Western Dedicated Freight Corridor- Phase I- CTP 3R - (Iqbalgarh to Vadodara)
NAME OF ENGINEERING STATUS
SL.NO ISSUES AND AREAS TO BE DEVELOPED WAY FORWARD & SUGGESTION PROJECT DESIGN STAGE STATUS DELAY REMARKS PRELIMINARY Design: Design: Completed 168 DESIGN Varied structures to be taken for the design upon 698 nos. of minor structures are receipt of proper variation instruction from Client. approved Delay in providing design input of existing IR bridges structures. Any variation if the design team is not solved, then 193 No’s of major structures are Delay in completion of Topo survey and Geotechnical management needs to take the issue with highest approved Investigation due to non-availability of access to the level of the Client and support to be provided to TECHNICAL Design team. Management shall emphasis on In Progress - bridge locations. DESIGN deploying strongly capable person at Balance 23 No’s of minor structures span Delay in Geotechnical Investigation & Survey data to not finalized by Employer for proposed GC/Engineer’s office. design submission. new structures at station/yard Design & drawings shall be taken up internally connecting road Deviation from the scope of work. within L&T. 1 Additional requirements from the Client/Engineer, which Exclusive resources shall be deployed for project 22 No's of pipe culvert CDP needs to be are beyond the contractual and codal requirements. and there shall be maximum cutoff period to be submitted by site (Technical design Delay due to non-adherence of approved drawings at maintained for which the deployed resources to be CDP In Progress - Approved) site for construct retained and beyond the same and based on the WDFC-CTP- Delay incurred by the DDC. actual situation, resources to be planned. 3R Dedicated surveyor to be posted and it shall be Resource Constraint at EDRC verified and properly benchmarked in discussion 610 No’s of structure base case finalization of base case alignment (delayed by 4 years). with the Client/Engineer. In Progress submitted, and other structure designs Base case - Denial of approved procedures due to change in Base case shall be submitted and approval to be (50 No’s) are in progress as per revised Engineer representative obtained before submission of Technical designs & scheduled. drawings
Method statement submitted to PMC as mitigation
CONSTRUCTION: measure along with RFI Design revision due to Execution issues during piling and Regular site visit to be conducted by the design substructures team and in case of issues with quality & 2 Construction In Progress - Design revision due to Execution issues in cross girder nonadherence of drawings NCR to be issued. and bearing pedestal. Nonadherence of the approved drawings
Transportation Infrastructure – Special Bridges RREC L&T Construction | 1
Sensitivity: LNT Construction Internal Use Western Dedicated Freight Corridor- Phase I- CTP 3R - (Iqbalgarh to Vadodara)
Transportation Infrastructure – Special Bridges RREC L&T Construction | 2
Sensitivity: LNT Construction Internal Use Western Dedicated Freight Corridor- Phase I- CTP 3R - (Iqbalgarh to Vadodara) Salient Features of Project Ludhiana Project Cost (in INR) 7746 crores (RCV) DFC-Route Map Overall Alignment Length 342 kms
Duration of Project 48 months Dadri
Rewari Khurja Contractual start date 6th Jun’16
Contractual completion date 31st May’20
Ajmer Kanpur Extension of Time (Date) 17th Mar’23 Mughalsarai Design Life & speed 100 yrs & 100 kmph Somnagar Type of Total scope Iqbalgarh S. No structures (No's) 1 Minor structures 376 Ahmedabad Dankuni CTP 3R (288 km) 2 Minor RUB 271 Makarpura 3 Major bridge 113 (Vadodara) 4 major RUB 46 Sachin 5 important bridge 5 6 Rail fly over bridge 16 Vaitarna 7 Road over bridge 13 8 Pedestrian subway 10 JNPT 9 Foot over bridge - CLIENT: ENGINEER: CONTRACTOR: 10 Track crossing 41 11 Minor structures for road 23 Total 914
Transportation Infrastructure – Special Bridges RREC L&T Construction | 3
Sensitivity: LNT Construction Internal Use Western Dedicated Freight Corridor- Phase I- CTP 3R - ( Iqbalgarh to Vadodara)
DESCRIPTION – DESIGN STAGES TARGET DATE – SUBMISSION TARGET DATE - APPROVAL
Approved Status Type of Scope S. No. Authority/ Technical Remark structures (No's) CDP Employer design Minor 1 721 698 698 676 1. * Span not finalized by Employer for proposed new structures structures at station/yard connecting road (23 No’s). Major 2. ** 22 No's of pipe culvert CDP needs to be submitted by site 2 193 193 193 193 structures (TD Approved) Total 914 891 891* 869**
As per Contract Design stage is only Coordination Event to the Construction Milestone
Transportation Infrastructure – Special Bridges RREC L&T Construction | 4
Sensitivity: LNT Construction Internal Use Western Dedicated Freight Corridor- Phase I- CTP 3R - (Iqbalgarh to Vadodara)
Critical concerns for Design
Delay in completion of Topo survey and Geotechnical Investigation by 6 Month due to non-availability of access to the bridge locations. Delay in providing the data for parallel structures (parallel to IR Structures) like HFL, IR Completion plan, IR Bridge register, Spanning Configuration, discharge, dimensions of existing IR bridges, etc., the complete design inputs were received after 1 year Delay in handing over the land to the Contractor by 8 month and Last 2km handed over on Oct 2019 Delay in finalization of spanning arrangement for structures (structures proposed by Client in their documents are not considering the requirements of concern authorities like IR/NHAI/SH/PWD/WRD/IOCL/etc.,) Frequent change in the span configuration and type superstructures by authority after approval as resulted in delay Delay in finalization of alignment which was due to issues in topo survey details and also due to changes in the bridge configuration as per the concern authority’s requirements. Introduction of new (additional) structures (117 Nos.) in the Contractor’s Scope of work during the detail design stage. This is due to the reason that feasibility study carried out by Client/PMC are not dually considering the Concern Authority’s requirements. Delay due to unreasonable requirements/demands by the PMC/Client. Delay due to non-adherence of approved drawings at site for construction. Delay due to submission by the Detailed Design Consultant. Transportation Infrastructure – Special Bridges RREC L&T Construction | 5 Sensitivity: LNT Construction Internal Use Western Dedicated Freight Corridor- Phase I- CTP 3R - ( Iqbalgarh to Vadodara)
Base Case Design Status
TARGET DATE – SUBMISSION TARGET DATE - APPROVAL DESCRIPTION – DESIGN STAGES SL.NO (WITH PMC) PLANNED ACTUAL PLANNED ACTUAL
1 Major Structures 31.10.2023 15.11.2023 31.12.2023 Ongoing
2 Minor Structures 31.10.2023 15.11.2023 31.12.2023 Ongoing
Critical concern for Base case design
Delay in finalization of base case alignment (delayed by 4 years).
Delay due to inadequate resource with EDRC and due to series of site related issues to be attended. Delay due to denial of approved procedures due to change in Engineer representative.
Transportation Infrastructure – Special Bridges RREC L&T Construction | 6