BOQ_Qty_Norikori Korona Road_K92_Dec. 2023
BOQ_Qty_Norikori Korona Road_K92_Dec. 2023
BOQ_Qty_Norikori Korona Road_K92_Dec. 2023
BILL OF QAUNTITIES
2 Group 2 – Establishment
2.1 Mobilisation of Contractor and its Site Establishment LS 1.00
2.2 Maintenance of Constrictor’s Site Establishment Month 6.00
2.3 Demobilisation and removal of all Site Establishments LS 1.00
Purchase a fully kitted Toyota Land Cruiser 4 Door complete with on-
2.4 No. 1.00
the-road-cost as project supervision vehicle.
2.5 Supply fuel and maintenance to Engineer's Supervision Vehicles Month 6.00
2.7 Supply, erect and remove Project Notice Boards No. 2.00
Sub Total As - Bill No. 02
Clearing & grubbing of right - off - way including the removal and
3.1 disposal of spoils, tree stumps and roots, and any other foreign Ha 1.40
material within the area of Work
Sub Total As - Bill No. 03
4 Group 4 – Earthworks
General Excavation of Type G material for both widening and slip
4.1 clearing including the carting and disposal to accepted disposal sites m3 4,013.49
in accordance with the CEMP
Excavate and repair soft spot with the supply, place and compacting
4.2 m3 1,697.38
of granular material the provision of geo fabric material
6.1 Prime pavement surface including the Provision of blotter material m2 42,000.00
Apply first coat seal using 19mm nominal size precoated sealing
6.2 m2 38,500.00
chips
Apply second coat seal using 14mm nominal size precoated sealing
6.3 m2 35,000.00
chips
Sub Total As - Bill No. 06
7 Group 7 – Drainage
Remove Existing Culverts <Ø1200 mm including excavation &
7.1 No. 8.00
backfilling
7.2 Supply and install new culverts (CMP)
a) Ø 450 mm m -
b) Ø 600 mm m 56.40
c) Ø 900 mm m 39.00
d) Ø 1200 mm m 7.80
8.1 Steel beam guardrails and posts shall be constructed and erected in m 130.00
accordance with the Drawings or as directed by the Engineer
8.2 Pavement Markings
i) Edge Line m 14,000.00
ii) Broken & solid line m 1,650.00
Iii) Double barrier line m 1,670.00
iv) Hazard line m 200.00
v) Broken line m 3,480.00
Sub Total As - Bill No. 08
Sub - Total