The document describes requirements of site utilities for engine set ups purchased from Apex Innovations
General Computer
Foundation block Water supply
Engine exhaust Drain Water
Electric supply
Photograph Photograph
Put vertical round/square/rectangular pieces at a pitch distance of foundations bolts. The size of the
pocket should be about 125-150 mm.
Pour the concrete in to the pit. Ensure that the block height above the ground level is 150 mm.
Computer
Provide computer of standard configuration with DVD drive (for computerized engine test set up). The
computer should have minimum 2GB RAM and USB port for communication. The computer may need
to be formatted before installing engine testing software.
Separate cabin for computer is not recommended. The computer needs to be near Engine panel Box.
Drain Water
The Dynamometer cooling outlet water, Engine cooling outlet water and Calorimeter cooling outlet
water is collected in a 75 mm PVC pipe. The institute has to arrange 75 mm PVC pipe for taking this
drain water outside the lab.