20210923 TIG7-8-2020-21 Minutes of Site Meeting No. 10
20210923 TIG7-8-2020-21 Minutes of Site Meeting No. 10
SCOPE OF WORK
Tigane Extension 7
Sewer Reticulation Info
Length: 15 123.56m
Manholes: 379
No of Connections: 1 599
Water Reticulation Info
75mm DIA 10 764m
110mm DIA 1 981m
160mm DIA 2 347m
No of Connections 1 599
Stormwater Info
Length 10 876m
Kerb inlets 153
Manholes 29
Roads Info
Length 18 021m
All roads will be surfaced with AsphalTech
Tigane Extension 8
Sewer Reticulation Info
Length: 15 123.56m
Manholes: 379
No of Connections: 1 506
Roads Info
Length 14 455m
All roads will be surfaced with AsphalTech
2.3 Absent:
None
6 CONTRACT DOCUMENTATION
6.1 Guarantees and Insurances
6.1.1 Extension 7:
Guarantees and Insurances are in place, and they are Info
valid for the duration of the contract
6.1.2 Extension 8:
Guarantees and Insurances are in place, and they are info
valid for the duration of the contract
8 PROJECT PROGRESS
8.1 Monthly Progress Report for Extension 7
8.1.1 The total construction period that has expired is 51% as per
the construction duration
8.1.2 Progress of works to date on site is 42.3% including roads,
refer to attached Contractor’s progress report for detailed
progress.
Progress of Sewer is a 100%
Sewer house connections 1599 of 1599
Progress of water is at 100% (Main lines only)
Water house connects 1535 of 1599.
Progress of stormwater is at 38%
Progress of Roads is at 0%
Financial progress is at 36%
12 COMMUNITY MATTERS
12.1 Extension 7
12.1.1 EPWP Participants:
There are 36 General Labourers under the Contractor and
Subcontractor:
0 Male Adults
32 Male Youth (1 being physically challenged)
1 Female Adult
3 Female Youth
12.1.2 CLO’s Report:
No report was presented due to absenteeism of the Info
CLO
12.2 Extension 8
12.2.1 EPWP Participants:
There are 35 General Labourers under the Contractor and
Subcontractor:
8 Male Adults
15 Male Youth (1 being physically challenged)
4 Female Adult
8 Female Youth
12.2.2 CLO’s Report:
No report was presented due to absenteeism of the Info
CLO
14 INFORMATION REQUIRED
14.1 Information Required by COM, Human settlement & HDA:
Layout Indicating current progress of works RFH/ MXN 15/10/2021
15 GENERAL
15.1 Mr Seleke enquired about the readiness of the All Ongoing
developer to commence with bulk and Mr Mashiya
indicated that they should arrange for handover within
the next two months
Mr Seleke requested the engineer to follow up with RFH Ongoing
the design team to finalise all the outstanding issues
especially electricity connections for all the pumps.
Human Settlement and HDA are requested MXN to MXN Ongoing
issue them with layouts indicating progress to date
and they are still waiting
The Engineer requested Mr Mashiya to escalate the MXN 15/10/2021
request of Human settlement and HDA to the CEO
Engineer reported that the OHS agent is paid by RFH, Tig Dev / Info
and no subcontractor should make any payment to Tsekgo
the OHS agent unless instructed by either MXN or RFH
Mr Nyachuru requested clarity on the payment of
surveyor by the contract and the engineer stated that All Ongoing
all survey works are covered under setting out of the
works for each sections
16 NEXT MEETING
16.1 The tentative date for site meeting no.11 is the 21st of
October 2021 at 10h00
17 CLOSURE
17.1 There being no any other matter the meeting was closed at
11:28
MINUTES APPROVAL
………………………………………….
FOR RAJASAMWAY FAMILY HOLDINGS
……………………………………………………………
FOR MXN DEVELPOMENT CONSTRUCTION CC (Developer/Client)
……………………………………………………………
FOR MXN DEVELPOMENT CONSTRUCTION CC (Principal Contractor)
……………………………………………………………
FOR TIGANE DEVELOPERS (Contractor Ext. 7)
……………………………………………………………
FOR TSEKGO CONSTRUCTION (Contractor Ext. 8)
…………………………………………………………..
FOR DEPARTMENT OF HUMAN SETTLEMENT
……………………………………………………………
FOR HOUSING DEVELOPMENT AGENCY (HDA)
…………………………………………………
FOR CITY OF MATLOSANA (COM)