Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 23

COST SUMERY OF G+2 BUILDING

ITEM DESCRIPTION OF WORKS AMOUNT


2 MAIN BULDING 7070292.30
3 SEPTIC TANK 75108.47
TOTAL 7,145,400.77
REMARK:- From this eastimation works 90% is existing building eastimated 6,430,860.69
ITEM DESCRIPTION OF WORKS AMOUNT
A. SUB STRUCTURE
1 EXCAVATION AND EARTH WORK 100648.88
2 CONCRETE WORK 1089972.46
3 MASONRY WORK 365307.38
SUB TOTAL "A" 1,555,928.72
B. SUPER STRUCTURE
1 Concrete Works 1975988.45
2 BLOCK WORK 324083.17
3 ROOFING WORK 126158.32
4 CARPENTARY & JOINARY WORK 208010.00
5 METAL WORK 306352.56
6 Finishing work 2240385.39
7 PAINTING WORK 54540.62
8 GLAZING WORK 107576.04
9 Sanitary installation 29756.26
10 Electrical Installation 141512.78
SUB TOTAL "B" 5,514,363.59
GRAND TOTAL "A" & "B" 7,070,292.30

SEPTIC TANK
ITEM DESCRIPTION OF WORKS AMOUNT
A. SUB STRUCTURE
1 EXCAVATION AND EARTH WORK 29919.70
2 CONCRETE WORK 34167.27
3 MASONRY WORK 11021.50
TOTAL 75,108.47
7,145,400.77
Item Description Unit Qty Unit Price Amount
A. Sub structure

1.Excavation and Earth Work

1.1 Clear the site to remove top soil to an average depth of 20 cm.

m2 174.97 14.75 2,580.81


Bulk excavation to a depth of 150cm from reduced ground level m3 95.60 98.33 9,400.35
1.2 Excavation trench foundation ,pit excavation to a depth of not exceeding 120cm starting from the reduced ground
level. m3 85.60 118.00 10,100.80
1.4 Backfill under hard core ,around foundation wall and footing colomun with selected materials & well compacted at
every 20 cm. select material /soil/from quary out of site/ m3 132.50 191.43 25,364.48
1.6
Cart away surplus excavated material and spread on a chosen site at a distance not exceeding 2 km from site. m3 185.62 170.61 31,668.63
1.7 Hard basaltic or equivalent stone hard core well rolled consolidated and blinded with crushed stone to a finished
thickness of 25 cm m2 165.20 130.35 21,533.82
Total Carried to Summary 100,648.88
2. Concrete Works
2.1 5cm thick lean concrete in class C-5 with minimum cement content of 150 kg/m 3 under footing
a) Under footing and grade beam m2 56.20 46.88 2,634.66
c) Under Masonry m2 32.50 46.88 1,523.60
2.2 Reinforced concrete in class C-25 with minimum cement content of 360 kg/ m 3 filled in to form work and vibrated
around steel reinforcement bar. (form work and reinforcement bar measured separately)
a. in foundation footings m3 28.62 2,333.84 66,794.50
b. in foundation column m3 8.42 2,333.84 19,650.93
c. in grade beam m3 18.56 2,333.84 43,316.07
d. 10 cm thick mass concrete floor slab. m2 165.20 183.38 30,294.38
2.3 Provide, cut and fix in position sawn zigba form work:
a. footing. m2 65.23 141.45 9,226.78
b. For foundation column m2 46.52 141.45 6,580.25
C. For grade beam m2 132.60 141.45 18,756.27
2.4 Steel reinforceent bars price includes cutting, bending, placing in position and tying wires according to structural
drawing.
a. Diam.6mm deformed bar Kg 4,395.12 47.91 210,570.20
b. Diam.8mm deformed bar Kg 3,265.20 46.15 150,688.98
c. Diam.12mm deformed bar Kg 3,465.00 46.15 159,909.75
c. Diam.14mm deformed bar
Kg 4,265.30 46.15 196,843.60
c. Diam.16mm deformed bar Kg 3,752.60 46.15 173,182.49
Total carried to summary 1,089,972.46
Item Description Unit Qty
3. MASONRY WORK
3.1 50cm thick roigh hard trachytic stone foundation masonry wall bedded in cement sand mortar mix of 1:4.
m3 215.60 1,017.32 219,334.19
3.2 Ditto as item 3.1 but semi-dressed stone masonry wall above N.G.L. up to grade beam & external side left for
pointing.(price includes pointing to external side of the wall with cement sand mortar of ratio 1:2) m3 132.42 1,102.35 145,973.19
Total carried to summary 365,307.38
B. SUPER STRUCTURE
1. Concrete Works
2.2 Reinforced concrete in class C-25 with minimum cement content of 360 kg/ m 3 filled in to form work and vibrated
around steel reinforcement bar. (form work and reinforcement bar measured separately)
b. in column m3 32.15 2,333.84 75,032.96
c. in beam m3 42.50 2,333.84 99,188.20
d. stair concrete m3 16.40 2,333.84 38,274.98
d. 15cm thick floor slab. m3 132.46 2,333.84 309,140.45
2.3 Provide, cut and fix in position sawn zigba form work:
b. in column m2 326.52 141.45 46,186.25

c. in beam m2 345.60 141.45 48,885.12


d. suspened slab. m2 420.12 209.83 88,153.78
d. stair concrete m2 56.20 209.83 11,792.45
Steel reinforceent bars price includes cutting, bending, placing in position and tying wires according to structural
2.4
drawing. 0.00
a. Diam.6mm deformed bar Kg 3,652.40 47.91 174,986.48
b. Diam.8mm deformed bar Kg 5,642.70 46.15 260,410.60
c. Diam.10mm deformed bar Kg 6,452.70 46.15 297,792.11
c. Diam.12mm deformed bar Kg 4,657.80 46.15 214,957.47
c. Diam.14mm deformed bar Kg 6,742.96 46.15 311,187.60
c. Diam.16mm deformed bar
Kg - 46.15 0.00

Total carried to summary 1,975,988.45


2. BLOCK WORK
2.1 20 cm thick class B .H.C.B wall bedded and jointed in cement and sand mortar 1:3 internal and external left for
plastering. m2 785.90 295.01 231,848.36
15cm thick class B .H.C.B wall bedded and jointed in cement and sand mortar 1:3 internal and external left for
plastering.

m2 425.30 216.87 92,234.81


Total carried to summary 324,083.17
3. ROOFING WORK
Roof covering in G-30 corrugated galavanized iron sheet including roof ridge cover fixed to purlins with dome
headed galvanized nails, purlin measured separetely and roof cover measured in horziontal projection m2 73.20 495.6 36,277.92
G-28 galvanized iron sheet metal gutter devolepment length 50 cm welded at joints. provide 2% slope towards
down pipe & shall include 3 coats of oil paint ml 132.56 365 48,384.40
Supply & fix diameter 110 mm P.V.C pipe for Down pipe fixed to wall with metal straps welded joints towards to
ground & shall inculds elbow & 3 coats oil paint.
ml 145.60 285 41,496.00

126,158.32
4. CARPENTARY& JOINARY WORK

All structural members shall be well seasoned and free of harmful defects. Each truss shall be painted anti- termite
solution and firmly fixed to R.C beams with Dia 6mm plain bars
Diametr 10-12 cm eucalyptus upper & lower, members of truss ml 425.00 80.00 34,000.00
Diametr 8-10cm eucalyptus vertical & diagonal truss member ml 265.00 80.00 21,200.00
5x7cm sawn Zigba ,Tsid or equvalant wooden purlins ml 245.00 450.00 110,250.00
Supply & fix 8mm thick chip wood ceiling nailed to price includes (4x5)cm Zigba,Tsid or equvalant wooden
battens at c/c 60cm on both side & 2*4 cm corner list & battens. ml 76.00 560.00 42,560.00
208,010.00
5-METAL WORK
supply and fix Main entrance Door made of vertical and horizontal frame (CHS)tube Diam 50 *1.5 mm thick and
(SHS ) tube 25x25x2mm c/c 15cm for vertical rows and for horzontal rows c/c 30 cm.price shall
include30*30*50cm excavation and c-15 concrete iron mongory,lock and with all accessories. (approved quality by
the engineer)
size300x260cm m2 7.80 4,560.00 35,568.00
supply and fix metal doors shall be fabricated from locally manufactured 3.8 *1.25 mm thicknes LTZ tubular steel
profile,left for glazing .including price c/c 15 cm vertical raws 20*20*1 mm SHS tube grill , hinges, cylindrical
locks ,one coats of antrust & two coats oil paint.,with all its accessories( material quality approved by the engineer)
m2 85.62 1,650.00 141,273.00
supply and fix metal window shall be fabricated from locally manufactured 3.8 *1.25 mm thicknes LTZ tubular
steel profile,left for glazing .including price c/c 15 cm vertical rows 20*20*1 mm SHS tube grill , hinges,
handle ,one coats of antrust & two coats oil paint.,with all its accessories( material quality approved by the m2 52.60 1,235.60 64,992.56
engineer)
supply and fix for stair case & verenda Hand rail & balustrad made of RHS tube 40*20*2 mm for
horizontal c/c 50 cm & vertical c/c 25 cm at the top hand rail 10*5*2.5 cm wood , inculding 3 coats oil paint
(approved quality by the engineer) m2 32.50 1,985.20 64,519.00
306,352.56
6 . Finishing work

6.2 Apply 3 coats of plastering cement sand mortar (1:3) up to fine finish to all indicated internal & external Hollow
m2
concrete block/HCB/ ,brick wall ,column,beam,linten,slab & stair case. 3,456.80 167.50 579,014.00
Apply Pointing to indicated external or internal stone masonry wall surface in cement mortar (1:3) m2 1,235.60 98 121,088.80
apply and lay 3cm cement screed with cement sand mortar m2 465.30 2658 1,236,767.40
Supply & lay 2.5 cm thick terazzo tile flooring class 'A' inculding bedded in cement sand mortar (1:3) ratio 652.30 465.3 303,515.19
2,240,385.39
6.5 7-PAINTING WORK
Apply 3 coats of approved type plastic paint to all indicated & external surface m2 745.60 33.6 25,052.16
Apply 3 coats of approved type syntheticpaint to all indicated internal surface m2 685.30 43.03 29,488.46
54,540.62
8- GLAZING WORK
5mm thick clear glass Cutting & fixing glazed to metal bends with putty m2 132.50 549.21 72,770.33
Skerting ml 178.50 194.99 34,805.72
Total carried to summary 107,576.04
Item Description Unit Qty
9.Sanitary installation
Supply & install galvanized steel pipes for cold and hot water distribution to all sanitary fixtures according to the
drawing, complete with the necessary connection pieces such as bends, unions, etc. unit price shall include all the
necessary assistance to the installation of works such as chiselling of walls, slabs, beam, floors, etc. & closing them
with concrete or cement mortar, to normal condition; & excavation , back fiil for out side the installation shall be
tested at a presure of 10kg/cm2 by the expense of the contractor.(approved quality by the engineer)

9.1
a) Diam. 1/2 inch ml 24.00 114.13 2,739.12
a) Diam. 3/4 inch ml 36.00 167.31 6,023.16
Supply and fix European made gate valve approved by the client. Price includes all accessories
a) Diam. 1/2 inch no 6.00 185.44 1,112.64
9.2 a) Diam. 3/4 inch no 6.00 273.01 1,638.06
Supply & fix diameter 110 mm P.V.C pipe for Down pipe fixed to wall with metal straps welded joints towards to
ground & shall inculds elbow & 3 coats oil paint.
- Dia. 110 mm ml 12.00 60.75 729.00
- Dia. 50 mm ml 12.00 28.59 343.08
Supply & fix PPR Chrome Valves complete with unions ,elastic water proofing &hand wheels all the necesssary
accessories no 4.00 307.44 1,229.76
Supply & fix hand wash basins made of white vitreous china equipped with consealed bracket made of grey
mallable cast iron white painted complets with plug chains and traps.(approved quality by the engineer) 0.00
Hand wash basin Size(500*405)mm no 4.00 734.17 2,936.68
Supply & fix Turkish with with all accessories no 4.00 478.38 1,913.52
Supply and instal shawer Tray units made of enamelled cast iron steel plate &fiber glass ,including complete with
all the accessories.(approved quality by the engineer) 0.00
Shower Tray steel Plate Complite Size 70*70Cm no 4.00 1329.71 5,318.84
Supply & fix Shower head made of metal type no 4.00 118.45 473.80
Supply & fix toilet paper holder including fastering screws and the necessary accessories (approved quality by the
engineer) no 4.00 255.31 1,021.24
Supply & fix soap holder including fastering screws and the necessary accessories(approved quality by the
engineer) no 4.00 240.09 960.36
Supply & fix standard towel hanger including fastering screws and the necessary accessories.(approved quality by
the engineer) no 4.00 288.20 1,152.80
Supply & fix glass mirror iincluding fastering screws and the necessary accessories.(approved quality by the
engineer) no 4.00 541.05 2,164.20
10.External sanitary installation
Total carried to summary 29,756.26
10. Electrical Installation
11.10 DISTRIBUTION BOARDS
LIGHT POINT
Supply & install light points fed through PVC insulated conductors of 3x2.5mm2 in thermoplastic conduits of dia -
13.5mm for recessed installation including junction boxes with covers (screw type) & insulating caps. no 26.00 986.37 25,645.62
SOCKET OUT LET & other POINT
Supply & install flush mounted socket outlet point of 16A, single phase & with earthing contact fed through PVC
insulated conductors of 3x2.5mm2 in the thermoplastic condits of dia 16mm for recessed installation including
junction boses with covers & insulating caps - all complete, no 26.00 837.53 21,775.78
11.2 SOCKET FITINGS(approved quality by the engineer) 0.00
Supply and fix Flush or Surface mounting socket twin outlet 16-25 A/1ph No 26.00 74.30 1,931.80
switch FITINGS(approved quality by the engineer) 0.00
Supply and fix flush or Surface mounted gange switch no 26.00 65.62 1,706.12
LIGHT POINT
a)PHILIPS TCs 098/2.36 +2x'TL'D36w P(w)=2x36w no 26.00 1370.21 35,625.46
11.11 Power Feeder Cable (Measurement is tentative. ) 0.00
4x6mm2 ml 252.00 164.00 41,328.00
DISTRIBUTION BOARDS
floor mounted factory assembled and tested electrical distribution board of metal enclosure ,with locable door of
hinged joints, including three phase bars of 50A rating with separate neutral and earthing bars ,connection and
mounting accessories to the MDB
6 pc ACB 10A, 1 phase
6 pc ACB 16A, 1 phase
2 pc ACB 20A, 3phase
3 pc ACB 25A, 3phase
25% RESERVE SPACES No 3.00 4,500.00 13,500.00
ne 3,500.00 0.00
Total carried to summary 141,512.78

SEPTIC TANK
A. Sub structure
1.Excavation and Earth Work
Bulk excavation to a depth of 150cm from reduced ground level m3 24.00 98.33 2,359.92
1.2 Excavation trench foundation ,pit excavation to a depth of not exceeding 120cm starting from the reduced ground
level. m3 19.20 118.00 2,265.60
1.3 Excavation trenches for foundation ,pit excavation to a depth from120 -220cm starting from the reduced ground
level. m3 16.00 147.50 2,360.00
Excavation trenches for foundation ,pit excavation to a depth from 220-300cm starting from the reduced ground
level. m3 13.60 196.67 2,674.71
1.4 Backfill under hard core ,around foundation wall and footing colomun with selected materials & well compacted at
every 20 cm. select material /soil/from quary out of site/ m3 40.95 191.43 7,839.06
1.6
Cart away surplus excavated material and spread on a chosen site at a distance not exceeding 2 km from site. m3 72.80 170.61 12,420.41
Total Carried to Summary 29,919.70
2. Concrete Works
2.1 5cm thick lean concrete in class C-5 with minimum cement content of 150 kg/m 3 under footing
c) Under Masonry m2 16.00 46.88 750.08
2.2 Reinforced concrete in class C-25 with minimum cement content of 360 kg/ m 3 filled in to form work and vibrated
around steel reinforcement bar. (form work and reinforcement bar measured separately)
c. in grade beam m3 2.65 2,333.84 6,184.68
d. 15 cm thick slab. M3 2.36 2,333.84 5,507.86
2.3 Provide, cut and fix in position sawn zigba form work:
c. in grade beam m2 13.45 141.45 1,902.50
d. 15 cm thick slab. m2 12.65 209.83 2,654.35
2.4 Steel reinforceent bars price includes cutting, bending, placing in position and tying wires according to structural
drawing.
a. Diam.8mm deformed bar Kg 85.60 46.15 3,950.44
b. Diam.12mm deformed bar Kg 165.80 46.15 7,651.67
c. Diam.14mm deformed bar Kg 120.60 46.15 5,565.69
Total carried to summary 34,167.27
Item Description Unit Qty
3. MASONRY WORK
3.1 50cm thick roigh hard trachytic stone foundation masonry wall bedded in cement sand mortar mix of 1:4.
m3 65.80 167.50 11,021.50
Total carried to summary 11,021.50
No L*W*D Qty Description No L*W*D Qty Description

A.SUB - STRUCTURE
1.excavation & earth work 25cm thick sound basaltic Hard Core

1 13.10 1.1 site clear 1 12.10

15.46 29.56 m2 14.46 174.97

1 12.10 1.1 Bulk excavation in ordinary soil

14.46 - 1.00

0.50 87.48 M3 Net Total 1.00 0.00

1.2 Excavate in ordinary soil for


trench foundation up to 120 174.97

2 12.10 ddt beam

0.50 trunch 1 43.38 total length of beam

1.20 14.52 0.25 10.85

2 13.46 2 23.2

0.50 0.25 11.60

1.20 16.15 pad 22.45

3 1.6 152.52 m2 total hard core

1.6 2.CONCRETE WORKS


1.20 9.22 M3 Net Total 2.1 50mm thick lean concrete in C-5
11 1.40 a) under footing pad
1.40 3 1.6 pad

1.20 25.87 1.6

3 3.20 7.68 M3 Net Total

1.60 11 1.40

1.20 18.43 1.40

84.19 21.56

Deduction For footing pad 3 3.20

21 1.20 1.60

0.50 15.36

1.00 12.60 44.60

71.59 M3 Net Total 1 13.96 b) under grade beam

1.5 Fill around footings and under


hardcore 0.25 3.49

Fill Around Footing 48.09 M2 Total

3 1.6 pad UNDER MASNRY WALL

1.6 1 53.12

1.20 9.22 M3 Net Total 0.50 26.56 M2 Total

11 1.40

1.40 2.2 Reinforced concrete in class C-25

1.20 25.87 a) footing

3 3.20 3 1.6 pad

1.60 1.6

1.20 18.43 0.40 3.07 M3 Net Total

53.52 11 1.40

Fill AROUND MASON 1.40

1 53.12 EXTERNAL SIDE 0.30 6.47

0.25 P=12.1*2+14.46*2 3 3.20

1.15 15.27 1.60

1 49.12 INTERNAL SIDE 0.40 6.14

0.25 15.68

1.15 14.12 15.68 M3 Net Total

29.39 M3 Net Total b) foundation column

Fill Under hard core 20 0.25 F1

1 11.10 0.25

13.46 D=ANGL0.3+BULK0.5=0.8 1.65 2.06 M3 TOTAL FC

0.50 74.70 c) grade beam

157.62 TOTAL FILL 1 104.64 P=14.46*3+4.75+0.25+3.86+0.25+12.1*4+3.75

Deduction 0.25

pad 0.30 7.85


3 1.6 F1 7.85 M2 TOTAL GB

1.6 d) 100mm thick mass concrete for ground floor

0.4 3.07 152.52 M2 Net Total

11 1.4 2.3 'Form Work

1.4 a) footing

0.3 6.47 3 6.4 pad

3 3.2 0.40 7.68 M3 Net Total


1.6 11 5.60

0.4 6.14 0.30 18.48

20 0.25 For Column 3 9.60

0.25 D=ANGL0.3+BULK0.5+ PIT EXN 1-0.25PAD=1.55 0.40 11.52


1.65 2.06 Sub Total 37.68

Deduction For masnory 37.68 M3 Net Total

20 1.20 FOOTING COLOMUN

0.50 20 1.00 F1

1.15 13.80 1.65 33.00 M2

31.55 M3 Total Deduction c) grade beam

126.07 TOTAL FILL external side

1.6 Cart away & spread surplus excavated 2 104.64 p=113.1

5.91 For site clear 0.30 62.78

87.48 For bulk Excavation - ddt footing colomun only from external

71.59 For Trench Excavation 0.00

164.99 M3 Total cart awey 62.78 M2 TOTAL GB


No L*W*D Qty Description No L*W*D Qty Description
3. MASONRY WORKS form work

A) below NGL from the reduced level from Ground - G+1

2 65.58 2 104.64 p=120.45

0.50 2 0.40 167.42 M2 TOTAL

1.15 75.42 slab

75.42 total 1 12.10

ddt footing colomun 2 10.10 244.42

20 0.25 F1 & F2 1 4.50 12.1

0.25 1 4.20 18.90 14.46

1.15 1.44 2 104.64 sofit beam 174.966

73.98 M2 0.30 62.78 349.932

A) ANGL from the reduced level 326.10 m3

2 65.58 STAIR 19.95

0.50 2 2.00 landing & flight 329.982

0.30 19.67 1 1.00 4

19.67 total 18 A=1*2B*H

ddt footing colomun 2 0.02 0.81

20 0.25 F1 & F2 4.81 M2

0.25 masnory work

0.30 0.38 1 99.36 HCB 20

19.30 M2 2.70 268.27 G+0-G+1

SUPER STRUCTUE from G+0- G1

ELRVATION COLOMUN 268.27 m2

20 0.25 from Ground - G+1 DDT

2 0.25 DOOR

2.70 6.75 m3 0.00 M2

intermdet beam beam 268.27 HCB 20

1 104.64 from Ground - G+1 HCB 15

2 0.25 1 80.00 GROUND

0.30 15.70 M2 TOTAL 2.7 216.00 M2

STAIR G+0-G+1

1 2.00 landing & flight 55.71 P=55.71

2 1.00 2.6 0.00

0.15 1 216.00 HCB 15


16 0.02 A=1*2B*H ROOFING WORK

2 2.00 1.44 10.2 G-30

2.04 M3 19 0 M2

6.55
slab 4.35 0

1 12.10 0.00 m2

2 10.91 gutter

0.15 39.60

1 4.65 78 0.00 douwn pipe 110

2 5.45 dia 12-10 equliptos

0.15 7.60 10.2 0.00 truss

47.21 m3

10.2 0.00 dia 10-8 equliptos


form work 19 0.00 purlin 7*5

ELRVATIO COLOMUN 6.55 0.00

20 1.00 from Ground - G+1 0.00 ml

2 2.70 chipwood

108.00 m3 same with hard core

152.52 m2
No L*W*D Qty Description No L*W*D Qty Description

METAL WORK sanitery work

DOOR GSP

1 6.1 for EXTERNAL DOOR 36.00 25mm (3/4')

2.7 16.47 24.00 20mm (1/2')

1 3 for kanshelo 12.00 pvc 110mm

2.6 7.8 12.00 pvc 50mm

7.80 m2 total GET VALVES

1 7.5 for INTERNAL DOOR & toilet 6.00 1/2

2.7 20.25 6.00 3/4

1 4.4 WIDOW 4.00 CROW GET CETVALVE 1/2

1.8 7.92 4.00 HAND WASH

G+1 4.00 TURCKSH

DOOR 4.00 SHOWER TREYY

1 10.1 for bed room 4.00 shwer head

1 2.6 26.26 4.00 PAPER HOLDER

WIDOW 4.00 SOAP HOLDER

1.00 10.8 4.00 TOWEL HANGER

1.00 1.7 18.36 M2 4.00 MIROR

62.98 total door SDB

26.28 total window ELECTRICAL WORK


HAND REIL 26.00 LIGHT POINT

1 16.65 26.00 SOCKET OUT LET

1 16.65 FOR GRIL 26.00 SOCKET FITING


FINISHING WORK 26.00 2 WEY SWICH TYP

3 COAT OF PLASTERIN 26.00 LIHNT FITING AND LAMP

2 484.27 968.54 total HCB 26.00 LIHNT FITING RZB

20 0.50 colomn 1.00 MDB

2 2.70 54.00 2.00 SDB

47.21 SLAB

1069.75 total plastering

152.52 cement screed

152.52 TERAZOO
painting work
1069.75 m2 same with plastering

534.88 plastic

534.88 syntetic

clear glass

39.73 FROM DOORN

26.28 FROM WINDOW

66.01 M2 CLEAR GLASS

2.00 104.64 209.28 10CM SKERTING


Dia Length No of bars Sub total
LocationShape (mm) (m) No.ba Elem. T.No ø6mm ø8mm ø10mm ø12mm ø14mm ø16mm ø20mm
Footing pad
F-1 14 1.80 10.00 22.00 220.00 396.00
F-2 14 2.00 11.00 6.00 66.00 132.00
F-3 in short direction 14 2.10 22.00 3.00 66.00 138.60
F-3 in long direction 14 3.30 11 3.00 33.00 108.90
Footing column
C-1 16 2.84 6.00 20.00 120.00 340.80
C-1(stirup) 6 0.90 10.00 20.00 200.00 180.00
MESH from 8 8.11 57.00 1.00 57.00 462.27
8 10.75 43.00 1.00 43.00 462.25
8 3.50 26.00 1.00 26.00 91.00
8 4.70 20.00 1.00 20.00 94.00

Grade beam GB
top & bottom
14 15.27 6.00 2.00 12.00 183.24
over lap 14 8.90 2.00 2.00 4.00 35.60
stirap 6 1.10 101.00 2.00 202.00 222.20
14 9.11 6.00 2.00 12.00 109.32
over lap 14 6.77 2.00 2.00 4.00 27.08
stirup 6 1.10 60.00 2.00 120.00 132.00
Total length (m) 534.20 1,109.52 - - 1,130.74 340.80 -
Prepared By._____________ Unit weight (k.g) 0.222 0.395 0.617 0.889 1.210 1.580 2.469 2.7
Signiture_________________ Total wt (k.g) 118.71 438.33 - - 1,368.06 538.55 - 0.56
0.3
SUPPER STRACTURE 3.56
elevation column
C-1 & 2 14 3.70 6.00 40.00 240.00 888.00
C-1(stirup) 6 0.90 18.00 40.00 720.00 648.00
top beam
top & bottom
14 15.27 6.00 4.00 24.00 366.48
over lap 14 8.90 2.00 4.00 8.00 71.20
stirap 6 1.10 101.00 4.00 404.00 444.40
14 9.11 6.00 4.00 24.00 218.64 10.66
over lap 14 6.77 2.00 4.00 8.00 54.16 71.066667
stirup 6 1.10 60.00 4.00 240.00 264.00
all slab bar
axis A-B 10 7.85 76.00 1.00 76.00 596.60
axis 1-4 8 12.55 84.00 1.00 84.00 1,054.20
over lap 12 5.25 24.00 2.00 48.00 252.00
axis 1-4 10 7.70 76.00 1.00 76.00 585.20
over lap 12 4.35 20.00 2.00 40.00 174.00
over lap 12 1.50 15.00 1.00 15.00 22.50
stair
in vertical 12 4.25 9.00 4.00 36.00 153.00
over lap 12 4.90 9.00 4.00 36.00 176.40
tred & riser 8 8.37 5.00 4.00 20.00 167.40
in horizontal 8 2.00 26.00 4.00 104.00 208.00
in vertical 12 4.95 9.00 4.00 36.00 178.20
over lap 12 5.05 9.00 4.00 36.00 181.80
tred & riser 8 6.4 5.00 4.00 20.00 128.00
in horizontal 8 2.00 26.00 4.00 104.00 208.00
Total length (m) 1,356.40 1,765.60 1,181.80 1,137.90 1,598.48 - -
Prepared By._____________ Unit weight (k.g) 0.222 0.395 0.617 0.889 1.210 1.580 2.469
Signiture_________________ Total wt (k.g) 301.42 697.52 729.51 1,011.47 1,933.96 - -
No L*W*D Qty

1 4.00
4.00

1.50 24.00

1 4.00

4.00
1.20 19.20

19.20

1 4.00

4.00

1.00 16.00

1 4.00

4.00

0.85 13.60
1 18.00

0.50
4.55 40.95

24.00

48.80

72.80
septic tanck
Description No L*W*D

A.SUB - STRUCTURE

1.excavation & earth work


1.1 Bulk excavation in ordinary soil
for septic tank
1 16.00

M3 total bulck 1.00


1.2 Excavate in ordinary soil for
trench foundation up to 120
from septic tank

1 14.00
0.40

M3 Net Total 0.35


1.2 Excavate in ordinary soil for
trench foundation from 120-220
form water wall 1 3.00

3.00

M3 Net Total 0.15


1.2 Excavate in ordinary soil for
trench foundation from 220-300MM

1 16.00

1.5 Fill around mason and under


hardcore 0.35
Fill AROUND MASON 1 12.00

0.35

M3 Net Total 1 3.00


1.6 Cart away & spread surplus excavated 3.00

For bulk Excavation

For Trench Excavation

M3 Total cart awey 2 4.60

0.80

4.50

2 3.00

0.80

4.50
Qty Description

2.CONCRETE WORKS
2.1 50mm thick lean concrete in C-5
UNDER MASNRY WALL

16.00 M2 Total

2.2 Reinforced concrete in class C-25


c) grade beam

1.96

1.96 M2 TOTAL GB
slab

1.35

2.3 Form Work

c) grade beam

external side

5.60
enternal side

4.20

9.80 M2 TOTAL GB
suspended slab
9.00 m2

3. MASONRY WORKS

A) below NGL from the reduced level

long side

33.12

21.60

54.72 M3 total BNGL


septic tanck
Dia Length No of bars
LocationShape (mm) (m) No.ba Elem. T.No
Grade beam GB
top & bottom
12 3.20 6.00 4.00 24.00
stirap 8 1.50 65.00 1.00 65.00
all slab bar
axis 5-6 14 4.95 16.00 1.00 16.00
axis a-d 12 4.95 16.00 1.00 16.00
Total length (m)
Prepared By._____________ Unit weight (k.g)
Signiture_________________ Total wt (k.g)
Sub total
ø6mm ø8mm ø10mm ø12mm ø14mm ø16mm ø20mm

76.80
97.50

79.20
79.20
- 97.50 - 156.00 79.20 - -
0.222 0.395 0.617 0.889 1.210 1.580 2.469
- 38.52 - 138.67 95.82 - -

You might also like