This form provides agreed record of necessary stoppage of work indicating reason for stoppage and related information.
Two original copies of this form to be completed and signed by [Contractor] and [Consultant] for record Purpose
Stoppage Duration
Stoppage From To Total Work Instructed
Day/Date Stoppage Reason
Circumstances HR HR. Hrs. Location By
[Contractors] Comments
Due to bad weather condition (Heavy rain) the, scaffold erection and carpentry work for 6th Floor slab have been postponed from 3rd of January
2023 to 4th of January 2023 because of high risks works, such as work at heights, and concrete quality issues the work been stopped.
[Consultant’s ] Comments
Position Position
Company Company