SoF_KC Field_A01_Working
SoF_KC Field_A01_Working
Statement of Fitness
Prepared Signature Reviewed Signature & Checked Signature & Approved Signature &
by & Date By Date By Date By Date
Sylvester Mahalingam Akinyemi Rotimi
ofoni Nadarajan Okeremi Adefarasin
1. BROWNFIELD/MODIFIED ASSET – KALAEKULE FIELD
Statement of Fitness is a necessary part of starting up any new facility or existing facility post
modification or upgrade. The items contained in the Statement of Fitness are not new, but the Statement
of Fitness provides a structure for formal sign off & therefore increases their visibility and accountability.
Its aim is to verify & confirm that:
a. Process safety risks have been identified and documented and are managed to ALARP.
b. Employees or contractors executing HSSE Critical Activities are competent and fit to work.
c. HSSE Critical Equipment meets its Technical Integrity requirements.
d. Design and construction of the facility meet the design and engineering requirements.
e. Procedures are in place to operate Kalaekule facility and HSSE Critical Equipment within its
Operational Limits.
f. Safety Critical Equipment (SCEs), SCE related Performance Standards (PSs) acceptance criteria
and Maintenance / Inspection Routines are identified.
Signed:
----------------------------------------, date,
Well Delivery Advisor: Happy Agbeyi
----------------------------------------, date,
Project Delivery Manager: Dr. Akinyemi Okeremi
----------------------------------------, date,
Production Operations Manager: Mahalingam Nadarajan
----------------------------------------, date,
Manager Director: Rotimi Adefarasin
a. Process safety risks have been identified and documented and are managed to ALARP - HSSE Cases in place & approved
ALARP demonstration including SIMOPS & MOPO HSSE Olusegun Bayode Depend on the readiness of HSE case
ALARP demonstration including (Operational HSSE Case) HSSE / Operations Segun Bayode Depend on the readiness of HSE case
Signed_Emergency
Emergency response plan HSSE Olusegun Bayode Completed Preparedness and Response
Plan Rev 0 (2).pdf
b. Employees or contractors executing HSSE Critical Activities are competent and fit to work
Personnel in HSSE Critical roles are passed fit for work e.g. Incident Yemi Okeremi/M. Plan to identify and train personnel in the
Commander for EWT and EPF operations i.e. Offshore Installation Manager Project / Operations Nadarajan offing
d. Procedures are in place to operate Kalaekule Facilities and HSSE Critical Equipment within its Operational Limits (Operations)
Anne Akwara
Well Start-up and Operating Procedure Document completed Wells / Operations /Happy Agbeyi /S. Completed but awaits final signoff
Kalaekule Wells Start-Up
Ofoni Procedure_A01.docx
Operations Management System in place / Updated (OMS) Operations Sylvester ofoni Completed
OML-72_Kalaekule
Field_OMS_A01.docx
EWT Operations and Maintenance Philosophy for Kalaekule Field in Place Operations
Sylvester
Completed
EWT_OPNS. & MAINT.
ofoni/Nadarajan PHILOPHY_A01.docx
e. Procedures are in place to operate HSSE Critical Equipment within its Operational Limits (Maintenance Management Systems)
WAEP Subsea Asset (Equipment) register has been built using excel sheet Maintenance & Silas Dagyeng Built but need to be updated Signed Subsea_PIPELINE
and SCEs classified Integrity
IDENTIFICATION -
M. Nadarajan/S.
Staff in HSSE Critical positions trained Operations ‘’On-the-Job training’’ at advance stage
Ofoni
Y. Okeremi/ K.
Mechanical completion of all Topside hardware/equipment on Kalaekule Adebayo/T. Not required for EWT but required for
Flare Platform i.e. KCVJ-A Project Engineering Commingling stage (EPF)
Olarinoye / Eloka
Anyosa
SLB: Mechanical completion of all SLB equipment on the SEWOP Process Segun Oyebanji Work in progress
Engineering
Process Segun Oyebanji / To be carried out after staging completion
SLB: Pre-commissioning of all staged equipment on the SEWOP Engineering / S. Ofoni offshore
Operations
g. Permits and Certificates
Mathias
Life Extension Certificates (covering inspection of underwater and topside Project Onosemuode / Vendors inspection reports available
STRUCTURAL
structures of KCDP-A/B and KCPP-A & KCVJ-A) Management INSPECTION
Ehiaghe Caulcrick
Flaring Permits HSSE Olusegun Bayode Renewal is in progress
EWT Permits HSSE Olusegun Bayode Renewal is in progress