Activity Start Date End Date

Team Formation 1/1/2022 1/5/2022


Old Rulebook study and Case study 1/6/2022 1/12/2022
Department Calculation 1/13/2022 1/19/2022
Final frame desingning 1/20/2022 1/31/2022
CAE and Component Designing 2/2/2022 2/10/2022
Market Survey & Sponsorship generation 3/1/2022 3/15/2022
Team Registration 1/30/2022 2/2/2022
Final Calculation 1/19/2022 2/10/2022
Design Optimization and assembly 2/13/2022 2/16/2022
New Rulebook study 1/9/2022 1/13/2022
B-plan and cost analysis 2/24/2022 3/10/2022
Preparation for virtual round 4/20/2022 4/24/2022
Virtual presentation 4/25/2022 4/25/2022
Material and Component Procurement 4/2/2022 4/15/2022
frame maufacturing 5/1/2022 5/7/2022
Knuckle and Wheel hub manufacturing 5/8/2022 5/10/2022
Steering Parts Manufacturing 5/11/2022 5/15/2022
Pedal Assembly manufacturing 5/16/2022 5/19/2022
Assembly of Chassis 5/20/2022 5/26/2022
Brake Assembly 5/27/2022 5/29/2022
Bodyworks and painting 5/30/2022 5/31/2022
College Level Technical Inspection 6/1/2022 6/1/2022
Testing (phase 1) 6/2/2022 6/12/2022
Transportation NA NA
Dynamic Round (IKR 2022) NA NA
Duration
5
7
7
12
9
16
4
23
4
5
17
5
1
14
7
3
5
4
7
3
2
1
11