Diagram / Schematic of Installation (Before TNB Meter) Please attached Service Notification number
during submission at respective TNB local office
Detailed Site Development Plan (JUPEM standard map with Coordinates System –
3(vii)
UTM WGS84)
4. Map B – Load & Metering Details Appendix 6
5. Preliminary metering information sheet (for supply intake at 11kV & above) Appendix 8

6. Power Quality Compliance Declaration Form (applicable for PQ sensitive customer) Appendix 7
7. Substation Land Documents

8. Fire-fighting Documentation for attached substation

44
Overview on Technical Requirement for Supply Application
Application Submission – Consultant Engineer to submit required documents to TNB local office as
1 initiation of supply application journey

55
Overview on Technical Requirement for Supply Application
Application Submission – Consultant Engineer to submit required documents to TNB local office as
1 initiation of supply application journey

66
Overview on Technical Requirement for Supply Application
2 Technical Review – a process where mutual agreement between TNB & Consultant Engineer on technical design is achieved

Technical Document Important information to


Reviewed by TNB TNB
Consultant submit
technical i. Supply Scheme
document/drawing Map B – Load & Metering Details ii. Demand Estimation
iii. Substation Requirements

TNB Review Site Plan & Contour Plan with Proposed Sub-
(Joint meeting if required) station Sites (Top view & Side-Section Plan)
NO Orientation & Design of Substation
Layout Plan of Sub-station Building

Location plan on meter panel / room or front


elevation of building requiring supply
Accepted i. Location of meter
Location & Layout Plan of Main Switch Room ii. Specification & Design of
meter panel
Preliminary metering information sheet (for
YES supply intake at 11kV & above)

Single Line Diagram / Schematic of Installation Compliance of Landlord Tenant


Estimation & Issue (Before TNB Meter) Scheme
Connection Charge
Power Quality Compliance Declaration Form Compliance of customer
(applicable for PQ sensitive customer) equipment on PQ
77
Overview on Technical Requirement for Supply Application
2 Technical Review – Example/Case Study – Demand Estimation

Assuming a development required electricity as below:


A. What is the demand estimation?
1. 40 unit Rumah Teres 1 Tingkat
B. What supply scheme required?
2. 20 unit Rumah Berkembar 2 Tingkat C. How many substation required?
3. 10 unit Kedai 1 Tingkat
Reference from ESAH 3.1 A Demand Estimation

No of kWMD Total
Type of Premise GCF
Consumer Groups Coincident Factors Units /Unit kWMD

Residential 0.90
Rumah Teres 1 Tingkat 40 3.00 0.90 108
Commercial 0.87 Rumah Berkembar 1 Tingkat 20 7.00 0.90 126

Industrial 0.79 Kedai 1 Tingkat 10 15.00 0.87 131


Total MD for Development 365

*The above MD range is meant for reference as the minimum value. MD declared by consultants must be
accompanied with the connected load and design calculations of the development
88
Overview on Technical Requirement for Supply Application
2 Technical Review – Example/Case Study – Supply Scheme Required

Assuming a development required electricity as below: Summing up all


A. What is the demand estimation?
1. 40 unit Rumah Teres 1 Tingkat premises MD in a
B. What supply scheme required? single development,
2. 20 unit Rumah Berkembar 2 Tingkat C. How many substation required?
3. 10 unit Kedai 1 Tingkat substation is
required
Each unit of premise could
be supplied through 230V or B Supply Scheme Required
400V (UG/OH) according to Table 3-1: Minimum supply schemes for various M.D levels Table 3-2: Requirement of substations for single development
MD per unit declared M.D ranges of individual
consumer
Supply voltage Minimum supply scheme M.D ranges of single
Substations requirement
development
Single phase overhead or underground services from
Calculation from Demand Estimation Up to 12 kVA 230V
existing LV network Up to 350kVA
A new 11/0.4kV substation may be required,
subject to system capability study by TNB
Three phase overhead or underground cable service
>12kVA to 100kVA
400V from existing LV network subject to system capability >350 kVA to < 1000kVA A new 11/0.4kV substation is required
(Non-Domestic)
study by TNB
Three phase overhead or underground cable service 11/0.4kV and/or 11kV substations is required. A
Up to 100 kVA (Domestic) 400V from existing LV network subject to system capability 1000kVA up to <5000kVA new PPU may be required, subject to system
Type of No of kWMD Total study by TNB capability study by TNB
GCF
Premise Units /Unit kWMD Underground cable service from feeder pillar or a 22/0.4kV and/or 22kV substations is required. A
>100kVA to 350kVA 400V new/existing substation, subject to system capability 1000kVA up to 10000kVA new PPU may be required, subject to system
study by TNB capability study by TNB
Rumah Teres 1 >350 kVA to 1000kVA 400V Direct underground cable service from new substation 11/0.4kV and/or 11kV and/or 33kV substations
40 3.00 0.90 108 and/or PPU is required. A new PMU may be
Tingkat Directly fed through TNB 11kV switching station. An 5000kVA to 25000kVA
required subject to system capability study by
Rumah 1000kVA up to <5000kVA 11kV additional PPU land may need to be allocated subject
TNB
to system capability study by TNB.
Berkembar 1 20 7.00 0.90 126 Directly fed through TNB 22kV switching station An
11/0.4kV and/or 11kV and/or 33kV substations
Tingkat and/or PPUs and PMUs 132kV is required. A
1000kVA up to 10000kVA 22kV additional PPU land may need to be allocated subject Above 25000kVA
new PMU 275kV may be required subject to
to system capability study by TNB’
Kedai 1 Tingkat 10 15.00 0.87 131 system capability study by TNB
Directly fed through TNB 33kV switching station An
Total MD for Development 365 5000kVA to 25000kVA 33kV additional PMU land may need to be allocated subject
to system capability study by TNB’
Directly fed through TNB 132kV or 275kV substation
respectively. TNB shall reserve the absolute right to
25,000kVA to
132kV , 275 kV provide alternative arrangements after taking into
<100,000kVA
consideration the location, economic and system
security factor
Directly fed through TNB 275kV substation. TNB shall
reserve the absolute right to provide alternative
100,000kVA and above 275 kV
arrangements after taking into consideration the
location, economic and system security factor 99
Overview on Technical Requirement for Supply Application
2 Technical Review – Example/Case Study – Numbers of Substation Required

Assuming a development required electricity as below:


A. What is the demand estimation?
1. 40 unit Rumah Teres 1 Tingkat
B. What supply scheme required?
2. 20 unit Rumah Berkembar 2 Tingkat C. How many substation required?
3. 10 unit Kedai 1 Tingkat

C How many substation required


TRANSFORMER UTILISATION DURING PLANNING STAGE Since majority of the load is
residential (234kW vs 131kW),
Calculation from Demand Estimation No Type of Development % Transformer Loading
% transformer loading during
1. Residential 85% planning stage is 85%. Hence
2. Commercial 60% the computation as below:
Type of No of kWMD Total
GCF
Premise Units /Unit kWMD
3. Industrial 60%
365𝑘𝑊
Rumah Teres 1
40 3.00 0.90 108
Mixed (Residential + *Majority Residential: 85% = 429.41𝑘𝑊
Tingkat
Rumah
4. Commercial / Industrial) Majority Commercial / 0.85
Berkembar 1 20 7.00 0.90 126 [for non-compact sub] Industrial: 60%
Tingkat 429.41𝑘𝑊
Kedai 1 Tingkat 10 15.00 0.87 131 **Mixed (Residential + 505.19𝑘𝑉𝐴
Total MD for Development 365 5. Commercial / Industrial) 60% 0.85
[for compact sub]
Therefore, nearest transformer
Individual/Dedicated capacity is 750kVA. A single
6. Based on customer’s load
Commercial or Industrial chamber substation is required.
*Max capacity for compact substation is limited to 500kVA for residential development
* Max of one transformer for each substation site
10
10
Overview on Technical Requirement for Supply Application
2 Technical Review – a process where mutual agreement between TNB & Consultant Engineer on technical design is achieved

Map B is important to determine demand estimation, supply


Example of a complete Map B scheme and substations required in a development. In
addition, meter type prior to kWMD/unit also could be
checked through Map B.

1111
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design

Manual/Document below could be obtained through ESAH link in TNB


website:
1. Substation Design Booklet Edition 2.0 (2024)
2. Compact Substation Plinth Design
3. PIAT Civil Checklist for 11kV Substation
4. Anti Climb Fence

Substation Design Booklet Edition 2.0 (2024)

https://www.tnb.com.my/commercial-industrial/for-housing-developers- PIAT Civil Checklist for 11kV Substation


electrical-contractors/#electricity-supply-application-handbook-esah
12
12
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design

1. Trench depth 1500mm


2. Trench width 900mm

13
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design

Location of light at outer of building

Lampiran C1: 1 2 B 3
PE 11/0.4kV Bersendirian 1 Ruang
(RMU) A

Lighting: A
RMU 3+2

A
TX

FEEDER PILLAR
1. Outdoor – LED 23W with water
1000 KVA

TX S/GEAR
ROOM ROOM

proof casing EL
EL

2. Indoor – LED T8 23W B

14
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design

Location of light at inner of building


Light mounted on wall at height of 2.7m from floor

Light fixture suspended from


ceiling at height of 2.7m from floor

1 2 B 3

A
RMU 3+2

A
TX
FEEDER PILLAR

1000 KVA

TX S/GEAR
ROOM ROOM

EL
EL

B
15
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design

Compact Substation Plinth Design

16
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design

Compact Substation Plinth Design

17
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design

Usage of Bollard replacing anti climb fence

18
Overview on Technical Requirement for Supply Application
Estimation & Connection Charge Issuance – After completion of technical review, all information and
3 specification would be used by TNB for estimation and determination of tapping point hence connection charge
issued accordingly

Pre-Requisite for work commencement Commissioning


Estimation i. Connection Charge Payment &
Application CCC supporting
& ii. Site Readiness
Submission iii. Permit & Wayleave Approval letter
Connection Charge
Issuance iv. Substation handover

1 2 3 4 5 6 7 8

Kick Off Construction SD Payment


Technical Document &
Review Meeting Work
Meter
Installation

CC Issuance after completion of technical review


MSL 3A = 30 days for 22kV and below, 60 days for 33kV
19
19
Overview on Technical Requirement for Supply Application
4 Kick Off Meeting

A kick off meeting will be held between TNB, Developers &


Consultants to have mutual agreement on:

1. Supply Requirement Date


2. Program of Work
i. Date of CSP payment
ii. Date of Substation ready including substation
land matter
iii. Date of Site Ready
3. Roles of each parties

20
20
Overview on Technical Requirement for Supply Application
5 Pre-requisite for work commencement

Construction site ready


- Access road
- Drainage work, water and others utility
- No blockages

Substation handover
- Approved PIAT Civil
- Substation Land Matter related document
submitted to TNB (lease or handover) TNB start
construction
work
Road Digging Permit / Wayleave
- Cost of road digging charged by local
authorities to be borne by applicants

Connection Charge
- Paid for full settlement

21
21
Overview on Technical Requirement for Supply Application
6 Construction Work

Pre-Requisite for work commencement Commissioning


Estimation i. Connection Charge Payment &
Application CCC supporting
& ii. Site Readiness
Submission iii. Permit & Wayleave Approval letter
Connection Charge
Issuance iv. Substation handover

1 2 3 4 5 6 7 8

Kick Off Construction SD Payment


Technical Document &
Review Meeting Work
Meter
Installation

Time taken to implement electrification scheme


after completion of pre-requisite
MSL 3B = 60 days for 22kV and below, 120 days
for 33kV (PJCJ = 180 days)
22
22
Overview on Technical Requirement for Supply Application
7 Commissioning & CCC Supporting Letter

Surat kepada ACEM & IEM pada 27 Ogos 2020 bertajuk Pematuhan dan Penambahbaikan Proses Kerja Perancangan Bekalan Elektrik
bagi Permohonan ‘Certificate of Completion and Compliance (CCC) adalah dirujuk 23
23
Overview on Technical Requirement for Supply Application
7 Commissioning & CCC Supporting Letter

From TNB to Consultant Engineer From Consultant Engineer to TNB


after commissioning of supply to apply for CCC Supporting Letter

24
24
Overview on Technical Requirement for Supply Application
8 Security Deposit Payment & Meter Installation

Draft Move In is
allowed after CC
Payment

Submit Move in
through MyTNB SD paid
Portal

Approved by
REWORK Careline Install meter

YES

Approved? COMPLETE

Issue SD
25
25
Overview on Technical Requirement for Supply Application
Recap on High Level Process for Supply Application > 100A
Application CC Issuance after completion of
Submission technical review
MSL 3A = 30 days for 22kV and
below, 60 days for 33kV

Pre-Requisite for work commencement Commissioning


Estimation i. Connection Charge Payment &
& ii. Site Readiness CCC supporting
Connection Charge iii. Permit & Wayleave Approval letter
Issuance iv. Substation handover

1 2 3 4 5 6 7 8

Appendix 4 SD Payment
(Electricity Technical Document Kick Off Construction
Meeting Work &
Supply Review
Application Meter
Exceeding i. ESAH 3.1
Installation
100A ii. Substation Design Booklet
Checklist for Edition 2.0 (2024)
Consultant iii. PIAT Civil Checklist Time taken to implement electrification
Engineer) scheme after completion of pre-requisite
MSL 3B = 60 days for 22kV and below,
120 days for 33kV (PJCJ = 180 days)

26
26
Thank you
“If you fail to plan, you are planning to fail”

27