Kalaekule Field

WEST AFRICAN EXPLORATION AND


PRODUCTION COMPANY LIMITED.

DOCUMENT NUMBER DATE REVISION

OM72-PCC-CHK-0001-R01 27/12/2023 A01

Statement of Fitness

RETURN CODE TICK SIGNATURE

A ACCEPTED- Do not resubmit unless document is modified:


Operations may proceed.

B ACCEPTED AS NOTED- Revise to incorporate comments &


resubmit: Operations may proceed.

C NOT ACCEPTED- Revise to incorporate comments and


resubmit: Operations must not proceed

D INFORMATION ONLY- No impact on program

Prepared Signature Reviewed Signature & Checked Signature & Approved Signature &
by & Date By Date By Date By Date
Sylvester Mahalingam Akinyemi Rotimi
ofoni Nadarajan Okeremi Adefarasin
1. BROWNFIELD/MODIFIED ASSET – KALAEKULE FIELD

Company: West African Exploration & Production Company Ltd


Facility: Kalaekule Field

Statement of Fitness is a necessary part of starting up any new facility or existing facility post
modification or upgrade. The items contained in the Statement of Fitness are not new, but the Statement
of Fitness provides a structure for formal sign off & therefore increases their visibility and accountability.
Its aim is to verify & confirm that:
a. Process safety risks have been identified and documented and are managed to ALARP.
b. Employees or contractors executing HSSE Critical Activities are competent and fit to work.
c. HSSE Critical Equipment meets its Technical Integrity requirements.
d. Design and construction of the facility meet the design and engineering requirements.
e. Procedures are in place to operate Kalaekule facility and HSSE Critical Equipment within its
Operational Limits.
f. Safety Critical Equipment (SCEs), SCE related Performance Standards (PSs) acceptance criteria
and Maintenance / Inspection Routines are identified.

The facility therefore meets the criteria necessary to introduce hydrocarbons.

Signed:

----------------------------------------, date,
Well Delivery Advisor: Happy Agbeyi

----------------------------------------, date,
Project Delivery Manager: Dr. Akinyemi Okeremi

----------------------------------------, date,
Production Operations Manager: Mahalingam Nadarajan

----------------------------------------, date,
Manager Director: Rotimi Adefarasin

Document Number: OM72-PCC-CHK-0001-R01 Rev: A01 Document Date: 27/12/2023 Page 2 of 7


Checklist for Statement of Fitness
Project Title: Kalaekule

Trafic Link to Evidents


Activity Description Discipline Action Party Remark/Status and Close out Plan
Light

a. Process safety risks have been identified and documented and are managed to ALARP - HSSE Cases in place & approved
ALARP demonstration including SIMOPS & MOPO HSSE Olusegun Bayode Depend on the readiness of HSE case
ALARP demonstration including (Operational HSSE Case) HSSE / Operations Segun Bayode Depend on the readiness of HSE case

HSSE / Process Olusegun Bayode /


HAZOP Action Close Out Report Action close in progress
Engineering Olusegun Oyebanji
Fire and Gas Study Report HSSE Olusegun Bayode Completed
HSSE & SP Risk Studies including HEMP + Bow Ties (or similar) & Fire
HSSE Olusegun Bayode Depend on the readiness of HSE case
and Explosion Assessment

Signed_Emergency
Emergency response plan HSSE Olusegun Bayode Completed Preparedness and Response
Plan Rev 0 (2).pdf
b. Employees or contractors executing HSSE Critical Activities are competent and fit to work

Yemi Okeremi / Available, to be finalize.


Operator Competence Assurance Plan with HSSE critical roles identified Project/Operations M. Nadarajan

Personnel in HSSE Critical roles are passed fit for work e.g. Incident Yemi Okeremi/M. Plan to identify and train personnel in the
Commander for EWT and EPF operations i.e. Offshore Installation Manager Project / Operations Nadarajan offing

c. HSSE Critical Equipment meets its Technical Integrity requirements

Workshop on this conducted but HSE


SCEs have been identified and documented, included in HSSE Case HSSE Olusegun Bayode
case is still pending

d. Procedures are in place to operate Kalaekule Facilities and HSSE Critical Equipment within its Operational Limits (Operations)

Signed_SLB DOS for


Process
SLB Start-up & Operating Procedures in place
Engineering
Olusegun Oyebanji Completed Extended Well Test
Opertion_(Approved).pdf
SLB Cause & Effect in place Instrumentation & Taiwo Olarinoye Cause & Effect in place SLB_WAEP EWT CAUSE
Control
AND EFFECT DIAGRAM
REV T.xls
SLB WT-Data Acquisition
Process
SLB Data Acquisition and Safety Control System in place
Engineering
Olusegun Oyebanji Completed and Conttol systems for
Kalaekule EWT (1).pdf

SLB PFD, P&ID and other drawings prepared and approved


Process
Olusegun Oyebanji Completed
SLB P&ID_Individual Well
Engineering Test PID.pdf

Well Handover Certificate completed Wells Happy Agbeyi Certificates completed


Well Handover Certificate
(1).pdf

Well Unloading and ramp up Plan/Procedure Document for KCDP-A


Production
Anne Akwara Completed
PETROLEUM
Technology ENGINEERING
Production
Well Unloading and ramp up Plan/Procedure Document for KCDP-B Anne Akwara KCDP-B is in progress
Technology

Anne Akwara
Well Start-up and Operating Procedure Document completed Wells / Operations /Happy Agbeyi /S. Completed but awaits final signoff
Kalaekule Wells Start-Up
Ofoni Procedure_A01.docx

Well & Reservoir Management Plan in place


Production
Anne Akwara Available but need approval
Kalaekule WFRM Plan 2022 -
Technology final.docx
Project Delivery
Provision of all Systems or Equipment operating manuals, Test certificates Yemi Okeremi/ Request made to vendors yet to be
and Engineering
and original manufacturer material safety data sheet (MSDS) Kehinde Adebayo provided
Manager

Operations Management System in place / Updated (OMS) Operations Sylvester ofoni Completed
OML-72_Kalaekule
Field_OMS_A01.docx

EWT Operations and Maintenance Philosophy for Kalaekule Field in Place Operations
Sylvester
Completed
EWT_OPNS. & MAINT.
ofoni/Nadarajan PHILOPHY_A01.docx
e. Procedures are in place to operate HSSE Critical Equipment within its Operational Limits (Maintenance Management Systems)

WAEP Subsea Asset (Equipment) register has been built using excel sheet Maintenance & Silas Dagyeng Built but need to be updated Signed Subsea_PIPELINE
and SCEs classified Integrity
IDENTIFICATION -

Document Number: OM72-PCC-CHK-0001-R01 Rev: A01 Document Date: 27/12/2023 Page 4 of 7


EQUIPMENT LIST.pdf
1.Asset Register_Kalaekule
Kehinde Adebayo/
WAEP topside Asset (Equipment) register has been built using excel sheet Maintenance & Taiwo Platform 1.xlsx
Built but need to be updated
and SCEs classified Integrity Olarinoye/Eloka
Anyosa
2. Asset Register_Kalaekule
wells & others 2.xlsx
SLB Asset (Equipment) register has been built using excel sheet and SCEs Maintenance &
Olusegun Oyebanji Completed
SLB EWT Equipment
classified Integrity Register List.pdf
Maintenance &
SLB Equipment data Sheets
Integrity
Olusegun Oyebanji Completed Equipment Data Sheet

Wells Integrity (Maintenance) Management Wells Happy Agbeyi Completed


Well Integrity Maintenance
Procedure_A01_2024.pdf
f. Modifications are complete and have been authorized as specified in Management of Change; * Applies to modifications or Brownfield works only

M. Nadarajan/S.
Staff in HSSE Critical positions trained Operations ‘’On-the-Job training’’ at advance stage
Ofoni

Management of Change Procedures in place Process Olusegun Oyebanji


Available but need to be progress for WAEP - Management of
Engineering approval Change Procedure_R01.docx
Y. Okeremi/ K.
Mechanical completion of all Topside hardware/equipment on Kalaekule Adebayo/T. Not required for EWT but required for
Platform A i.e. KCDP – A carried out Project Engineering Olarinoye / Eloka Commingling stage (EPF)
Anyosa
Y. Okeremi/ K.
Mechanical completion of all Topside hardware/equipment on Kalaekule Adebayo/T. Not required for EWT but required for
Platform B i.e. KCDP – B carried out Project Engineering Olarinoye / Eloka Commingling stage (EPF)
Anyosa
Y. Okeremi/ K.
Mechanical completion of all Topside hardware/equipment on Kalaekule Adebayo/T. Not required for EWT but required for
Production Platform i.e. KCPP-A Project Engineering Olarinoye / Eloka Commingling stage (EPF)
Anyosa

Y. Okeremi/ K.
Mechanical completion of all Topside hardware/equipment on Kalaekule Adebayo/T. Not required for EWT but required for
Flare Platform i.e. KCVJ-A Project Engineering Commingling stage (EPF)
Olarinoye / Eloka
Anyosa

Document Number: OM72-PCC-CHK-0001-R01 Rev: A01 Document Date: 27/12/2023 Page 5 of 7


Y. Okeremi/ K.
Adebayo/T.
Pre-commissioning and Commissioning of all Topside hardware/equipment Not required for EWT but required for
Project/Operations Olarinoye / Eloka
on Kalaekule Platform A i.e. KCDP – A, carried out Commingling stage (EPF)
Anyosa/S.
Ofoni/Nadarajan
Y. Okeremi/ K.
Adebayo/T.
Pre-commissioning and Commissioning of all Topside hardware/equipment Not required for EWT but required for
Project/Operations Olarinoye / Eloka
on Kalaekule Platform B i.e. KCDP – B carried out Commingling stage (EPF)
Anyosa/S.
Ofoni/Nadarajan
Y. Okeremi/ K.
Adebayo/T.
Pre-commissioning and Commissioning of all Topside hardware/equipment Not required for EWT but required for
Project/Operations Olarinoye / Eloka
on Kalaekule Production Platform A i.e. KCPP – A carried out Commingling stage (EPF)
Anyosa/S.
Ofoni/Nadarajan
Y. Okeremi/ K.
Adebayo/T.
Pre-commissioning and Commissioning of all Topside hardware/equipment Not required for EWT but required for
Project/Operations Olarinoye / Eloka
on Kalaekule Flare Platform i.e. KCVJ - A carried out Commingling stage (EPF)
Anyosa/S.
Ofoni/Nadarajan
Mechanical completion of all Subsurface (SURF) hardware/equipment on Silas Dagyeng/ Not required for EWT but required for
Kalaekule Field carried out. (KCDP-A/B, KCPP-A and KCVJ-A SURF Engineering Eloka Anyosa Commingling stage (EPF)
Pre-commissioning of all Subsurface (SURF) hardware/equipment on Silas Dagyeng/ Not required for EWT but required for
Kalaekule Field carried out. (KCDP-A/B, KCPP-A and KCVJ-A SURF Engineering Eloka Anyosa Commingling stage (EPF)

SLB: Mechanical completion of all SLB equipment on the SEWOP Process Segun Oyebanji Work in progress
Engineering
Process Segun Oyebanji / To be carried out after staging completion
SLB: Pre-commissioning of all staged equipment on the SEWOP Engineering / S. Ofoni offshore
Operations
g. Permits and Certificates
Mathias
Life Extension Certificates (covering inspection of underwater and topside Project Onosemuode / Vendors inspection reports available
STRUCTURAL
structures of KCDP-A/B and KCPP-A & KCVJ-A) Management INSPECTION
Ehiaghe Caulcrick
Flaring Permits HSSE Olusegun Bayode Renewal is in progress
EWT Permits HSSE Olusegun Bayode Renewal is in progress

Document Number: OM72-PCC-CHK-0001-R01 Rev: A01 Document Date: 27/12/2023 Page 6 of 7


KEY:
Completed and Signoff In progress Not Started

Document Number: OM72-PCC-CHK-0001-R01 Rev: A01 Document Date: 27/12/2023 Page 7 of 7