Professional Documents
Culture Documents
[IABSE Symposium Report vol. 96 iss. 15] Jung, Doyoung_ Kim, Hando_ Baek, Yeongin_ Kim, Jaehong - Application of BIM to a Cable-stayed Bridge Construction (2009) [10.2749_222137809796068127] - libgen.li
[IABSE Symposium Report vol. 96 iss. 15] Jung, Doyoung_ Kim, Hando_ Baek, Yeongin_ Kim, Jaehong - Application of BIM to a Cable-stayed Bridge Construction (2009) [10.2749_222137809796068127] - libgen.li
Jaehong Kim
General manager
Daelim Industrial Co.
Seoul, Korea
kjh7906@daelim..co.kr
Summary
3D modeling and BIM technology are being used more and more in the construction industry. The
scope of this paper arose as we wondered how the general contractor can benefit from the use of 3D
models. Presented herewith is the application of BIM to an actual bridge now under construction in
Cheongpoong, Choongcheongbuk-Do. This constitutes the first application of BIM in Korea.
Virtual construction of the cable-stayed bridge was performed to visualize design and analyze
constructability and coordination problems and to integrate the bridge’s visualization, cost, and
schedule under location-based conditions with industry-specific solutions for 3D modeling. Two
hundred and ninety-two main 3D objects constituted the cable-stayed bridge, which is 442m long
with a main span of 327m. BIM application benefits such as clash detection, interdisciplinary
communication, and method-statement simulation have been confirmed. In addition, integration of
a 3D model, cost, and schedule is shown by comparing the measurements of different structures at a
specific time using 2 different construction sequencing scenarios and work breakdown structures
(WBS). It is possible to create dynamic graphics and effects and explore complete projects under
real-world conditions before they are constructed.
Keywords: building information modeling (BIM), 3D modeling, cable-stayed bridge, clash
detection, simulation, visualization, virtual construction
Case Study
The BIM application methods were applied to a cable-stayed bridge, Cheongpoong Bridge, now
under construction by Daelim. It is located in Chooncheongbuk-Do, Korea, crossing the Chung Ju
Lake. This bridge is the first steel-concrete hybrid cable-stayed bridge in Korea. It is 442m long
with a main span of 327m. Because the bridge is being built across an in-land lake with a depth of
over 40m, and because its variation throughout the year is high due to unpredictable rainfall, the
main span is supposed to be constructed by the member erection method and the free cantilever
method (FCM). All pieces of the main span are delivered through the side span, with a derrick crane
lifting and installing each component of the edge girder, cross beam, stringer, and PC slab. Since
this method is being tried for the first time, construction know-how is insufficient, and a series of
bottlenecks are expected. BIM application prior to actual construction is expected to be helpful.
General contractor BIM users are generally divided into two groups: (1) workers at the construction
site, and (2) the project management team at the head office.
1. This experiment performed clash detection, analyzed constructability, provided decision-making
and coordination support, and simulated the construction sequence by applying BIM’s 3D
visualization and simulation function at the construction site. Consequently, contractors can cut
construction costs by direct and ripple effects, as well as secure construction safety.
Fig. 1 : Clash Detection Fig. 2 : 2D dwg. Adjustment
2. Project management teams can improve the accuracy of earned value management and their
understanding of the current situation with visual connecting schedules and cost and visual
information together, which also contribute to the project performance.
- Data Date : October 20th, 2008 - Data Date : October 20th, 2008
- Cumulative Rate of Progress : 92.60% - Cumulative Rate of Progress : 95.97%
- Earned Value : $20,757,000 - Earned Value : $21,511,000
- Expected Completion Date : July 8th, 2009 - Expected Completion Date : June 10th, 2009
In conclusion, we obtained the desired result from the case study of the Cheongpoong Bridge, but
the construction industry’s working environment and education system are not yet set up to apply
BIM technology entirely. Since this research was carried out under the assumption of those
constraints mentioned above, the results are also limited.
As IT development grows faster and faster, it is clear that the working environment of construction
keep pace with it. Every party in the construction industry should be concerned about the newest
technology trends and make a constant effort to change and improve the process. Hereafter, based
on the research of BIM application throughout the life cycle of construction projects, BIM should
be systemized, with related education and environmental conditions continuously expanded.
Application of BIM to a Cable-stayed Bridge Construction
Jaehong Kim
General manager
Daelim Industrial Co.
Seoul, Korea
kjh7906@daelim..co.kr
Summary
3D modeling and BIM technology are being used more and more in the construction industry. The
scope of this paper arose as we wondered how the general contractor can benefit from the use of 3D
models. Presented herewith is the application of BIM to an actual bridge now under construction in
Cheongpoong, Choongcheongbuk-Do. This constitutes the first application of BIM in Korea.
Virtual construction of the cable-stayed bridge was performed to visualize design and analyze
constructability and coordination problems and to integrate the bridge’s visualization, cost, and
schedule under location-based conditions with industry-specific solutions for 3D modeling. Two
hundred and ninety-two main 3D objects constituted the cable-stayed bridge, which is 442m long
with a main span of 327m. BIM application benefits such as clash detection, interdisciplinary
communication, and method-statement simulation have been confirmed. In addition, integration of
a 3D model, cost, and schedule is shown by comparing the measurements of different structures at a
specific time using 2 different construction sequencing scenarios and work breakdown structures
(WBS). It is possible to create dynamic graphics and effects and explore complete projects under
real-world conditions before they are constructed.
Keywords: building information modeling (BIM), 3D modeling, cable-stayed bridge, clash
detection, simulation, visualization, virtual construction
1. Introduction
Recently, competition among construction project bidders has been very keen, causing construction
companies’ earnings to plummet. Contractors now test various project management methods to
potentially reduce cost. One of the newest technologies in use is Building Information Modeling
(BIM), which is of concern to both the academy and the industry. BIM refers to the process of
generating and managing building data during its life cycle, typically it using 3D, real-time,
dynamic building modeling software to increase productivity in building design and construction.
According to a 2004 National Institute of Standards and Technology (NIST) Report, costs of
inadequate interoperability by stakeholder group, by life-cycle phase were quantified as $15.8
billion for the U.S. capital facilities supply chain in 2002 (NIST, 2004). This means there are many
cost losses in the construction industry due to lack of information during a project’s life cycle. BIM
technology offers a solution to these problems, and it can be applied not only to building
construction but also to the construction of other infrastructures to improve project performance. So
far, BIM 3D modeling has not been applied as a total solution for integrating processes and
information in Korea, but it has been partially applied throughout a project’s life cycle to solve
specific problems (Kim, 2008).
Presented herewith is the application of BIM to an actual bridge now under construction
Cheongpoong, Choongcheongbuk-Do, representing the first time BIM has been used in Korea.
Virtual construction by 3D modeling of the cable-stayed bridge was performed during the actual
construction phase to visualize designs, analyze constructability and coordination among parties,
and integrate visualization, cost, and schedule under location-based conditions with industry-
specific solutions.
• Clash detection
The creation of 3D model • Analyzing constructability
• Decision-making
& coordination support
• Coordination between the 3D
modeler & general contractor • 3D visualization & simulation
• Adjustment 3Dmodel’s level of detail
according to abjective
according to objective
• Improving the accuracy of
earned value management
2D 3D
model
• Understanding the current
dwg. situation of the site
• 3D visual synchronized with
the cost and schedule
Application on
project management team
Fig. 1: BIM Applications for the General Contractors
3.1 3D modeling
The basic 3D modeling of the bridge was created by Revit Architecture of AutoDesk. It has two
main objectives: (1) global modeling, in which the objectives are simulation of construction
sequence and synchronization of schedule, cost, and visual information, and (2) local modeling, in
which the objectives are clash detection and constructability tests, including operation of equipment
tests.
In global modeling, the entire bridge is divided into pylons, piers, the side span, the main span, and
cables, with the level of each activity considered. A concrete placing unit divides the pylons, piers,
and side span, and each member models the main span and cable so that they can be put together
according to activity level and user’s preference. Local modeling even describes reinforcing bars
and equipment such as the derrick crane to discover potential clashes and check constructability.
Fig. 4 : Site Meeting using BIM tool Fig. 5 : Simulation of Construction Process
Figure 5 shows a simulation of an installation process of the main span derived from the discussion
using virtual reality (VR) technology. Virtools, VR software from the French company, Dassault
Systems, was used to create the virtual situation using the basic 3D model. A virtual experience of
the construction process guarantees constructability and safety, and improves workers’
understanding of the construction sequence.
- Data Date : October 20th, 2008 - Data Date : October 20th, 2008
- Cumulative Rate of Progress : 92.60% - Cumulative Rate of Progress : 95.97%
- Earned Value : $20,757,000 - Earned Value : $21,511,000
- Expected Completion Date : July 8th, 2009 - Expected Completion Date : June 10th, 2009
As shown in Table 1, the data date is set as October 20th, 2008. The prefabrication of Case 2
visually completes the main span construction, but the member erection method in Case 1 requires
4 more blocks for completion. The cumulative rate of progress in Case 2 is 3.4% higher, with an
expected earned value $754,000 higher than that of Case 1. In addition, the expected completion
date was advanced by a month.
4. Conclusion
This research focuses on the application of BIM in the construction phase of a cable-stayed bridge.
Possible BIM technologies are derived and tested on the actual bridge now under construction.
General contractor BIM users are generally divided into two groups: (1) workers at the construction
site, and (2) the project management team at the head office.
1. This experiment performed clash detection, analyzed constructability, provided decision-making
and coordination support, and simulated the construction sequence by applying BIM’s 3D
visualization and simulation function at the construction site. Consequently, contractors can cut
construction costs by direct and ripple effects, as well as secure construction safety.
2. Project management teams can improve the accuracy of earned value management and their
understanding of the current situation with visual connecting schedules and cost and visual
information together, which also contribute to the project performance.
In conclusion, we obtained the desired result from the case study of the Cheongpoong Bridge, but
the construction industry’s working environment and education system are not yet set up to apply
BIM technology entirely. Since this research was carried out under the assumption of those
constraints mentioned above, the results are also limited.
As IT development grows faster and faster, it is clear that the working environment of construction
keep pace with it. Every party in the construction industry should be concerned about the newest
technology trends and make a constant effort to change and improve the process. Hereafter, based
on the research of BIM application throughout the life cycle of construction projects, BIM should
be systemized, with related education and environmental conditions continuously expanded.
5. References
[1] NIST, Cost Analysis of Iadequate Interoperability in the U.S. Capital Facilities Industry: NIST
GCR 04-867, Gaithersburg, MD, USA, 2004
[2] Kim, J., “Architecture Progamming Phase and Building Information Modeling”, Korean
Journal of Architecture, Vol. 52, No. 6
[3] Choi, C., “BIM Application Strategy by Phase of the Project as a Future Technology”, Korean
Journal of Construction Management, Vol. 9, No. 4
[4] Kang, H, Lee, M., “The Develoment of Construction Business Integrated Model through Case
Studies of BIM”, Conference on Architecture of Korea, Vol. 27, No. 1