Professional Documents
Culture Documents
TRANSFORMER_STABILITY_TEST_REPORT_TR_321
TRANSFORMER_STABILITY_TEST_REPORT_TR_321
TRANSFORMER_STABILITY_TEST_REPORT_TR_321
Prepared by
Ir Kamarul Ariffin Yahya
UPT-P27 Lead Electrical Engineer
P27 AMT Supervisor – Electrical
Page 1 of 17
1.0 Objective
The objective of this test is to verify the correct CT arrangement, cable connection and protection relay
setting for the following protections: 87T, 64REF, 50G SBEF for TR-321-C-02A, feeding from SB-321-C-01-
SP-11A to SB-321-D-02A.
Page 2 of 17
LREFPNDF1 | 64REF | dIoLo>(1)
DESCRIPTION PRIMARY VALUE I/U [pu/A/V TIME
Operation On
CT connection type Type 2
Operate value 5%xIn
Min. Operate Time 50
Page 3 of 17
4.0 Test 1: Verification of 87T stable, 64REF stable, 50G SBEF stable, 50N stable
1. VCB-SB-321-C-01-SP-11A rackout
2. Earth Switch SB-321-C-01-SP-11A open
3. VCB-SB-321-D-02-SP-01A closed
4. Earth Switch BUS-A SB-321-D-02-BB-A closed (simulating fault)
5. External 415Vac supply to cable section inside VCB compartment of SB-321-C-01-SP-11A
Bypass:
a. NER is bypass so that there is no limitation on earth fault current.
b. VCB-SB-321-C-01-SP-11A provided with temporary jumper to give closing permissive to
downstream.
c. VCB-SB-321-D-02-SP-01A bypass its mechanical interlock to make possible VCB close in service
position while Earth Switch Bus-A SB-321-D-02-BB-A closed
Page 4 of 17
4.1 Result: Measurement of ABB RET615
Page 5 of 17
4.3 Analysis fault current
Result: 87T stable since biased differential falls inside not operate zone.
Page 6 of 17
4.5 Analysis 64REF
As per RET615 measurement data, IoB-A = 0.0A. Since IoB < Is, as such 64REF stable.
50G SBEF is the 400/1 SBEF CT, installed at transformer star-point grounding; it is the measured Io for
the return earth fault current to power transformer (source).
50N is the 3P 2500/1 CT, correspond to the vector sum of 3P current on Incomer SB-321-D-01A; it is the
calculated Io due to unbalance of 3P current.
As per REF615 measurement data, Io-A = 12.9A. This due to small unbalance L1-L2-L3. The return earth
fault current to power transformer (source) is less than Is of both 50G SBEF and 50N. As such both 50G
SBEF and 50N stable.
Page 7 of 17
5.1 Test 2: Verification of 87T trip, 64REF stable
1. VCB-SB-321-C-01-SP-11A rackout
2. Earth Switch SB-321-C-01-SP-11A open
3. VCB-SB-321-D-02-SP-01A test position & open
4. Earth switch INC-A SB-321-D-02-SP-01A closed (simulating fault)
5. External 415Vac supply to cable section inside VCB compartment of SB-321-C-01-SP-11A
Bypass:
a. NER is bypass so that there is no limitation on earth fault current.
b. VCB-SB-321-C-01-SP-11A provided with temporary jumper to give closing permissive to
downstream.
Page 8 of 17
5.2 Result: RET615 fault recorder
Page 9 of 17
5.3 Analysis 87T
As per fault recorder, 3dI>T(1) which referring to 87T pick-up in 0mS since bias-differential current falls
inside operate zone, refer to graph below:
Page 10 of 17
6.1 Test 3: Verification of 87T stable, 64REF trip
1. VCB-SB-321-C-01-SP-11A is rackout
2. Earth Switch SB-321-C-01-SP-11A open
3. VCB-SB-321-D-02-SP-01A open
4. Temporary cable connected between L1-E in side cable compartment SB-321-D-02-SP-01A
(simulating fault)
5. Earth switch INC-A SB-321-D-02-SP-01A open
6. External 415Vac supply to cable section inside VCB compartment of SB-321-C-01-SP-11A
Bypass:
a. NER is bypass so that there is no limitation on earth fault current.
b. VCB-SB-321-C-01-SP-11A provided with temporary jumper to give closing permissive to
downstream.
Page 11 of 17
6.2 Result: RET615 fault recorder
Page 12 of 17
6.3 Analysis 87T
Such, 87T not pick-up since bias differential falls inside not operate zone, refer to graph below:
As per fault recorder, dIoLo>(1) which referring to Current IoB (64REF) pick-up in 15mS since 64REF
protection is set at 5%xIn = 125A.
50G SBEF protection by REF615 not pick-up since its Operated Delay Time is set at 1000mS; as such,
protection 64REF by RET615 will respond first.
50N protection by REF615 does not see any fault current since the simulated earth fault is located
before its CTs while VCB-SB-321-D-02-SP-01A is open condition, thus submission of Io equal to zero.
Page 13 of 17
7.1 Test 4: Verification of 87T stable, 64REF stable, 50G SBEF trip
1. VCB-SB-321-C-01-SP-11A is rackout
2. Earth Switch SB-321-C-01-SP-11A open
3. VCB-SB-321-D-02-SP-01A closed
4. Temporary cable connected between L1-E on busbar section inside VCU compartment at one of SB-
321-D-02-SP-01A Motor Feeder (simulating fault)
5. External 415Vac supply to cable section inside VCB compartment of SB-321-C-01-SP-11A
Bypass:
a. NER is bypass so that there is no limitation on earth fault current.
b. VCB-SB-321-C-01-SP-11A provided with temporary jumper to give closing permissive to
downstream.
c. 50N protection at REF615 SB-321-D-02-SP-01A set to OFF.
Page 14 of 17
7.2 Result: REF615 fault recorder
Page 15 of 17
7.3 Analysis:
As per fault recorder, Io>(2) which referring to Current Io (50G) pick-up in 984mS since 50G protection is
set at 0.05xIn = 20A @ DT 1000mS.
50G is the 400/1 SBEF CT, installed at transformer star-point grounding; it is the measured Io for the
return earth fault current to power transformer (source).
Also to note that from fault recorder, Current Io-Calc = 0.277xIn = 692.5A. Even though 50N time grading
is set at DT 700mS, this protection does not pick-up since it is purposely set to OFF for this test.
50N is the 3P 2500/1 CT, correspond to the vector sum of 3P current on Incomer SB-321-D-01A; it is the
calculated Io due to unbalance of 3P current.
Whenever both 50G protection ON and 50N protection ON, Io>(1) which referring to Current Io-Calc
(50N) pick-up in 689mS since 50N protection is set at 0.12xIn = 300A @ DT 700mS. Refer to fault
recorder below for the addition test being done to verify protection coordination between 50N and 50G:
Result of REF615 fault recorder (with 51G protection ON, 51N protection ON):
Page 16 of 17
8.0 Troubleshooting
Issue encounter: During performing 64REF unstable test for INC-A, both INC-A and INC-B 64REF pick-up.
This is a nuisance tripping for INC-B.
Analysis: On further checking, it is found-out that CT’s secondary wire having 2 point earthing. This
create a current flow path to both INC-A RET615 and INC-B RET615 whenever there is an earth fault at
one of the Power Transformer. This defeat the in-zone unit protection for a Power Transformer.
Rectification: One of the CT’s secondary wire earthing have been removed, which result successful in-
zone 64REF unstable test for INC-A.
Page 17 of 17