Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

Received: 26 December 2022 Revised: 11 May 2023 Accepted: 31 May 2023

DOI: 10.1002/cjce.25027

RESEARCH ARTICLE

Effect of plant density and hydraulic retention time on


phytoremediation of greywater using water hyacinth and
validation of its optimized result using artificial neural
network

Rajnikant Prasad 1,2 | Dayanand Sharma 3 | Ashutosh Kumar Pandey 4 |


Kunwar D. Yadav 1 | Sunil Kumar 5 | Hussameldin Ibrahim 6

1
Department of Civil Engineering, SV
National Institute of Technology, Surat, Abstract
India Water scarcity is a global issue and finding alternative ways to meet our water
2
Faculty of Civil Engineering, College of needs within available resources is becoming increasingly important. Repurposing
Militry Engineering, Pune, India
3
greywater for non-potable uses, such as irrigation and car washing, can help alle-
Civil Engineering Department, Sharda
University, Greater Noida, India
viate the demand for drinking water. Greywater recycling and reuse are viable
4
Centre for Energy and Environmental options to combat water scarcity. This study investigated the treatment of grey-
Sustainability-India, Lucknow, India water using phytoremediation, specifically focusing on the effect of water hyacinth
5
CSIR-National Environmental density and hydraulic retention time (HRT). An artificial neural network was used
Engineering Research Institute
to optimize these parameters in the treatment system. The experiment spanned
(CSIR-NEERI), Nagpur, India
6
Clean Energy Technologies Research
over 7 weeks and consisted of two phases. In phase I, different water hyacinth
Institute, Process Systems Engineering, densities (ranging from 1.0 to 4.0 kg/m2) were tested, while phase II examined
Faculty of Engineering and Applied various HRTs (ranging from 12 to 48 h). The results indicated that the optimal
Science, University of Regina, Regina,
Saskatchewan, Canada conditions for greywater treatment were a water hyacinth density of 2 kg/m2 and
an HRT of 48 h. Under these optimal conditions, the treatment system achieved
Correspondence
high removal efficiencies for turbidity (98.02 ± 0.75%), chemical oxygen demand
Hussameldin Ibrahim, Clean Energy
Technologies Research Institute, Process (59.42 ± 5.64%), ammonium-nitrogen (87.45 ± 7.29%), and phosphate (94.50
Systems Engineering, Faculty of ± 2.19%). However, the removal of total suspended solids was relatively low at
Engineering and Applied Science,
43.98 ± 9.20%. These findings were confirmed using an artificial neural network,
University of Regina, 3737 Wascana
Parkway, Regina, SK 4S 0A2, Canada. showing a strong correlation (R > 0.99). The study concludes that phytoremedia-
Email: hussameldin.ibrahim@uregina.ca tion using water hyacinth can be a viable option for greywater recycling and
reuse, effectively addressing water scarcity. The recommended optimal conditions
include a water hyacinth density of 2 kg/m2 and an HRT of 48 h.

KEYWORDS
floating plant, greywater, hydraulic retention time, density, water hyacinth

This is an open access article under the terms of the Creative Commons Attribution-NonCommercial-NoDerivs License, which permits use and distribution in any
medium, provided the original work is properly cited, the use is non-commercial and no modifications or adaptations are made.
© 2023 The Authors. The Canadian Journal of Chemical Engineering published by Wiley Periodicals LLC on behalf of Canadian Society for Chemical Engineering.

Can J Chem Eng. 2024;102:113–128. wileyonlinelibrary.com/journal/cjce 113


1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
114 PRASAD ET AL.

1 | INTRODUCTION respectively. Despite the variations in retention time


required for different types of wastewater treatment,
By 2030, rapid urbanization and population growth, with there is a lack of comprehensive studies that investigate
around 55% of the world’s population residing in urban the effect of changing retention time on the treatment
areas, are anticipated to grow the water demand 60%.[1] efficiency for GW. Thus, there is a need for more research
The increasing burden on the available freshwater to identify the optimum retention time and plant density
resources worldwide has led us to think of new ways to required for the effective treatment of GW.
meet our water demand within the available resources. Numerous methods are available for GW treatment
Reusing greywater (GW) after suitable treatment for non- like physical, chemical, and biological treatment tech-
potable purposes like gardening, vehicle cleaning, and fire niques, having success in varying degrees. Many treat-
fighting can reduce the potable water demand.[2] GW is an ment systems are efficient in treating GW. However,
encouraging, permanent source and accounts for more than these technologies cannot be implemented in developing
60%–70% of municipal wastewater generation.[3] countries due to their capital, operation, and mainte-
In many parts of the world, the floating freshwater nance costs.[19] The natural treatment system, which
aquatic plant known as water hyacinth is considered a relies on the natural process for contamination remedia-
noxious weed. The proliferation of water hyacinth results tion, has been considered a promising method: economi-
in doubling its capacity within 15–20 days, depending cal and easy to operate. It involves a complex mechanism
upon the nutrient availability. The proliferation is essen- between water, plants, substrates, and microorganisms
tial for wastewater remediation using phytoremediation for removing contaminants like organic matter, nutri-
techniques. The criteria of phytoremediation include ents, and other pollutants from wastewater.[20]
rapid growth rate, high nutrient absorption rate, and ease Several studies are available on environment friendly
to harvest, which water hyacinth fulfills. Water scarcity and economically viable technology.[21] Constructed wet-
and hyacinth problems can be alleviated by utilizing land is a proven technology for wastewater treatment.
them under controlled conditions for GW treatment. Vertical flow wetlands, horizontal sub-surface wetlands,
According to the different literature, water hyacinth and free-flowing surface wetlands are the three primary
can be effectively used for the removal of pollutants from forms of man-made wetlands used in wastewater remedi-
pig farm wastewater,[4,5] domestic wastewater,[6–8] petro- ation.[20] The free water surface system comprises an area
leum refinery wastewater,[9] institute wastewater,[10] pol- of open water with floating vegetation or emergent
luted rural river water,[11] aquaculture wastewater,[12] plants. Due to its oxygen enriching capacity, free water
dairy manure wastewater,[13] duck farm effluent,[14] and surface systems are used for wastewater treatment from
textile effluent.[15,16] However, the key parameters driv- different industries and domestic units.
ing aquatic plant treatment performance are plant An artificial neural network (ANN) is a convincing,
density, hydraulic retention time (HRT), and plant quick, flexible, and accurate modelling tool that uses
growth rate.[17] The plant density selection is a significant mathematical logic to mimic the way the human brain
factor in treatment performance. The growth of water recognizes patterns. When modelling complex interac-
hyacinth is directly correlated with nutritional availabil- tions between inputs and outputs, they are utilized as
ity, environmental factors, and wastewater pH. Water modelling tools for non-linear statistical data.[22] ANNs
hyacinth flourishes due to the increased concentration of are effective mathematical tools for modelling, simulat-
nutrients. However, proliferation is directly proportional ing, and optimizing different processes.[23–25] Applica-
to the decay rate, that is, the growth rate in particularly tions of ANN include dye adsorption using zinc oxide,[26]
nutrient-rich wastewater directly relates to decay and leachate adsorption,[27] and cattle dung and flower quan-
decomposition. Hence, optimum initial plant density is tity optimization for vermicomposting.[28] Using ANN,
crucial in treatment performance to avoid decaying. It the experimental dataset was validated and the optimum
also considers the frequency of harvesting needed for the outcome was predicted for water hyacinth density and
continuous operation of the treatment system. HRT for GW treatment in a floating plant treatment sys-
Change in the retention time accounts for variation tem. This study predicted optimum water hyacinth den-
in treatment performance. The retention time depends sity and HRT using multi-layered feed-forward ANN with
on the pollution level in the wastewater. For example, back-propagation (BP).[29] It solves the non-linear regres-
Rangel-Peraza et al.[10] reported a retention time of sion models.[30] BP was used to analyze the findings of the
4 days, Agarry et al.[9] and Shah et al.[18] reported network, which resulted in a reduction of error through the
10 days, and Rezania et al.[6] reported 12 days of reten- process of tracing links between inputs and outputs.[31] Sev-
tion time for institute wastewater, petroleum refinery eral studies have proven the efficacy of ANN models for
wastewater, municipal wastewater, and domestic sewage, envisaging the wastewater treated.[32,33]
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
PRASAD ET AL. 115

The research aimed to investigate the use of water tank made of PVC with 1.2 m long, 0.83 m wide, and
hyacinth for the treatment of GW through phytoremedia- 0.34 m deep placed at 1.5 m height provided continuous
tion techniques. Specifically, it aimed to identify the opti- flow into the reactor. A pipe connected from the header
mum initial plant density and HRT required for effective tank to each of the reactors equipped with a flow control
treatment. The study also explore the use of constructed valve maintained the reactor’s hydraulic inflow rates. The
wetlands as a natural and cost-effective method for GW study was carried out for 31 days; after that, the water hya-
treatment. Furthermore, the study propose the use of cinth started growing out of the reactor.
ANN as a modelling tool to predict the optimum outcome
of water hyacinth density and HRT for GW treatment in
a floating plant treatment systems. 2.3 | Methodology

The study was carried out in two phases. Phase I deter-


2 | MATERIALS AND METHODS mined the optimum water hyacinth density under a con-
stant 24 h HRT and 60 L/day flow rate. A volumetric
Figure 1A depicts the flowchart of the methodology used method was used to check the reactor inflow and outflow
in the study. It provides a visual representation of the rates. The water hyacinth density of 1, 2, 3, and 4 kg/m2
study’s overall approach and helps to clarify the research was used in the reactor and designated D1, D2, D3, and
process. D4, respectively. In phase II, the treatment performance
was evaluated at a water hyacinth density of 2 kg/m2 and
HRT of 12, 24, 36, and 48 h for the reactor and designated
2.1 | GW and water hyacinth collection as H1, H2, H3, and H4, respectively. The flow rate was
computed by considering the reactor’s theoretical HRT
GW was collected from the student hostel at the Sardar and surface area. The HRT, t (h), was calculated using
Vallabhbhai National Institute of Technology (SVNIT), Equation (1).
Surat, India (21.1643 N, 72.7841 E). A separate collec-
tion system of capacity 350 L was installed for collecting V Ay
t¼ ¼ ð1Þ
GW from hand basins, showers, and bathrooms. Daily, Q Q
250 L of GW was collected, and the remaining was
discarded. Where Q (L/day) is the designed flow rate, which is
Baby water hyacinths (10–12 cm height) were col- assumed constant, A (m2) is the surface area of the reac-
lected from Hazira Lake of Surat, India, and stored in the tor, V (m3) is the reactor volume, y is the depth of flow in
propagation area, which was used as a storage bank for the floating plant treatment system.
further studies. All foreign matter on the water hyacinth
was removed by thoroughly washing with tap water
before cultivation in the propagation area. Similar-sized 2.4 | Sampling and analysis
baby water hyacinth (70–100 g) with a 12–14 cm height
were used in phases I and II. The presence of new roots The GW sampling started 7 days after planting to avoid
and the higher nutrient requirements of baby water hya- the initial fluctuations and allow water hyacinth to adopt
cinth compared to matured ones justify selecting the baby the new environment. The outflow (treated effluent) sam-
water hyacinth. Moreover, the baby water hyacinth roots ple was collected using siphon action. The samples
release more oxygen into the water than the developed (inflow and outflow) were collected daily from 9:00 to
roots.[34] 10:00 AM and analyzed immediately or stored under refrig-
eration at 4 C for further determination. Chemical oxygen
demand (COD) was analyzed using a COD reactor at 150 C
2.2 | Experimental set-up for 2 h, and excess hot potassium dichromate was titrated
with ferrous ammonium sulphate. Ammonium-nitrogen
Floating Pond Treatment Systems (FPTS) consist of four (NH4+-N) and phosphate (PO43) by stannous chloride
rectangular reactors of 1.0 m long, 0.3 m wide, 0.3 m deep, method were analyzed in accordance with standard proce-
a surface area of 0.3 m2, and a total volume of 90 L dures (APHA 2012). Total suspended solids (TSS) were ana-
(Figure 1B). The inflow pipe (12.7 mm diameter) was lyzed by the filtration method using Whatman GF/F filters.
located at 0.2 m from the bottom of the reactor towards The pH, water temperature, and TDS measurements
the top, and the outflow pipe at 25 mm from the bottom at were done using a portable pH and TDS meter (Hanna
the bottom of the reactor in the middle width. A header Instruments, HI98129, Romania).
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
PRASAD ET AL.

F I G U R E 1 (A) Flowchart of the methodology. (B) Greywater treatment system used in this study. BOD, biochemical oxygen demand;
COD, chemical oxygen demand; HRT, hydraulic retention time; TDS, total dissolved solids; TSS, total suspended solids.
116
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
PRASAD ET AL. 117

2.5 | Statistical analysis Where N = Total number of data points; yAct,i ¼


Actual result; yprd,i ¼ Predicted result; ym = Mean value of
The experimental data were analyzed using SPSS 22.0, the result.
and p < 0.05 was interpreted for the insignificant differ- The commonly employed error function, MSE, was
ence level. One-way analysis of variance (ANOVA) was used in this study (Equation (3)),
performed to analyze the differences in the average out-
flow values for each physicochemical parameter. 1X N  2
MSE ¼ yin  ^yin ð3Þ
N I¼1

2.6 | ANN modelling


Where, N = number of patterns used in training;
The ANN is a neural network toolbox (NNT) that makes M = number of output nodes; i = Index of the input pat-
use of multi-layered hidden neural neurons to carry out tern (vector); yin and ^yin ¼ Actual and predicted outputs.
computational modelling for complex and non-linear
systems.[22] The ANN architecture developed for this study
was utilized to optimize water hyacinth density and HRT 3 | RESULTS A ND DISCUSSIONS
for the GW treatment. Using MATLAB R2015a
(MathWorks Inc., USA), various ANN topologies were The FPTS showed quick start-up attributed to the rapid
trained to estimate the total number of neurons in the hid- growth of water hyacinth under phase I and II. The
den layer. The training parameters used are provided in results showed a strong relationship between the water
Table 1. The ANN with minimum mean square error hyacinth density and HRT in the overall treatment per-
(MSE) and maximum overall correlation coefficient (R) formance. The growth exceeded expectations to such an
reached closer to 1, and regression value (R2) calculated by extent that the baby plant roots floated in the air outside
using Equation (2) was considered as optimal topology.[35] the reactor and survived, showing that the mother plant
supplied the nutrients required for its growth through
N 
P  stolon inside the reactor. Even though the baby plant sur-
yprd,i  yAct,i
vived, it was not directly involved in the treatment pro-
R2 ¼ 1  i¼1N   ð2Þ
P cess resulting in the stoppage after 31 days.
yprd,i  ym
i¼1

3.1 | Effect of temperature and pH


T A B L E 1 Artificial neural network training parameters for the
tabulated parameters. GW temperature and pH significantly impact water hya-
Parameters Set value cinth growth[36] and can significantly affect the treatment
performance.[7] The average inflow GW temperature
Model type Feed-forward-
backpropagation
was 25.25 ± 1.13 C, with an average outflow GW temper-
ature of 24.30 ± 1.43 C, 24.17 ± 1.40 C, 24.17 ± 1.39 C,
Transfer functions
24.07 ± 1.41 C for reactor D1, D2, D3, and D4, respec-
Between hidden input–output TANSIGMOID tively, during the Phase 1 (Figure 2A). The reduction in
Between output-in and PURELIN the outlet GW temperature was observed compared to
output-out the inlet. For phase II, the average inflow GW tempera-
Training function Levenberg– ture was 27.49 ± 2.16 C with an average outflow GW tem-
Marquardt (TRAINLM) perature of 28.29 ± 2.43 C, 27.19 ± 2.23 C, 27.02 ± 2.13 C,
Performance function MSE < 0.01 and 28.79 ± 2.73 C, respectively for reactor H1, H2, H3,
(termination criteria) and H4, respectively (Figure 3A).
Adaption learning function LEARNGDM Similar to phase I, a slight reduction in GW tempera-
Optimum number of hidden 20 ture was observed for reactor H2 and H3, whereas for
neurons for removal of pollutants reactor H1 and H4, an increase in water temperature was
% data for training 70 observed. However, there was no significant difference
% data for testing 15 between the inflow and outflow as well as between differ-
ent outflows (p > 0.05) in phase I and phase II. Qin
% data for validation 15
et al.[7] reported a similar result, where the water temper-
Epochs limit (iterations) 1000
ature ranged between 24.5 and 31 C. The average
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
118 PRASAD ET AL.

F I G U R E 2 Temporal variations in (A) water temperature, (B) pH, (C) turbidity; (D) total dissolved solids (TDS), and (E) total suspended
solids (TSS) during density study.

temperature in the present study lies between 21.8 and and outflow ranged between 7.17 and 7.92 for D1, 7.07
29 C, which is considered ideal for water hyacinth and 7.92 for D2, 7.11 and 7.85 for D3, and 7.10 and 8.04
growth. However, the minimum and maximum water for D4. Figure 2B shows a minor reduction in the pH of
temperatures for water hyacinth growth required are the outflow in all the reactors. A significant difference in
12 and 35 C, respectively.[37] Thus, the study was carried pH was observed for inflow and outflow except for reac-
out under the suitable temperature required for water tors D4. However, significant difference ( p > 0.001) was
hyacinth proliferation. not observed between the outflow of the reactors D1, D2,
Water hyacinth is sensitive to the pH of the water in D3, and D4. For phase II, inflow pH ranged between 7.64
which it is grown, affecting the treatment performance. and 7.91, and outflow ranged between 7.42 and 7.71 for
For phase I, inflow pH ranged between 7.42 and 7.86, H1, 7.39 and 7.71 for H2, 7.4 and 7.8 for H3 and 7.41 and
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
PRASAD ET AL. 119

F I G U R E 3 Temporal variations in (A) water temperature, (B) pH, (C) turbidity, (D) total dissolved solids (TDS), and (E) total suspended
solids (TSS) during hydraulic retention time study.

7.98 for H4 (Figure 3B). Significant difference (p < 0.001) microbial activity required for nitrification. Therefore,
was observed between the inflow and outflow except for the pH in the present study was within the optimum
H4. However, a significant difference was observed growth conditions required for water hyacinth growth
between the outflows between the H1 and H4. That a and development.
decrease in pH was observed in the outflow compared to
the inflow in phase I and phase II indicates diffusion of
atmospheric CO2 into the water column. Agarry et al.[9] 3.2 | Removal of turbidity, TDS, and TSS
observed a pH range of 7.4 to 7.7 to treat petroleum refin- performance
ery wastewater. The pH range of 6 to 9 is optimum for
water remediation using macrophytes.[18] Moreover, the The stable colloidal suspensions in the GW were mea-
pH range of 6.6 to 8 is required for the improved sured in turbidity and dissolved liquid content in
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
120 PRASAD ET AL.

molecular and ionized in TDS[38] and were found to 6.97 ± 6.39%, 5.58 ± 6.97% for reactor D1, D2, D3, and
reduce in both the phases of the study. For phase I, the D4, respectively.
average inflow turbidity was 55.36 ± 6.63 NTU, and the For phase II, the average TDS inflow was 371.25 ±
outflow turbidity was 6.09 ± 2.74 NTU, 4.48 ± 1.81 NTU, 19.28 mg/L and outflow TDS of 379.68 ± 38.27 mg/L,
4.35 ± 1.88 NTU and 4.98 ± 2.29 NTU for reactor D1, D2, 368.35 ± 32.12 mg/L, 368.39 ± 38.10 mg/L, and 371.94 ±
D3, and D4, respectively (Figure 2C). The corresponding 45.17 mg/L for reactor H1, H2, H3, and H4, respectively
average turbidity removal was 88.94 ± 4.97%, 91.90 (Figure 3D). The corresponding TDS removal was 2.23 ±
± 3.12%, 92.11 ± 3.28%, and 90.96 ± 4.13% for reactor D1, 8.20%, 2.25 ± 7.46%, 2.07 ± 7.78%, and 1.01 ± 9.60% for reac-
D2, D3, and D4, respectively. The optimum turbidity tors H1, H2, H3, and H4, respectively. Significant difference
removal was observed in reactor D2 with an average (p > 0.1) was not observed between the inflow and the out-
removal of 91.90 ± 3.12%. Increasing the water hyacinth flows for phases I and II. Similar results were reported by
density beyond the density used in reactor D2 does not fur- Olukanni and Kokumo,[43] where a TDS reduction of 12.64%
ther improve the turbidity removal efficiency. The turbidity was observed. Thus, it can be concluded that water hyacinth
removal can be due to the dense root of the water hyacinth does not significantly contribute to TDS removal.[44]
trapping the colloidal suspension particles in the TSS represents the suspended matter present in the
GW. However, increasing water hyacinth density beyond the GW. For phase I, the average inflow TSS was 137.52 ±
density used in reactor D2 does not further contribute to 16.19 mg/L, and outflow TSS was 90.16 ± 13.18 mg/L,
treatment performance. 88.81 ± 13.81 mg/L, 90.16 ± 13.18 mg/L, and 91.55 ±
For phase II, the average inflow turbidity was 40.32 ± 13.21 mg/L, respectively for reactors D1, D2, D3, and D4.
8.74 NTU, and outflow turbidity was 1.94 ± 1.04 NTU, The corresponding removal was 34.39 ± 6.42%, 35.40 ±
1.27 ± 0.82 NTU, 1.02 ± 0.81 NTU, and 0.79 ± 0.36 NTU 7.04%, 34.39 ± 7.89%, 16.00 ± 9.09% for reactors D1, D2,
for reactor H1, H2, H3, and H4, respectively (Figure 3C). D3, and D4, respectively was observed with maximum
The corresponding average turbidity removal was reduction in reactor D2 (Figure 2E). Similar result
95.21 ± 2.11%, 96.93 ± 1.70%, 97.38 ± 1.61%, 98.02 ± 0.75% was observed for phase II, where the average TSS inflow
for reactor H1, H2, H3, and H4, respectively. It was was 156.65 ± 22.48 mg/L, and average TSS outflow was
observed that with a reduction in GW flow rate, the turbid- 118.61 ± 9.62 mg/L, 108.35 ± 7.69 mg/L, 95.29 ± 5.85 mg/L,
ity removal performance improved with maximum removal and 86.0 ± 6.44 mg/L for reactors H1, H2, H3, and H4,
observed in reactor H4.[39] The extensive water hyacinth respectively (Figure 3E). The corresponding removal of 23.10
roots significantly contributed to the turbidity reduction ± 10.03%, 29.54 ± 10.39%, 37 ± 9.91%, and 43.98 ± 9.20% for
from GW.[40] reactor H1, H2, H3, and H4 were observed in phase II. The
Significant turbidity removal was observed in all the maximum removal was observed in reactor H4. Significant
systems, irrespective of the water hyacinth density and difference (p < 0.001) was observed between the inflow and
hydraulic loading rate. Moreover, the visual observation outflow and different outflow. The removal mechanism
of the reactor showed the presence of snails on the reac- involves the trapping of suspended solids in the roots of
tor walls. These snails clean suspended solids and prevent water hyacinth. Trapped solids are then mobilized by the
algal growth on the reactor walls.[41] The enhanced tur- microorganisms present on the roots, acting as a site for
bidity removal was observed because of the settling of the microbial growth, and, in the end, they settle at the bottom
lighter organic matter on the roots of water hyacinth of the reactor.[34] Similar results were reported by Rezania
through rhizofilteration, physicochemical absorption, et al.[42] with 34% of TSS removal, and Loan et al.[45] reported
and accumulation of the heavier suspended particles at 44.4–53.4% for domestic wastewater treatment. However,
the bottom of the reactor.[38] Therefore, reactor H4 (den- higher removal (91.8%) than the current study was observed
sity 2 kg/m2 and HRT of 48 h) showed the highest turbid- by Fazal et al.[46] for the treatment of industrial wastewater
ity removal. using water hyacinth.
For phase I, the average inflow TDS was 384.68 ±
29.36 mg/L, and outflow TDS was 358.39 ± 24.42 mg/L,
360.61 ± 18.41 mg/L, 356.42 ± 16.05 mg/L, and 361.68 ± 3.3 | Removal of COD, ammonium-
17.57 mg/L for D1, D2, D3, and D4 reactor, respectively nitrogen, and phosphate
(Figure 2D). The maximum reduction was observed in
reactor D3. In contrast to the high turbidity removal, Reduction in the COD was observed in both the phases.
very low TDS removal was observed. Rezania et al.[42] For phase I, the average inflow COD was 147.61
reported a similar result of 11% TDS removal from ± 26.47 mg/L, and outflow COD was 91.61 ± 19.48 mg/
domestic wastewater treatment. The corresponding L, 76.42 ± 13.84 mg/L, 76.08 ± 12.82 mg/L, and 79.47
average TDS removal was 6.55 ± 6.63%, 5.85 ± 7.18%, ± 14.52, respectively for reactor D1, D2, D3, and D4
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
PRASAD ET AL. 121

F I G U R E 4 Temporal variations in (A) chemical oxygen demand (COD), (B) ammonium-nitrogen, (C) phosphate, (D) water hyacinth
weight during the density study.

(Figure 4A). The corresponding average removal effi- removal was reported by Rezania et al.[6] with 95% COD
ciency of 38.16 ± 5.28%, 48.09 ± 3.87%, 48.29 ± 2.84%, for domestic wastewater. Kumari and Tripathi[48]
and 45.61 ± 8.07% was observed for reactors D1, D2, D3, reported 83.2% COD removal in municipal wastewater
and D4, respectively. The maximum removal was using a combination of Salvinia natanas and water
observed for reactor D2, followed by D3, D4, and least hyacinth.
in D1. Ammonium-nitrogen is wastewater’s most effective form
For phase II, the average inflow COD was 103.74 ± of nitrogen.[49] For phase I, average inflow ammonium-
14.04 mg/L, and outflow COD was 57.25 ± 7.30 mg/L, nitrogen was 7.06 ± 0.71 mg/L and outflow ammonium-
56.0 ± 4.86 mg/L, 44.68 ± 4.92 mg/L, and 41.53 ± 4.04 mg/L nitrogen was 4.33 ± 0.40 mg/L, 4.00 ± 0.33, 4.01 ± 0.69 mg/
respectively for reactors H1, H2, H3, and H4 (Figure 5A). L, and 4.35 ± 1.09 mg/L, respectively for reactors D1, D2,
The corresponding average removal of 44.62 ± 4.02%, D3, and D4 (Figure 4B). The corresponding average
45.37 ± 6.41%, 56.48 ± 5.33%, and 59.42 ± 5.64% was ammonium-nitrogen removal was 38.45 ± 5.53%, 42.85
achieved for reactors H1, H2, H3, and H4, respectively. ± 6.90%, 42.83 ± 10.28%, and 38.31 ± 14.42% for reactors
Significant ( p < 0.001) difference in the treatment perfor- D1, D2, D3, and D4, respectively. Significant (p < 0.001) dif-
mance was observed between the inflow and outflow. ference was observed between inflow and outflow with
The highest average COD removal was observed for reac- maximum reduction in reactor D2, followed by D3, D1,
tor H2, followed by H3, H4, and H1. The water hyacinth and D4. Higher removal was observed for reactor D2,
root system function, similar to the microbial growth providing optimum density. Further increase in the
media, provided suitable conditions in the rhizosphere water hyacinth density reduces the average removal
for the microbial degradation of organic pollutants[11] efficiency because increased density increases the rate
and nutrients into inorganic compounds used by water of decay in the reactor, thereby reducing pollutants.
hyacinth.[47] Similar treatment performance was reported For phase II, the average inflow ammonium-nitrogen
by Loan et al.[45] with 44.5–53.4% COD removal for was 8.04 ± 1.38 mg/L and outflow ammonium-nitrogen
domestic wastewater treatment. However, higher COD was 4.92 ± 1.44 mg/L, 3.78 ± 0.96 mg/L, 2.42 ± 0.86 mg/L,
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
122 PRASAD ET AL.

F I G U R E 5 Temporal variations in (A) chemical oxygen demand (COD), (B) ammonium-nitrogen, (C) phosphate, (D) water hyacinth
weight during the hydraulic retention time study.

and 1.02 ± 0.62 mg/L respectively for reactors H1, H2, Phosphorous is present in the form of phosphate, and
H3, and H4 (Figure 5B). The corresponding average only the orthophosphate form is used by the plants in the
ammonium-nitrogen removal was 39.27 ± 12.42%, wetland-type of treatment systems. For phase I, the
52.64 ± 9.65%, 69.65 ± 9.34%, and 87.45 ± 7.29% from average inflow phosphate was 0.98 ± 0.17 mg/L and
reactors H1, H2, H3, and H4, respectively. Significant outflow phosphate was 0.71 ± 0.18 mg/L, 0.58 ± 0.17 mg/L,
( p < 0.001) difference was observed for inflow and out- 0.59 ± 0.13 mg/L, and 0.56 ± 0.11 mg/L for reactors D1,
flows. Reactor H4 obtained the highest removal with D2, D3, and D4, respectively (Figure 4C). The correspond-
an HRT of 48 h. This can be attributed to the availabil- ing average phosphate removal was 27.63 ± 10.50%, 41.99
ity of enough contact time between the nutrients pre- ± 9.41%, 39.56 ± 09.06% and 42.23 ± 12.37% was observed
sent in the GW and water hyacinth roots. in reactors D1, D2, D3, and D4, respectively. Significant
The ammonium-nitrogen removal can be attributed difference (p < 0.001) was observed between the inflow and
to plant uptake, bacterial nitrification, and denitrifica- the outflow. With an increase in water hyacinth density,
tion. Moreover, the physical structure of water hyacinth the phosphate requirement increases for the growth result-
obtains the nutrition directly from the water column, as ing in phosphate removal. However, increased density also
they are floating into the water and are not rooted in the results in increased plant litter decaying rate, which needs
substrate. Valipour et al.[34] reported an average to be frequently removed to maintain the treatment perfor-
72 ± 1.84% ammonium-nitrogen reduction, showing pri- mance. Reduced removal in reactor D3 can result from the
marily water hyacinth roots in the transportation and decaying process in the treatment system, which continues
shoots accumulating a considerable amount of nitrogen to reactor D4. The maximum phosphate reduction was
and phosphorous compared to the root area. Akinbile observed for reactor D2, followed by D4, D3, and D1.
and Yusoff[12] observed 96.12% ammonium-nitrogen For phase II, the average inflow phosphate was 1.09 ±
removal from wastewater. 0.14 mg/L and outflow phosphate was 0.34 ± 0.12 mg/L,
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
PRASAD ET AL. 123

0.24 ± 0.11, 0.18 ± 0.11, and 0.06 ± 0.03 mg/L for reactors increases the initial treatment performance; however,
H1, H2, H3, and H4, respectively (Figure 5C). The corre- this increases the harvesting frequency. Across all plant
sponding average phosphate removal was 69.02 ± 8.07%, treatment systems, the lower the maintenance, the
78.92 ± 7.37%, 84.23 ± 7.28%, and 94.50 ± 2.19% was greater the utilization rates. Therefore, it is necessary to
observed in reactors H1, H2, H3, and H4, respectively. Simi- find the optimum water hyacinth density that provides
lar to turbidity, the removal percentage increases with an the optimum harvest rate. Additionally, it was observed
increase in HRT. A significant difference between the differ- that matured water hyacinth is not as effective as baby
ent outflow was observed. A reduction in phosphate removal plants in the treatment performance. This can be due to
was observed due to the plants dead and decaying in the the fact that the roots of the matured plant turned black
reactor.[43] A sudden spike in the phosphate reduction was and the decomposition started. The decomposition pro-
observed as seen from the Figure 5C, which can be the result cess results in the release of nutrients into the water col-
of the decaying process during which the rate of release of umn, making it ineffective in further treatment. In the
phosphate was more than the rate of removal. These findings case of baby plants, nutrients are required for their
were comparable to those previously reported where the growth and multiplication. In the preliminary study of
methods of nitrogen removal by water hyacinth include water hyacinth growth patterns, it was observed that
plant uptake and the effect of rhizospheric microbes.[50] after developing 4–5 baby plants (stolon growth), the
Kutty et al.[51] reported 83% reduction in phosphate on 48 h mother plant’s nutrients uptake reduces, and it survives
retention time and 84% reduction on the 4 days retention only to nourish the baby plant via stolon.
time. Further increase in HRT does not increase treatment At this stage, the mother plant’s rapid decaying rate
performance. In contrast, Mahunon et al.[4] reported 99.35% needs to be removed to maintain the treatment perfor-
removal with an HRT of 15 days to treat pig farm wastewa- mance; otherwise, nutrients are recycled back into the
ter. However, lower phosphate removal was observed by water column. Thus, harvesting is crucial to avoid the addi-
Loan et al.[45] with the removal of 56.7–61.4% observed. The tion of pollutants from the decaying process of water hya-
initial phosphate removal occurs through the plant and cinth. In this study, based on the ammonium-nitrogen and
microbial uptake, as well as sedimentation. The sustainable phosphate removal performance (Figure 5B,C), the removal
phosphate removal method includes adsorption, accumula- efficiency decreases after 20–22 days, indicating the degra-
tion, and burial in the reactor bottom. Further, the microbes dation of matured water hyacinth biomass. Therefore, it is
present on the water hyacinth roots may have played a necessary to harvest the matured water hyacinth biomass
substantial part in the phosphate removal owing to the within 20–22 days, keeping the young water hyacinth for
biological and biochemical mineralization of organic phos- further treatment. In contrast, Rezania et al.[42] reported
phorous.[52] The plant uptake is recycled back into the water 14 days for harvesting water hyacinth for domestic waste-
columns through the plant growth, death, and decay cycle. water treatment in a continuous treatment system.
Overall, the performance of FPTS was considerable for GW
treatment in both phase studies.
Merino-Solís et al.[53] showed that increasing the HRT 3.5 | Growth of water hyacinth
led to a significant improvement in the removal efficiency
of COD, TSS, ammonium-nitrogen, and total nitrogen. The The growth of water hyacinth relates to the uptake of
maximum removal efficiency of COD, TSS, ammonium- nutrients for growth and development. In the current
nitrogen, and total nitrogen were achieved at an HRT of study, biomass growth was recorded at the start and end
6 days, which were 95.8%, 96.2%, 99.7%, and 95.8%, respec- of the experiment. From the visual appearance, rapid
tively. However, increasing the HRT beyond 6 days did not growth was observed in both phase studies, which can be
result in further significant improvements in the removal related to the presence of sufficient nutrients. Initially,
efficiency of these pollutants. The study highlights the the growth of mosquito larva was observed in the reactor,
importance of optimizing the HRT for the efficient removal which was overcome using covering the study area using
of pollutants in ecological wastewater treatment systems. mosquito net. Although the plant was appropriately
washed before its use in the reactor, small organisms like
snails attached to the roots of water hyacinth and frogs
3.4 | Effect of time on treatment were observed. The number of snails increased with time.
performance Their presence showed the effectiveness and replicates
the natural treatment system where other microbiota also
In FPTS with plant-like water hyacinth (rapid growth), help in the remediation of pollutants. At the beginning of
timely harvesting plays a critical role in treatment perfor- the second phase study, yellow striped armyworm, Spo-
mance. When a higher initial plant density is used, it doptera ornithogalli, was observed, reducing leaf growth.
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
124 PRASAD ET AL.

The reactor was restarted with new seeding of water hya- starts. In the meantime, the plant occupies space in the
cinth, and the development of yellow striped armyworm, treatment system with overall performance close to nega-
Spodoptera ornithogalli, was not observed. tive since, during the degradation process, nutrients are
The measurement of water hyacinth biomass showed released back into the water. When the matured plant,
that density and HRT influenced the growth. For phase I, known as the mother plant, has produced enough stolon
an increase in the biomass weight was inversely plants, these baby plants in the growing phase have high
proportional to the initial plant density. The water hya- nutrient uptake potential compared to the mother plant.
cinth initial weight was 300, 600, 900, and 1200 g, which Initially, the mother plant provides nutrients for the
increased to 386 g (128.66%), 528 g (88.0%), 670 g growth and development of the baby plants using stolon,
(174.44%), and 750 g (62.50%) for D1, D2, D3, and D4, and once the baby plants develop roots, the stolon and
respectively (Figure 4D). An increase in weight was mother plant lose their purpose and start decomposing.
observed between the initial and final weights and in To avoid decomposition, harvesting the mother plant
between the final weights. The number of water hyacinth becomes crucial. Moreover, the increase in density
increased to 10, 19, 25, and 28 from 4, 7, 13, and 16 in reduces plant productivity, causing significant differences
reactors D1, D2, D3, and D4, respectively. A higher in treatment performance. The increased density causes a
increase in weight can be attributed to the increase in the sizeable dying and decaying process and considerably
baby plants’ numbers through stolon. Lower plant den- reduces the treatment performance.
sity showed the highest increased weight due to the The primary mechanism for nitrogen and phospho-
increased free surface area for baby plant growth and rous removal was through water hyacinth uptake. The
multiplication. However, when this free surface reduces harvested water hyacinth can be used as a rich source of
by increasing the plant density, it reduces stolon growth; nitrogen and phosphorous for soil enrichment. The
hence the fight for space, light, and nutrients produces most feasible and economical method of utilization is
many immature baby plants. compost production or use as such in gardens. The bio-
For phase II, water hyacinth weight was reduced with mass can be decomposed to form a compost to increase
an increase in HRT. The initial water hyacinth weight soil fertility by providing a source of carbon, nitrogen,
was 600 g in all the reactors, and the final weight was and potassium.[54]
1365, 1208, 1058, and 1032 g for reactors H1, H2, H3, and
H4, respectively. The corresponding increased weight
was 765 g (127.50%), 608 g (101.33%), 458 g (76.33%), and 3.7 | Optimization and validation
432 g (72.0%) for reactors H1, H2, H3, and H4, respec- using ANN
tively. The increase in weight was observed between the
initial and final weight (Figure 5D). Initially, 7 baby To mathematically validate the optimization results,
water hyacinths were seeded into the reactor, which ANN was used. ANN model was used by Behera et al.[55]
increased to 19, 17, 16, and 15 in reactors H1, H2, H3, to inspect and predict CH4 (%) using extracted LPG and
and H4, respectively. leachate. Pandey et al.[56] studied the impact of HRT and
The biomass weight was greater in the reactor with biodegradability for sludge acidogenesis using opera-
higher HRT than in those with lower HRTs. The tional parameters of the reactor through ANN, and other
increased retention time increases the plant’s nutrient studies show how machine learning is important in natu-
uptake and hence can relate to the increased growth. In ral sciences from waste to energy production.[24,32,33,57,58]
the case of short retention time, the plant’s nutrient In the current study, ANN model was used with water
absorption reduces, as seen through treatment perfor- temperature, pH, TDS, phosphate, COD, and
mance. The current study showed that growth and multi- ammonium-nitrogen as input variables and phosphate,
plication reduce when the water hyacinth plant is short COD, and ammonium-nitrogen as targets for water hya-
on nutrients. cinth density and HRT optimization (input provided as
supplementary). In the obtained results from the output
it was observed that the 20 optimum hidden neurons
3.6 | Harvesting and use of harvested were directly dependent on the predicted phosphate,
water hyacinth COD, and ammonium-nitrogen, with water hyacinth
density and HRT optimization from ANN model as
Harvesting is a crucial parameter in GW treatment using shown in Figure 6.
a floating plant (water hyacinth). The nutrient uptake The backpropagation model of ANN was used to
capacity of water hyacinth reduces with age as the plant study the water hyacinth harvesting pattern behaviour by
moves towards maturity; after that, the degradation selecting a model with the highest R value and lower
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
PRASAD ET AL. 125

F I G U R E 6 The schematic diagram for the hidden neural network used for water hyacinth density optimization and effect of hydraulic
retention time (HRT) study. COD, chemical oxygen demand; TDS, total dissolved solids.

MSE value for the purpose of training, testing, and HRT and output parameters more accurately with
validating the datasets. The model of ANN was used to the selected input values which were collected from the
optimize and predict the density of water hyacinth and laboratory investigation. The data obtained from the
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
126 PRASAD ET AL.

F I G U R E 7 Comparison of predicted and experimental phosphate, chemical oxygen demand (COD), and ammonium-nitrogen removal
for the optimum (A) water hyacinth density (2 kg/m2) and (B) hydraulic retention time (48 h).

experimental work was used to train and construct the 4 | CONCLUSIONS


neural network model. Out of the 31 experimental data
points, 70% were used to train the model and the remain- This study investigated the effect of plant density and HRT
ing 30% (15% + 15%) for the testing, training, and valida- on the GW treatment capacity of FPTS using water hya-
tion of the model. Continuous monitoring data of cinth. The study found that a water hyacinth density of
phosphate, COD, and ammonium-nitrogen, analyzed 2 kg/m2 and HRT of 48 h achieved an average removal
daily during the experiment, was further used to predict efficiency of 1.01 ± 9.60%, 44.91 ± 8.54%, 97.92 ± 0.76%,
phosphate, COD, and ammonium-nitrogen removal 59.62 ± 7.97%, 73.80 ± 23.68%, and 91.92 ± 10.38% for
using the neural network model. The obtained results TDS, TSS, turbidity, COD, ammonium-nitrogen, and phos-
showed the phosphate, COD, and ammonium-nitrogen phate, respectively. The results were validated using ANN,
removal for water hyacinth density and HRT optimiza- which showed a strong correlation coefficient (R > 0.99).
tion as shown in Figure 7A,B, respectively. The present The study suggested that water hyacinth needs to be har-
study also reflected the predicted and actual phosphate, vested every 20–22 days to maintain its effectiveness in the
COD, and ammonium-nitrogen removal up to ±4% error. treatment system. However, further studies are required to
The training of model was performed until the value of be investigated for the long-term treatment performance
R reached up to a constant value near to 1, and the MSE of FPTS using water hyacinth and to develop treatment
lower value was predicted with the help of Equation (3). systems that can improve the removal of solids. Overall,
The training (R) coefficient for phosphate, COD, and the findings of this study suggested that FPTS using water
ammonium-nitrogen removal was 0.99 for each, which hyacinth could be an effective decentralized treatment
showed that the ANN model efficiently learned the inter- option for wastewater treatment.
disciplinary relation between input and output variables,
as shown in Figure 6. The validation and test coeffi- AUTHOR CONTRIBUTIONS
cient®for each category was 1, concluding that the model Rajnikant Prasad: Conceptualization; data curation;
was efficient enough to generalize and test the data with formal analysis; investigation; methodology; writing –
similar order capacity. The model results showed that original draft. Dayanand Sharma: Methodology;
the most outstanding performance after neuron optimi- resources; writing – review and editing. Ashutosh Kumar
zation was with 6–20–1 topology, and it was selected Pandey: Resources; writing – review and editing.
for the developed model for phosphate, COD, and Kunwar D. Yadav: Project administration; resources; super-
ammonium-nitrogen removal for water hyacinth den- vision; writing – review and editing. Sunil Kumar: Writing
sity and HRT optimization, respectively, as shown in – review and editing. Hussameldin Ibrahim: Data cura-
Figures 6 and 7. tion; validation; writing – review and editing.
These figures showed the ANN output plots in train-
ing, validation, testing, and all datasets, as well as the F U N D I N G IN F O R M A T I O N
R values and MSE of training datasets for water hyacinth This research did not receive any specific grant from pub-
density optimization and HRT. lic, commercial, or not-for-profit funding agencies.
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
PRASAD ET AL. 127

FI NAN CIA L I NT ER ES TS [16] R. Prasad, D. Sharma, K. D. Yadav, H. Ibrahim, Can. J. Chem.


The authors declare they have no financial interests. Eng. 2021, 100, 439.
[17] H. Hu, X. Li, S. Wu, C. Yang, Bioresour. Technol. 2020, 315,
123809.
N O N - F I N A N CI A L IN TE R E S T S
[18] M. Shah, H. N. Hashmi, A. Ali, A. R. Ghumman, J. Environ.
The authors have no relevant financial or non-financial
Health Sci. Eng. 2014, 12, 1.
interests to disclose.
[19] V. Arunbabu, S. Sruthy, I. Antony, E. V. Ramasamy, Journal
of Water Process Engineering 2015, 7, 153.
CONFLICT OF INTEREST STATEMENT [20] R. H. Kadlec, R. Knight, J. Vymazal, H. Brix, P. Cooper,
The authors declare no conflict of interest. R. Haberl, Constructed wetlands for pollution control: processes,
performance, design and operation, IWA Publishing, London
P EE R R EV IE W 2000.
The peer review history for this article is available at [21] Y. M. Patil, V. K. Patki, S. Jahagirdar, R. Karale,
https://www.webofscience.com/api/gateway/wos/peer-review/ V. Angathekar, Mater. Today: Proc. 2021, 45(7), 6946.
[22] K. D. Navamani, B. C. H. Aditya Narayana, M. Arivazhagan,
10.1002/cjce.25027.
J. Environ. Manage. 2018, 206, 69.
[23] F. M. Elfghi, Chem. Eng. Res. Des. 2016, 113, 264.
DATA AVAILABILITY STATEMENT [24] K. K. Kishore, M. Singh, N. Khatri, Fuel 2023, 334, 126549.
The data that support the findings of this study are avail- [25] N. Khatri, A. K. Vyas, A. S. H. Abdul-Qawy, E. R. Rene,
able from the corresponding author upon reasonable Environ. Res. 2023, 217, 114843.
request. [26] M. Maghsoudi, M. Ghaedi, A. Zinali, A. M. Ghaedi,
M. H. Habibi, Spectrochim. Acta, Part A 2015, 134, 1.
ORCID [27] N. G. Turan, B. Mesci, O. Ozgonenel, Chem. Eng. J. 2011,
173, 98.
Hussameldin Ibrahim https://orcid.org/0000-0002-
[28] A. Hosseinzadeh, M. Baziar, H. Alidadi, J. L. Zhou, A. Altaee,
7118-2580 A. A. Najafpoor, S. Jafarpour, Bioresour. Technol. 2020, 303,
122926.
R EF E RE N C E S [29] D. Sharma, A. K. Pandey, K. D. Yadav, S. Kumar, Bioresour.
[1] United Nations, The World’s Cities in 2018, Data Booklet Technol. 2021, 324, 124672.
(ST/ESA/SER.A/417). 2018, https://digitallibrary.un.org/ [30] D. B. Das, T. Thirakulchaya, L. Deka, N. S. Hanspal, Environ.
record/3799524?ln=en (accessed: April 2023). Processes 2015, 2, 1.
[2] S. Pradhan, S. G. Al-Ghamdi, H. R. Mackey, Int. Biodeterior. [31] A. Witek-Krowiak, K. Chojnacka, D. Podstawczyk, A. Dawiec,
Biodegrad. 2019, 145, 104792. K. Pokomeda, Bioresour. Technol. 2014, 160, 150.
[3] A. K. Vuppaladadiyam, N. Merayo, A. Blanco, J. Hou, [32] N. Khatri, K. K. Khatri, A. Sharma, Water Sci. Technol. 2019,
D. D. Dionysiou, M. Zhao, Algal Res. 2018, 35, 106. 80, 213.
[4] S. E. R. Mahunon, M. P. Aina, A. V. O. Akowanou, [33] N. Khatri, K. K. Khatri, A. Sharma, Journal of Water Process
E. K. Kouassi, B. K. Yao, K. Adouby, P. Drogui, Environ. Sci. Engineering 2020, 37, 101477.
Pollut. Res. 2018, 25, 29219. [34] A. Valipour, V. K. Raman, Y. H. Ahn, Water 2015, 7, 329.
[5] F. Li, X. He, A. Srishti, S. Song, H. T. W. Tan, D. J. Sweeney, [35] B. Ait-Amir, P. Pougnet, A. El Hami, in Embedded Mechatro-
S. Ghosh, C.-H. Wang, Bioresour. Technol. 2021, 327, 124809. nic Systems (Eds: A. El Hami, P. Pougnet), ISTE Press, London
[6] S. Rezania, M. Ponraj, M. Fadhil Md Din, S. Chelliapan, 2015, p. 151.
F. Md Sairan, Desalin. Water Treat. 2014, 57, 1. [36] A. Hailu, E. G. Degaga, Journal of Natural Sciences Research
[7] H. Qin, Z. Zhang, M. Liu, H. Liu, Y. Wang, X. Wen, Y. Zhang, 2018, 8, 94.
S. Yan, Ecological Engineering 2016, 95, 753. [37] D. J. Kriticos, S. Brunel, PLoS One 2016, 11, 1.
[8] P. Sharma, A. K. Pandey, A. Udayan, S. Kumar, Bioresour. [38] D. Selvaraj, G. Velvizhi, J. Environ. Manage. 2021, 286, 112253.
Technol. 2021, 326, 124750. [39] C. O. Akinbile, T. A. Ogunrinde, H. Che bt Man, H. A. Aziz,
[9] S. E. Agarry, K. M. Oghenejoboh, G. K. Latinwo, Int. J. Phytorem. 2016, 18, 54.
C. N. Owabor, Environ. Technol. 2018, 41, 1793. [40] R. Bhutiani, D. R. Khanna, V. Tyagi, F. Ahamad, International
[10] J. G. Rangel-Peraza, K. Mendivil-García, C. I. G. Cedillo-Herrera, Journal of Research 2015, 3, 1.
J. J. Rochín-Medina, A. E. Rodríguez-Mata, Y. A. Bustos- [41] J. Wang, G. Fu, W. Li, Y. Shi, J. Pang, Q. Wang, W. Lü, C. Liu,
Terrones, Environ. Technol. 2019, 40, 633. J. Liu, Aquaculture and Fisheries 2018, 3, 22.
[11] B. Lu, Z. Xu, J. Li, X. Chai, Ecological Engineering 2018, [42] S. Rezania, M. F. M. Din, S. M. Taib, F. A. Dahalan, A. R. Songip,
110, 18. L. Singh, H. Kamyab, Int. J. Phytorem. 2016, 18, 679.
[12] C. O. Akinbile, M. S. Yusoff, Int. J. Phytorem. 2012, 14, 201. [43] D. O. Olukanni, K. O. Kokumo, American Journal of Engineering
[13] S. Tripathi, P. Sharma, D. Purchase, R. Chandra, Bioresour. Research 2013, 2, 450.
Technol. 2021, 333, 125192. [44] G. R. Munavalli, P. S. Saler, Water Sci. Technol. 2009,
[14] J. Lu, Z. Fu, Z. Yin, J. Environ. Sci 2008, 20, 513. 59, 713.
[15] A. K. Pandey, V. K. Gaur, A. Udayan, S. Varjani, S.-H. Kim, [45] N. T. Loan, N. M. Phuong, N. T. N. Anh, Environ. Eng.
J. W. C. Wong, Chemosphere 2021, 272, 129936. Manage. J. 2014, 13, 2031.
1939019x, 2024, 1, Downloaded from https://onlinelibrary.wiley.com/doi/10.1002/cjce.25027 by Nat Prov Indonesia, Wiley Online Library on [10/07/2024]. See the Terms and Conditions (https://onlinelibrary.wiley.com/terms-and-conditions) on Wiley Online Library for rules of use; OA articles are governed by the applicable Creative Commons License
128 PRASAD ET AL.

[46] S. Fazal, B. Zhang, Q. Mehmood, Ecological Engineering 2015, [56] P. A. Kumar, J. Park, A. Muhorakeye, R. Morya, S. H. Kim,
84, 551. Bioresour. Technol. 2023, 372, 128629.
[47] C. R. Penton, J. L. Deenik, B. N. Popp, G. L. Bruland, [57] A. K. Pandey, J. Park, J. Ko, H. H. Joo, T. Raj, L. K. Singh,
P. Engstrom, D. S. Louis, J. Tiedje, Soil Biol. Biochem. 2013, N. Singh, S. H. Kim, Bioresour. Technol. 2023, 370, 128502.
57, 362. [58] D. Singh, D. Chavan, A. K. Pandey, L. Periyaswami, S. Kumar,
[48] M. Kumari, B. D. Tripathi, Ecological Engineering 2014, 62, 48. Sci. Total Environ. 2021, 785, 147243.
[49] W. H. T. Ting, I. A. W. Tan, S. F. Salleh, N. A. Wahab, Journal
of Water Process Engineering 2018, 22, 239.
SU PP O R TI N G I N F O RMA TI O N
[50] A. Bednarek, S. Szklarek, M. Zalewski, Ecohydrol. Hydrobiol.
Additional supporting information can be found online
2014, 14, 132.
[51] S. R. M. Kutty, S. N. I. Ngatenah, M. H. Isa, A. Malakahmad, in the Supporting Information section at the end of this
Engineering Technology 2009, 60, 826. article.
[52] M. Truu, J. Juhanson, J. Truu, Sci. Total Environ. 2009, 407,
3958.
[53] M. L. Merino-Solís, E. Villegas, J. de Anda, A. Lopez-L opez, How to cite this article: R. Prasad, D. Sharma,
Water (Switzerland) 2015, 7, 1149. A. K. Pandey, K. D. Yadav, S. Kumar, H. Ibrahim,
[54] W. Su, Q. Sun, M. Xia, Z. Wen, Z. Yao, Resources 2018, 7, 46. Can. J. Chem. Eng. 2024, 102(1), 113. https://doi.
[55] S. K. Behera, S. K. Meher, H. S. Park, Clean Technol. Environ. org/10.1002/cjce.25027
Policy 2015, 17, 443.

You might also like