Professional Documents
Culture Documents
S Curve OKI PULP & PAPER MILL PROJECT
S Curve OKI PULP & PAPER MILL PROJECT
1 Civil Work & Building Facility Ls 1 Rp 2,482,787,873 7.01% 0.23% 0.23% 0.25% 0.42% 0.31% 0.31% 0.31% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34% 0.13%
96.65%
2 Factory Equipment and Mechanical & Electrical Ls 1 Rp 32,930,856,137 10.97% 1.00% 0.59% 0.59% 0.59% 0.59% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.54% 0.11%
Total Precast Factory & Equipment at Cilegon Rp 35,413,644,010 17.98% 0.23% 0.23% 1.25% 1.01% 0.90% 0.90% 0.90% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% 0.24% - - - - - - -
93.08%
E
B Precast Concrete Form Work
1 Steel formwork : column 750x750mm Set 1 1,806,921,100 Rp 1,806,921,100 0.917% 0.09% 0.55% 0.07% 0.07% 0.07% 0.07%
2 Steel formwork : column 1875/1500x750mm Set 1 3,353,049,600 Rp 3,353,049,600 1.702% 0.17% 1.02% 0.13% 0.13% 0.13% 0.13% 89.50%
3 Steel formwork R Beam 600x1000 mm Set 1 3,653,667,800 Rp 3,653,667,800 1.855% 0.19% 1.11% 0.19% 0.19% 0.19%
4 Steel formwork R Beam 1000/500x1000 mm Set 1 5,758,637,900 Rp 5,758,637,900 2.923% 0.29% 1.75% 0.29% 0.29% 0.29%
5 Steel formwork L Beam 650x1140 mm Set 1 7,528,303,000 Rp 7,528,303,000 3.821% 0.38% 2.29% 0.38% 0.38% 0.38%
6 Steel formwork Flat Slab 3990x250 mm L 45 m Set 1 5,758,637,900 Rp 5,758,637,900 2.923% 0.29% 1.75% 0.44% 0.44%
7 Steel formwork Wall Panel 3995x200 mm L 100 m Set 2 9,763,669,400 Rp 19,527,338,800 9.912% 0.99% 5.95% 1.49% 1.49% 85.93%
I
8 Steel formwork Double T Variable L 38 m Set 3 5,143,912,100 Rp 15,431,736,300 7.833% 0.78% 4.70% 1.18% 1.18%
9 Steel formwork Double T Typical L 100 m Set 1 7,733,211,500 Rp 7,733,211,500 3.925% 0.39% 2.36% 0.59% 0.59%
Total Precast Concrete Form Work Unit 12 Rp 70,551,503,900 35.81% 3.58% 1.57% 5.36% 8.11% 10.52% 4.75% 1.93% - -
82.36%
D
Column
C.1.1 Column Tipe 750 x 750 mm 79.25%
Sub Total Unit 177 Rp 2,813,164,000 1.428% 0.11% 0.11% 0.11% 0.11% 0.11% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13% 0.13%
73.22%
C.2.3 Rectangular Beam 1000 x 1000
Sub Total Unit 97 Rp 4,894,361,500 2.484% 0.19% 0.19% 0.19% 0.19% 0.19% 0.22% 0.22% 0.22% 0.22% 0.22% 0.22% 0.22%
Sub Total Unit 218 Rp 5,651,599,400 2.869% 0.22% 0.22% 0.22% 0.22% 0.22% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26% 0.26%
M
C.5 Flat Slab t = 250 mm
68.09%
Sub Total Unit 286 Rp 7,831,567,400 3.975% 0.30% 0.30% 0.30% 0.30% 0.30% 0.41% 0.41% 0.41% 0.41% 0.41% 0.41%
U
Sub Total Unit 110 Rp 9,830,647,900 4.990% 0.37% 0.37% 0.37% 0.37% 0.37% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45% 0.45%
62.26%
Total Precast Concrete Element Unit 1,918 Rp 65,784,509,800 33.39% 2.50% 2.50% 2.50% 2.50% 2.50% 2.98% 2.98% 2.98% 2.98% 2.98% 2.98% 2.98%
B
57.57%
D Embeded Accessories
D.1 Column
D.1.1 Column Tipe 750 x 750 mm
Sub Total Unit 177 Rp 1,709,948,700 0.868% 0.09% 0.52% 0.07% 0.07% 0.07% 0.07%
A
51.36%
D.1.3 Column Tipe 1875 x 750 mm
Sub Total Unit 40 Rp 1,981,916,000 1.006% 0.10% 0.60% 0.08% 0.08% 0.08% 0.08%
R
D.2.2 Rectangular Beam 1000 x 500
Sub Total Unit 18 Rp 11,055,600 0.006% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
A
Unit 0.07% 0.41% 0.05% 0.05% 0.05% 0.05%
Sub Total Unit 286 Rp 654,383,400 0.332% 0.03% 0.20% 0.02% 0.02% 0.02% 0.02%
K
D.7 Double Tee Roof
D.7.1 Double Tee Roof Variable High
Sub Total Unit 110 Rp 476,399,000 0.242% 0.02% 0.15% 0.02% 0.02% 0.02% 0.02%
Total Embeded Accesories Unit 1,918 Rp 15,167,761,100 7.70% 0.77% 4.62% 0.58% 0.58% 0.58% 0.58%
29.81%
E.4 12.41%
Ledger Beam 650 x 1140
Sub Total Unit 218 Rp 892,396,590 0.453% 11.53% 0.01% 0.01% 0.01% 0.01% 0.01% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
10.65%
E.5 Flat Slab t = 250 mm
9.77%
Sub Total Unit 286 Rp 1,138,978,350 0.578% 0.02% 0.02% 0.02% 0.02% 0.02% 0.08% 0.08% 0.08% 0.08% 0.08% 0.08%
8.87%
Sub Total Unit 538 Rp 2,363,254,980 1.200% 0.04% 0.04% 0.04% 0.04% 0.04% 0.17% 0.17% 0.17% 0.17% 0.17% 0.17%
6.30%
E.7 Double Tee Roof
5.29% 5.29% 5.29%
E.7.1 Double Tee Roof Variable High
Sub Total Unit 110 Rp 1,440,981,500 0.731% 0.02% 0.02% 0.02% 0.02% 0.02% 0.10% 0.10% 0.10% 0.10% 0.10% 0.10%
Total Delivery to Baung OKI Unit 1,918 Rp 10,082,581,190 5.12% 0.21% 0.21% 0.21% 0.21% 0.21% 0.68% 0.68% 0.68% 0.68% 0.68% 0.68%
0.46%
0.23%
CUMULATIVE MONTHLY PROGRESS PLAN ( % ) 0.23% 0.46% 5.29% 5.29% 5.29% 6.30% 7.97% 8.87% 9.77% 10.65% 11.53% 12.41% 13.29% 14.17% 15.05% 15.93% 23.00% 29.81% 39.38% 51.36% 57.57% 62.26% 65.50% 68.09% 70.66% 73.22% 76.15% 79.25% 82.36% 85.93% 89.50% 93.08% 96.65% 97.33% 98.01%
MONTHLY PROGRESS ACTUAL (%) 0.23% 0.23% 4.92% 0.00% 0.00% 0.93% 1.69%
CUMULATIVE MONTHLY PROGRESS ACTUAL ( % ) 0.23% 0.46% 5.38% 5.38% 5.38% 6.30% 7.99%
0.23% 5.15%
Feb-16
Bulan ke - 9
37
NOTE
02/29/16
s/d
03/06/16
100%
98.01%
97.33%
96.65%
93.08%
90%
89.50%
85.93%
82.36%
80%
79.25%
76.15%
70%
73.22%
70.66%
68.09%
65.50%
60%
62.26%
57.57%
50%
51.36%
40%
39.38%
30%
29.81%
23.00%
20%
15.93%
15.05%
14.17%
13.29%
2.41%
10%
0%
Bulan ke - 8
37
4.930%