Overview_on_Technical_Requirement_for_Supply_Application_2024
Overview_on_Technical_Requirement_for_Supply_Application_2024
1
Overview on Technical Requirement for Supply Application
To comprehend high level process of supply application > 100A and its critical milestones
To understand roles of electrical consultant engineer and TNB in supply application > 100A
To refer to guidelines e.g.: ESAH 3.1 and Substation Design Booklet Edition 2.0
(2024) in complying technical requirement for supply application
22
Overview on Technical Requirement for Supply Application
High Level Process for Supply Application > 100A
1 2 3 4 5 6 7 8
Roles of
TNB &
electrical
consultant
Engineer
for each
process
33
Overview on Technical Requirement for Supply Application
Application Submission – Consultant Engineer to submit required documents to TNB local office as
1 initiation of supply application journey
Reference in
No. Documents
ESAH 3.1
1. Consultant Appointment Letter Appendix 5
2. Developer/Project Owner Company Registration Certificate
3.
Map A – Basic Information (Developer/Consultant/Project Info – generated from Registration in MyTNB
MyTNB SSP)
Portal
3(i) Latest Development Order Plan Approved by Local Authority
Appendix 4
Site Plan & Contour Plan with Proposed Sub-station Sites (Top view & Side-Section (Electricity Supply
3(ii)
Plan) Application
3(iii) Layout Plan of Sub-station Building Exceeding 100A
Checklist for
3(iv) Location plan on meter panel / room or front elevation of building requiring supply Consultant
3(v) Location & Layout Plan of Main Switch Room Engineer)
3(vi) Single Line Diagram / Schematic of Installation (Before TNB Meter) Please attached Service Notification number
during submission at respective TNB local office
Detailed Site Development Plan (JUPEM standard map with Coordinates System –
3(vii)
UTM WGS84)
4. Map B – Load & Metering Details Appendix 6
5. Preliminary metering information sheet (for supply intake at 11kV & above) Appendix 8
6. Power Quality Compliance Declaration Form (applicable for PQ sensitive customer) Appendix 7
7. Substation Land Documents
44
Overview on Technical Requirement for Supply Application
Application Submission – Consultant Engineer to submit required documents to TNB local office as
1 initiation of supply application journey
55
Overview on Technical Requirement for Supply Application
Application Submission – Consultant Engineer to submit required documents to TNB local office as
1 initiation of supply application journey
66
Overview on Technical Requirement for Supply Application
2 Technical Review – a process where mutual agreement between TNB & Consultant Engineer on technical design is achieved
TNB Review Site Plan & Contour Plan with Proposed Sub-
(Joint meeting if required) station Sites (Top view & Side-Section Plan)
NO Orientation & Design of Substation
Layout Plan of Sub-station Building
No of kWMD Total
Type of Premise GCF
Consumer Groups Coincident Factors Units /Unit kWMD
Residential 0.90
Rumah Teres 1 Tingkat 40 3.00 0.90 108
Commercial 0.87 Rumah Berkembar 1 Tingkat 20 7.00 0.90 126
*The above MD range is meant for reference as the minimum value. MD declared by consultants must be
accompanied with the connected load and design calculations of the development
88
Overview on Technical Requirement for Supply Application
2 Technical Review – Example/Case Study – Supply Scheme Required
1111
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design
13
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design
Lampiran C1: 1 2 B 3
PE 11/0.4kV Bersendirian 1 Ruang
(RMU) A
Lighting: A
RMU 3+2
A
TX
FEEDER PILLAR
1. Outdoor – LED 23W with water
1000 KVA
TX S/GEAR
ROOM ROOM
proof casing EL
EL
14
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design
1 2 B 3
A
RMU 3+2
A
TX
FEEDER PILLAR
1000 KVA
TX S/GEAR
ROOM ROOM
EL
EL
B
15
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design
16
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design
17
Overview on Technical Requirement for Supply Application
2 Technical Review – Determination of Substation Design
18
Overview on Technical Requirement for Supply Application
Estimation & Connection Charge Issuance – After completion of technical review, all information and
3 specification would be used by TNB for estimation and determination of tapping point hence connection charge
issued accordingly
1 2 3 4 5 6 7 8
20
20
Overview on Technical Requirement for Supply Application
5 Pre-requisite for work commencement
Substation handover
- Approved PIAT Civil
- Substation Land Matter related document
submitted to TNB (lease or handover) TNB start
construction
work
Road Digging Permit / Wayleave
- Cost of road digging charged by local
authorities to be borne by applicants
Connection Charge
- Paid for full settlement
21
21
Overview on Technical Requirement for Supply Application
6 Construction Work
1 2 3 4 5 6 7 8
Surat kepada ACEM & IEM pada 27 Ogos 2020 bertajuk Pematuhan dan Penambahbaikan Proses Kerja Perancangan Bekalan Elektrik
bagi Permohonan ‘Certificate of Completion and Compliance (CCC) adalah dirujuk 23
23
Overview on Technical Requirement for Supply Application
7 Commissioning & CCC Supporting Letter
24
24
Overview on Technical Requirement for Supply Application
8 Security Deposit Payment & Meter Installation
Draft Move In is
allowed after CC
Payment
Submit Move in
through MyTNB SD paid
Portal
Approved by
REWORK Careline Install meter
YES
Approved? COMPLETE
Issue SD
25
25
Overview on Technical Requirement for Supply Application
Recap on High Level Process for Supply Application > 100A
Application CC Issuance after completion of
Submission technical review
MSL 3A = 30 days for 22kV and
below, 60 days for 33kV
1 2 3 4 5 6 7 8
Appendix 4 SD Payment
(Electricity Technical Document Kick Off Construction
Meeting Work &
Supply Review
Application Meter
Exceeding i. ESAH 3.1
Installation
100A ii. Substation Design Booklet
Checklist for Edition 2.0 (2024)
Consultant iii. PIAT Civil Checklist Time taken to implement electrification
Engineer) scheme after completion of pre-requisite
MSL 3B = 60 days for 22kV and below,
120 days for 33kV (PJCJ = 180 days)
26
26
Thank you
“If you fail to plan, you are planning to fail”
27