Professional Documents
Culture Documents
Zero Incident Program No.5
Zero Incident Program No.5
Table of Contents
I. Situationer
II. Program
1|Page
DocuSign Envelope ID: 17FB6E94-7AD5-41EF-8CC1-712208A840DE
I. Situationer:
Injuries caused by lifting incident can be life threatening. Lifting incident could affect anyone including the
public that can lead to injuries, loss time incident or fatality. It can also cause property damage inside the
project or public property. Lifting incident still rank as one the most common accident in the construction
Lifting incident accounts to a total of 59 incidents recorded from 2019 to 2021, 47% from struck by
object with breakdown as shown on the graph below
Brief Description:
A 210cm length x 13cm width aluminum beam weighing approximately 5kg fell from a height
approximately 8meters onto the back of victim’s head, breaking his hard hat and causing major
head trauma and bleeding
Contributory Factors:
Lifting procedure was not followed (ensuring no person/workers below the load during
operation)
Pre-lift were not performed to check stability of load or loose materials
Pre-assembled formwork was not in compliance with the approved methods drawing
Pre-use inspection / checks were not performed
Task Launch Meeting was conducted but not all key person / involved in the activity
attended
2|Page
DocuSign Envelope ID: 17FB6E94-7AD5-41EF-8CC1-712208A840DE
Incident no. 2
Brief Description:
Rebar cage with 2.3 meter diameter and 15 meter length was being lifted for splicing when 1 of 4-
leg lifting cable attached to the spreader bar got detached after weld of the stiffener ring loosened
from main bar. Crane operator immediately laid down the cage towards the direction of the
sudden swing hitting the fence and telecom cables along Cavitex.
Contributory Factors:
Quality of welding for stiffener not properly check prior to lifting
No documented inspection conducted by QA/QC personnel prior to installation
No clear location for installation of lifting gears during rebar cage insertion in method
statement
Incident no. 3
Brief Description
At around 2143H, after cleaning of tremie pipe (removal of hardened concrete inside the pipe)
that while lifted to lean on ground, pipe was detached in lifting chain. Unfortunately, rigger
assisting was struck initially his shoulder but mainly on his upper thigh left body part.
Contributroy Factors:
Used defecticve lifting chain sling
Chain sling wrapped around the tremie pipe instead of using a threaded puller
Inadequate risk assessment to the activity
Activity not properly coordinated and lack of supervision
C. Existing Requirements
Based on existing EHS Guidelines and procedures, there are provisions that are intended to
prevent accident involving lifting as specified in the following:
Each project shall incorporate in Project Execution Plan (PEP) the detail of plan for
protection of public and adjacent property during construction and demolition.
For areas commonly use or shared with public and when constructing temporary
structures intended for protection of public, coordination with LGU and other
concerned officials must be made and if required, secure necessary permits. Also,
necessary traffic management materials such as, but not limited to: Hard Barriers,
blinkers, rope lights, signage’s, including designated traffic enforcers must be
prepared/assigned to.
Net/screen shall be provided from the upper most part of the construction/ demolition
to ground level when the horizontal distance between the outermost face of the
building and the outer edge of the sidewalk is less than one-half (1/2) of the height of
the building (National Building Code Rule XI section 1106 no.4h ).
100% supervision by competent or technical people will be upheld during execution
of these activities to reduce imminent danger situation for public or by passer during
Construction
4|Page
DocuSign Envelope ID: 17FB6E94-7AD5-41EF-8CC1-712208A840DE
b) EHS Bulletin
c) Work Methodology
A system of practices, techniques, procedures, and rules used by those who work in a
discipline. Different methodologies have different strategies that aid in managing issues
should they arise during the project's delivery
Required in WAS/WAT, PEP, list of basic EHS requirements during kick off meeting with
subcon
Prepared by process owner, reviewed and approved by project team
d) Implementation Status
EHS Initiatives monitoring statistics related to lifting incident
5|Page
DocuSign Envelope ID: 17FB6E94-7AD5-41EF-8CC1-712208A840DE
II. Program
Elimination
The process of removing the hazard from the workplace. It is the most effective way to
control a risk because the hazard is no longer present. It is the preferred way to control a
hazard and should be use whenever possible
Substitution
The second most effective hazard control, involves replacing something that produces a
hazard with something that does not produce a hazard or lowers the risk
Engineering
are strategies designed to protect workers from hazardous condition by placing a barrier
between the worker and the hazard. Methods that are built into the design of a plant,
equipment or process to minimize the hazard. A very reliable way to control human
exposures as long as the controls are designed, used and maintained properly. These do
not eliminate hazards but rather isolate people from hazards
Administrative
are training, procedure, policy, or shift designs that lessen the threat of a hazard to an
individual. Administrative controls typically change the behavior of people rather than
removing the actual hazard or providing PPE
6|Page
DocuSign Envelope ID: 17FB6E94-7AD5-41EF-8CC1-712208A840DE
the chemical or material. The least effective control because it only provide a barrier but
does not remove the hazard. (GL-01-EHS-008)
i. Engineering
are strategies designed to protect workers from hazardous condition by placing a barrier
between the worker and the hazard. Methods that are built into the design of a plant,
equipment or process to minimize the hazard. A very reliable way to control human
exposures as long as the controls are designed, used and maintained properly. These do
not eliminate hazards but rather isolate people from hazards
Maintain 100% load moment indicator (lmi) and anti-collision (as applicable)
ii. Administrative
are training, procedure, policy, or shift designs that lessen the threat of a hazard to an
individual. Administrative controls typically change the behavior of people rather than
removing the actual hazard or providing PPE
Note: Riggers must be wearing orange safety helmet with tagging on behind “RIGGER”
iv. Foreman/Leadman
Inspect workers and work area prior to start of work
Report any hazard in the work area
Conduct “Linis bago Alis” before and after the activity
Monitor and control the workers
Participate in risk assessment
Facilitate daily training
Supervise and coordinate all activities in their areas
To be the role model in promoting safety in the project
Do not allow activity to start or continue when any of approved and agreed
hazard controls are not implemented
Obtain and provide feedback as required or as necessary
v. Workers
Report all hazard in the work area (unsafe act, unsafe condition)
Follow instruction from the supervisor to comply with EHS requirements
Regular conduct housekeeping “Linis Bago Alis”
Participate in risk assessment discussion
Attend daily toolbox meeting
To be the role model in promoting Safety in the project
Do not start or continue activity when any of approved and agreed hazard
controls are not implemented
Obtain and provide feedback as required or as necessary
Training method
Power point presentation
Actual demo/Role playing
o Build confidence: Different on-site scenarios will be given to participants.
This will provide a safe environment to encounter these scenarios for the
first time, which builds confidence in team members that can help them in
their day-to-day roles.
o Creative problem-solving: This will give each participants the chance to
get some experience in handling difficult situations and in developing
creative problem-solving skills.
Schedule
Participants Facilitators Method/Venue September October November December
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
STO/
EHS Mngr/EHSO PPT/AVP
EHS Directors
Per OpCen Echo Training
EHS Mngr/EHSO
GM/PM/PIC/PS/EHS Supt PPT/AVP
Echo Training
Project Team EHSO/EHS Supt PPT/AVP
On-site role playing
Echo Training
Coop/Subcon PIC & Supv PIC/PS PPT/AVP
On-site role playing
Workers Foreman/Leadman On-site role playing
CLU
PD/PIC (Bootcamp) PPT/AVP c/o CLU
EHS Head/EHS Directors
D. Feedback Mechanism
A system to gather information about reactions to the program which is used as a basis for
improvement of workplace safety, It is a helpful tools to get the Supervisor and workers to tell
what they feel, what they have done well, and which areas they need to tighten up in order for
this program to be successful. Benefits of feedback are the folllowing;
It improve the situation or the person’s or organization performance
It promotes and ensure engagement of all concern
It evaluate the effectiveness of Zero Accident Program implementation.
It obtain ideas collectively from other departments for the improvement of the
program
It obtain the pulses of different individuals working on the project
All collected feedback shall be discussed and analyzed by Project Team for continual
improvement of the program
E. Compliance/Adoption Monitoring
100% Implementation of all committed applicable controls shall be regularly monitored every
month and reported through the implementation/adoption monitoring that would also be a
basis for
Concerned to act on deficiencies for immediate close out
Remind and reprimand those concerned accountable for the non-conformance
Reward and recognition of good performance
1 Compliant
0 Non compliant
NA Not applicable
F. Penalty/Sanction
This program provides specfic penatly and sanction stated in MDC Code of Discpipline and
DOLE approve CSHP EHS Violation. The violation includes
Class B: Minor Infractions (1st offense – Written warning, 2nd offense – 3 days
suspension, 3rd offense – 10 days suspension, 4th offense – Termination)
11 | P a g e
DocuSign Envelope ID: 17FB6E94-7AD5-41EF-8CC1-712208A840DE
Class C: Less Serious Infractions (1st offense – 3 days suspension, 2nd offense – 10
days suspension, 3rd offense – Termination)
Minor EHS Violations (1st Offense – Formal written warning, 2nd Offense – 3 days barred,
3rd Offense – 10 days barred, 4th Offense – permanently barred)
Less Serious EHS Violation (1st Offense – 3 days barred, 2nd Offense – 10 days barred,
3rd Offense – permanently barred)
12 | P a g e
DocuSign Envelope ID: 17FB6E94-7AD5-41EF-8CC1-712208A840DE
Minor EHS Violations (1st Offense – Formal written warning, 2nd Offense – 3 days barred,
3rd Offense – 10 days barred, 4th Offense – permanently barred)
Less Serious EHS Violation (1st Offense – 3 days barred, 2nd Offense – 10 days barred,
3rd Offense – permanently barred)
Section 4. Failure to maintain and perform proper Housekeeping, Maintenance and LINIS
BAGO ALIS.
Section 5. Not wearing prescribed PPE in PPE Zone and required special PPE for a
particular activity
Section 7. Using substandard, worn out or damage lifting gear.
Section 8. Lifting load without Tag Line.
Section 14. Deliberately throwing tools, materials that could result/ has resulted to
property damage &/ or personal injury.
Section 15. Work related incident resulting injury and property damage to public.
Section 17. Wilful violation of EHS Procedure, Guidelines and Policy that caused near
miss
Section 21. Performing activity in unsafe condition or in imminent danger
13 | P a g e
DocuSign Envelope ID: 17FB6E94-7AD5-41EF-8CC1-712208A840DE
To encourage group or individual to work safely through an incentive award program for
safe workplace performance.
To improve the "Safety Culture" of the organization by providing award to group or
individual.
To recognize the contribution of group or individual for having safety in the work place.
Performance evaluation merit
Rewards and recognition can be through corporate level, per COG, per OpCen, per
Project, per Group, per Individual which may create detailed criteria (eligibility,
nomination, selection, token/prize, etc)
14 | P a g e