RURAL INFRUSTRUCTURE DEVELOPMENT PROJECT IN EMERGING REGIONS (RIDEP )

WEEKLY WORK PROGRAM


DISTRICT - Trincomalee CONTRACT NO - SLP116/EP/RR/2020/01
CONTRACTOR NAME : NAZEEHA HARDWARE AND CONSTRUCTION DATE: 24.08.2020 - 30/09/2020

MAN POWER PLANT &


NO. Date DESCRIPTION OF WORK LOCATION PERSON OF INCHARGE MATERIAL REMARKS
SK U/SK EQUIPMENT

Along the Information & necessary


1 8/24/2020 Topo Surveying Work M.Gafoor (Surveyor) 2 4 Total Station N/A
Aathiyammankerni Road action of consultant

Along the Information & necessary


2 8/27/2020 Submission of Topo Surveying M.Gafoor (Surveyor) N/A N/A
Aathiyammankerni Road action of consultant

Along the Information & necessary


3 8/29/2020 Removal of Structural and Obstruction T.Jathavan (T.O) 1 2 JCB N/A
Aathiyammankerni Road action of consultant

Along the Information & necessary


4 8/29/2020 Existing Cross Section Survey M.Gafoor (Surveyor) 1 3 Auto Level N/A
Aathiyammankerni Road action of consultant

Along the Information & necessary


5 9/7/2020 Preparation and Submission of Cross Section M.Gafoor (Surveyor) N/A N/A
Aathiyammankerni Road action of consultant

Receive The Design Level And Approved IFC Along the Information & necessary
6 9/25/2020 N/A N/A
Drawing Aathiyammankerni Road action of consultant

Road Way Excavtaion for unsuitable soil and Along the Information & necessary
7 9/26/2020 T.Jathavan (T.O) 1 3 JCB N/A
spoil waste Aathiyammankerni Road action of consultant

………………………………………………………..……………… 22.08.2020, 09.00AM