Professional Documents
Culture Documents
Site Requirement CRP 300_R01
Site Requirement CRP 300_R01
11/34
Original Issue Date 10/01/2018 Site Requirement for CRP 300
Revision No. 01
Valid Up to. 31/12/2024 External use
Plant Operator to
e Skilled 1 No.
Operate batching plant
Operator for Material
f Skilled 1 No.
Loader
6 Standard Weight For Calibration $$01
a Standard weight of 20 kg 60 Nos.
b Standard weight of 2 kg 2 Nos.
c Standard weight of 1 kg 2 Nos.
d Standard weight of 500 grams 2 Nos.
Activity to be Done with Plant Erection
Necessary safety requirements during plant Erection and Commissioning $$01
Slings and Lifting Belts should be in good condition.
Fire Extinguisher should be available at site
Suitable sign board should be available at site
Control Room
Control Cabin / Control Room Size 8 Feet X 6 Feet with glass window
Single phase 3 pin plug board (With Proper earthing provision)
Single phase 16 Amp point for A.C
Tube Light + A.C + Fan + PC + Printer + UPS (Ref: PC Specification Sheet)
Rubber mat for Control Panel. $$01
Civil Work
Foundation as Per layout Drawing.
RAMP for Aggregate. Bin
Cement Godown suitable as per your requirement
Water Tank
Underground / PVC water tank suitable capacity as per your requirement approx.20,000ltr
Water pipeline and connection till the plant