GAMBAR PFK RANDOMAYANG

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

INSERT

Skala 100 m

Tiang beton 13 mtr 350 daN = - btg


Tiang besi 12 mtr 200 daN = 38 btg
Tiang besi 11 mtr 200 daN (E) E = - btg
Tiang besi 9 mtr 200 daN (T.bnt TM) = 5 btg
Tiang besi 9 mtr 200 daN (T.bnt TR) = - btg

A3C-S 3 x 70 mm² = 1.79 KmS


A3C-S 3 x 150 mm² = - Kms
Tumpu Tunggal = 19 Set
Tumpu Ganda = 15 Set
KEBUN SAWIT Aspan Ganda = - Set
Aspan Ganda T.U. = 1 Set
2 x Aspan Ganda T.U = 2 Set
Aspan Type H = - Set
2atu Tupang Tarik = 11 Set
Tupang Tarik Khusus = 4 Set
T1 Tupang Tarik T. Bantu = 5 Set

T2 GD 3 phs 25 kVA = - bh
2atu
GD 3 phs 50 kVA = 1 bh
GD 3 phs 100 kVA = - bh
T1

T2
LVTC 3 x 35 +25 mm² DT = - Kms
LVTC 3 x 35 +25 mm² TT = 0.48 kms
LVTC 3 x 70 +25 mm² DT = - kms
LVTC 3 x 70 +25 mm² TT = - kms
Small Angle Assembly SA = 3 set
Large Angle Assembly LA = 5 set
Dead End Assembly DE = 4 set
Pentanahn Biasa = 2 bh
Pentanahn Type E E = - bh
Tupang Tarik = 2 set
Tupang Tarik T.Bantu = - set

PARAF TANGGAL KETERANAGAN:

Tiang Beton Existing


DIGAMBAR
JTM Existing
PEKERJAAN PEMINDAHAN TIANG
JTR Existing
DIPERIKSA
TAMBAK RANDOMAYANG
No. Lembar : 1/1

DISETUJUI Tanggal : 17 Januari 2023