Ref. No.

eo(ERr)/k0cpleterso25|49 ;Dteli-24lofasa
To,
The Staff Officer (E&M),
Rajrappa Area.
Subject: Un-availability of suficient no. of pumps due to non-return of freshly supplied 02 nos. of
2000 GPM pumps sent to M/sGRW Pumps Pvt. Ltd.
References:
1. Contract no.:
GEMC-511687754470175 dtd. 30.08.2023
2. GM(E&M)/transfer/24/1047-52(H) dtd. 22.02.2024 (Bare Pump 540 Cum/hr, 150 mtr. Head)
3. GM (E&M)/transfer/24/1151-54(H) dtd. 28.02.2024 (540 Cum/hr Pump set with electricals)
4. Gate Pass No. 009147 dtd. 15.05.2024

Dear Sir,
Three nos. of 2000 GPM Pumps were procured against survey off for Rajrappa Project out of
which 02 nos. of 2000 GPM pumps are received at RajrappaProject and one no. 2000 GPM pump given
to Argada Area on loan basis for 03 months on dated 28.02.2024. The above referred 02 nos. 2000
GPM Pumps, 150 mtr. head, Type- GHSK, having S. No.- HS-2555 & HS-2552 were procured and
supplied (as per above mentioned contract no.) by M/s GRW Pumps Pvt. Ltd. in the month of February,
2024 but no personnel or representative of M/s GRW PUMPS PRIVATE LIMITED, Kolkata- 700075
(Email id: sales@grwpumps.com, Mob. No.: 9831224076) has visited the site for the commissioning of
supplied pump sets even after several telephonic request and emailcorrespondence.
Also, the Supplied Bare Pump having SI. No.- HS-2552 on physical inspection, it is found that
itslower body of pump is defective thus it needed tobe replaced/ changed.
Since after several request, no one from the GRW has visited the site, so, we decided to start
the pump departmentally having vide Sl. No. - HS-2555, but soon after starting, it is observed that it is
taking more than rated current and also there is abnormal sound from the pump body. Therefore,we
stopped it and then installed another Pump of same Make and Model vide SI. No. - HS-2552 but similar
things observed for this pump also. As both the pumps are under Guarantee/ Warrantee period,
hence, we again communicated with M/s GRW PUMPS PRIVATE LIMITED representatives and stated all
the issues we are facing.
On 04.05.2024, two representatives of M/s GRW PUMPS PRIVATE LIMITED visited the site to
review the above issues and ajoint observation made is as under:
SI. No. PUMP SI. No. Observation
1 HS-2552 Cast Iron impellers found in place of Bronze impellers.
2 HS-2552 Lower Bodyof the Supplied Pump is found defective.
3 HS-2552 & HS-2555 NDE side bearings of both the pumps found damaged.
4 HS-2552 & HS-2555
Too much heating on Bearing Housing at NDE side while
running,
5 HS-2552 & HS-2555 More than 02 inch horizontal Play in the Shaft of Pumps.
6
Impeller damaged and its edges became sharp due very high
HS-2555 wear & tear, as it was in contact with inner
body while
running due to shaft horizontal play.
After the visit and interference of the
competent authority, it was mutually decided that they
willcollect the pump from the site and deliver it
after rectification of allthe issues. So, that Pump can
be operated in safe and healthy condition.
Hence, on 15.05.2024, two representatives of M/sGRW PUMPS
pump and assured us that they have all the necessary spares and
PRIVATE LIMITED received the
its rectification will not accessories available with them and
take more than a week or two.
But it's been past more than 30 days since they have
no information is provided by M/s GRWN Pumps collected the pumps from the site but yet
Pvt. Ltd. about both the pumps sent to them. Tilldate
they have neither returned the
As the Monsoon 2024 is about to come pumps, nor responding to any correspondence.
and we are fully dependent on these two
2000 GPM) for dewatering of monsoon water from pumps (of
the mines. Henceforth, please arrange to
two nos. of 2000 GPM Pump (or equivalent) either provide
from M/s GRW PUMPS PRIVATE LIMITED or from
any other source within a week to prevent from any
loss of machines and
Currently, we are in deficiency of 02 nos. Of 2000 GPM pump for productivity in the mine.
monsoon. Therefore, Irequest you to take suitable action to availtwo dewatering during upcoming
nos. of 2000 GPM pumps.

Kindly take the action on urgent basis.

Project Engineer (E&M),


Rajrappa Project.