mini project3 ppt (1)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 23

DESIGN OF

AQUEDUCT
Presented by :

Ankita Gajendra (2001003)


Ashirbad Kathua (2001005)

Department of Civil Engineering


GITA AUTONOMOUS COLLEGE, BHUBANESWAR
CONTENTS…
1 Cross Drainage Works 4 Design Considerations of
Aqueduct
2 Types of Cross Drainage Works 4.1 Design of Drainage Water way
4.2 Design of Canal Water way
2.1 Aqueduct 4.3 Head loss and bed
2.2 Drainage Syphon level at different sections
2.3 Super Passage 4.4 Design of Transition
2.4 Canal Syphon
2.5 Level Crossing
2.6 Inlet and Outlet
5 Conclusion
3 Types of Aqueduct 6 Reference
3.1 Type l
3.2 Type ll
3.3 Type lll
1 Cross Drainage Works
 The structures that are built to cross
the canal water across the drain or any
obstructions are called cross drainage
works.

 It prevent the canal water from mixing


into drain water.

 This type of structure is costlier one


and needs to be avoided as much as
possible.
Lune Aqueduct , Lancashire
2 Types of Cross Drainage Works
The canal crosses the drainage water in either of the following ways :

1. Canal over the drainage :


(i) AQUEDUCT
(ii) DRAINAGE SYPHON

2. Canal below the drainage :


(i) SUPER PASSAGE
(ii) CANAL SYPHON

3. Drain passes through the canal :


(i) LEVEL CROSSING
(ii) INLETS AND OUTLETS
Aqueduct

 In an aqueduct, the canal bed level is


much higher than HFL of drain.

 Here both the canal water and


drainage water flows freely under
gravity.

 A canal trough is to be constructed


in which canal water flows from
upstream to downstream.
Drainage Syphon (Syphon Aqueduct)

 In an syphon aqueduct, canal water


is carried above the drainage but the
HFL of drain is above canal trough.

 The drainage water flows under


syphonic action.

 The flooring of drain is depressed


downwards by constructing a vertical
drop to discharge the drain water.
Super Passage

 In a Super passage, the FSL(Full


Supply Level) of canal is below the
drainage bed level.

 Here both the drainage water and


canal water flows freely under gravity.

 A drainage trough is constructed at


road level through which drainage water
flows from upstream to downstream.

This is simply a reverse of Aqueduct.


Canal Syphon

 In an canal syphon, drainage is


carried over canal similar to a super
passage but the FSL of canal is above
the drainage trough.

The canal water flows under syphonic


action.

Flooring of canal is depressed and


ramp like structure is provided at
upstream and downstream to form
syphonic action.
Level Crossing

 When the bed level of canal is equal to


the drainage bed level, then level crossing
is to be constructed.

This consists the following steps :


 Construction of weir to stop
drainage water behind it.
 Construction of canal
regulator across a canal.
 Construction of head
regulator across a drainage.
Inlet and Outlet

 An inlet is a structure constructed in


order to allow the drainage water to enter
the canal and get mixed with the canal
water.

 But, when the drainage discharge is


high, an outlet may sometimes be
constructed to escape out the additional
discharge.

 Such a structure is generally adopted


when the drainage discharge is small and
the drain crosses the canal.
3 Types of Aqueduct

Type I
 In this type, the sides of the aqueduct are
earthen bank with complete earthen slopes.
The length of the culvert through which the
drainage water has to pass under the canal
should not only be sufficient to accommodate
the water section of the canal but also the
earthen banks of the canal with adequate
slopes.
Type Il

 In this type, the canal continues


in its earthen section over the
drainage
 But the outer slopes of canal
banks are replaced by retaining
walls, thereby, reducing the length
of the drainage culvert.
Type Ill

 In this type, earthen sec- tion of the


canal is discontinued and the canal
water is carried in a masonry or a
concrete trough.

 The canal is generally flumed in this


case, so as to effect economy in
construction.

The culvert length or width of aqueduct is maximum in Type I and minimum in


Type III. An intermediate value exists in Type II.
4 Design Considerations of Aqueduct
Design of Drainage Water way:

An approximate value of required waterway for the drain may be obtained by
using the Lacey's equation, given by

P=4.75√Q
where P = etted perimeter in metres
Q = Total discharge in cumecs.

 Then the width of the pier and bays is selected to achieve the desired drainage
water way.
Design of Canal Water way:

 The width of the canal is


flumed to the half of the
normal width.

 A splay of 2:1(H:V) in
contraction zone is provided.

 A splay of 3:1(H:V) in
expansion zone is provided.

 In transitions the side


slopes of the canal section will
be warped in plan from the
original slope to vertical.
Head loss and bed level at different sections:

Here we assume that the bed level of canal at section 4-4 is given.

At Section 4-4

 R.L. of water surface at 4-4 =


R.L. of bed at 4-4 + Depth of water
in canal

 R.L. of TEL at 4-4 = R.L. of water


surface at 4-4 + Velocity head

The known condition of 4-4 shall


now be utilised for finding the bed
levels etc. at 3-3.
At Section 3-3

 R.L. of TEL at 3-3 = R.L. of TEL at 4-4 + Loss in expansion

Loss in expansion = 0.3


where V4 = velocity at 4-4
V3 = velocity at 3-3

 R.L. of water surface at 3-3 = R.L. of TEL at 3-3 - Velocity head


 R.L. of bed at 3-3 = R.L. of water surface at 3-3 - Depth of water in canal
At section 2-2
From section 2-2 to 3-3 , the trough section is constant. Therefore, area and
velocity at 2-2 are the same as at 3-3. But from 2-2 to 3-3, there is a friction loss
between 2-2 and 3-3 which may be computed bt Manning’s Formula as equal to

 R.L. of TEL at 2-2 = R.L. of TEL at 3-3 + Friction loss


 R.L. of water surface at 2-2 = R.L. of TEL at 2-2 – Velocity head
 R.L. of bed at 3-3 = R.L. of water surface at 2-2 - Depth of water in canal
At section 1-1

Loss of head in contraction transition from 1-1 to 2-2,

= 0.2

 R.L. of TEL at 1-1 = R.L. of TEL at 2-2 + Loss in contraction


 R.L. of water surface at 1-1 = R.L. of TEL at 1-1 – Velocity head
 R.L. of bed at 1-1 = R.L. of water surface at 1-1 - Depth of water in canal
Design of Transitions

Since the depth is kept constant, the transition can be designed on the basis of
Mitra's Hyperbolic transition equation,

Where = width of transition


= normal width of canal
= flumed width of canal
= length of transition
= distance from 2-2 for contraction transition
= distance from 3-3 for expansion transition
5 Conclusion
 Cross drainage works are buildings built to allow canal water to cross another
drainage water.

 The construction transports the discharge from the natural stream through the
canal that intercepts it.

 These structures can also be used for navigation and in land transportation.

 Out of all the cross-drainage works , aqueducts are most common and used to
cross the canal over the drainage which may be natural or artificial.

Generally, cross drainage work is a costly structure. Hence, the most


economical structure is selected.
6 Reference
Websites:
 www.theconctructor.org
 civiljungle.com
 wikipedia.org
 aboutcivil.org

Books:
• Irrigation Engineering & Hydraulic Structures by S.K.Garg
• Irrigation And Water Power Engineering by B.C.Punima , Ashok Kumar Jain ,
Arun Kumar Jain , Pande Brij Basi Lal
Thank you

You might also like