0.

5
0.25
0.15
0.35 0
0

malisasi 75 m3
0
2613
20 2613 m2

alat
Keranjang 3 12,500 37,500
Bodem 1 75,000 75,000
Benang 4 7,500 30,000
Ganco 2 25,000 50,000
Kereta dorong 1 600,000 600,000
Mobilisasi 1 4,000,000 4,000,000
Wales 8-10 Ton 1.80 1,400,000 2,520,000
Mesin gilas 1 ton 2.00 520,000 1,040,000
8,352,500

Harga Satuan rekap kebutuhan

180,000 Batu belah 15/20 = 101.93 m3 18,403,468


91,000 Pasir urug = 22.00 m3 2,266,000
85,000 Pedel = 176.20 m3 14,536,500

Keranjang = 3.00 bh 37,500


123,000 Bodem = 1.00 bh 75,000
103,000 Benang = 4.00 rol 30,000
91,000 Ganco = 2.00 btg 50,000
85,000 Kereta dorong = 1.00 bh 600,000
1,400,000 Wales 8-10 ton = 1.80 hr 2,520,000
Mesin gilas 1 ton = 2.00 jam 1,040,000
Mobilisasi = 1.00 ls 4,000,000
82,500
91,000 Tukang = 13.00 org 1,183,000
85,000 Pekerja = 258.00 org 21,930,000
520,000
66,671,468
ops/Biaya Umum 2,725,000
82,500 69,396,468
91,000
85,000
36,000 Papan Proyek 1 bh 250,000.00
Prasasti 1 bh 200,000.00
2007-12 ATK 1 Paket 250,000.00
82,500 Materai 10 lbr 100,000.00
91,000 Makan Minum 1 Paket 750,000.00
85,000 Foto Copy + Penjilidan 1 Paket 200,000.00

85,000 Honor Ketua TPK 1 OP 350,000.00


Honor Sek TPK 1 OP 325,000.00
Honor Anggota TPK 1 OP 300,000.00

2,725,000.00
RENCANA ANGGARAN BIAYA
(RAB)
Provinsi : Jawa Timur No. RAB : 02
Kabupaten : Tuban Program : Dana Desa Th 2024
Kecamatan : Bancar Jenis Kegiatan : Jalan Usaha Tani
Desa : Tlogoagung/Tagean Volume : 2,5 x 250 m

Volume Jumlah
Harga Jumlah DD
Satuan Swadaya
No Uraian Total Swadaya DD Satuan (Rp) (Rp)
(Rp)
a b c=a-b d e f=bxe g=cxe
I. BOP
1 Operasional 1.0 - 1.0 LS 2,725,000 - 2,725,000
Sub Total 1) - 2,725,000
II. BAHAN
1 Batu Brongkol 101.93 - 101.93 m3 180,000 - 18,347,400
2 Pasir Urug 22.00 - 22.00 m3 103,000 - 2,266,000
3 Pedel 176.20 - 176.20 m3 82,500 - 14,536,500

Sub Total 2) - 35,149,900


III. ALAT
1 Keranjang 3.0 - 3.0 bh 12,500 - 37,500
2 Bodem 3.0 - 3.0 bh 75,000 - 225,000
3 Benang 2.0 - 2.0 Rol 7,500 - 15,000
4 Ganco 1.0 - 1.0 bh 25,000 - 25,000
5 Kereta dorong 1.0 1.0 bh 600,000 - 600,000
6 Waless 8-10 ton 1.8 1.8 hr 1,400,000 - 2,520,000
7 Mesin gilas 1 ton 2.0 2.0 jam 520,000 - 1,040,000
8 Mobilisasi 1.0 1.0 ls 4,000,000 - 4,000,000

Sub Total 3) - 8,462,500


IV. UPAH
1 Tukang 13.0 - 13.0 HOK 91,000 - 1,183,000
2 Pekerja 258.0 - 258.0 HOK 85,000 - 21,930,000

Sub Total 4) - 23,113,000


Biaya dari DD 69,450,400
Sumber Dana Swadaya -
Total Biaya( DD + Swadaya) 69,450,400

Tlogoagung, 30 September 2023

Pj. KEPALA DESA KETUA TPK


MULYADI MASRONI
U
PEMERINTAH KABUPATEN TUBAN

KECAMATAN BANCAR

DESA TLOGOAGUNG

Keterngan : NAMA KEGIATAN

= Masjid Tagean PEMBANGUNAN JALAN USAHA


TANI DANA DESA
KABUPATEN
TUBAN TAHUN
= Lokasi Saluran Air 2024

= Pos Kampling LOKASI KEGIATAN

DUSUN TAGEAN
KECAMATAN BANCAR
KABUPATEN TUBAN

PETA SITUASI GAMBAR :


Tanpa Skala - PETA SITUASI
Batu Tepi
Panjang : 57 m Ordelag MENGETAHUI
KEPALA DESA TLOGOAGUNG

MULYADI

KETUA TPK
DESA TLOGOAGUNG

0,25 m 2,50 m ' 0,25 m ' 0.5


DETAIL JALAN MASRONI
0.5 ' m'
m ' 6% - 8% 4% 4% 0,3
Tanpa Skala
6% - 8%

0,35 0,35
PEMERINTAH KABUPATEN TUBAN

KECAMATAN BANCAR

DESA TLOGOAGUNG

NAMA KEGIATAN

PEMBANGUNAN JALAN USAHA


ANI DANA DESA
KABUPATEN
UBAN TAHUN
2024

LOKASI KEGIATAN

DUSUN TAGEAN
KECAMATAN BANCAR
KABUPATEN TUBAN

GAMBAR :
- PETA SITUASI

MENGETAHUI
KEPALA DESA TLOGOAGUNG

MULYADI

KETUA TPK
DESA TLOGOAGUNG

MASRONI