Professional Documents
Culture Documents
Vol II Omsanti Path(Farena Chowk) Omsatiya Estimation
Vol II Omsanti Path(Farena Chowk) Omsatiya Estimation
Submitted by:
Hatemalo Engineering And Construcation Pvt.Ltd
Sainamaina-08, Rupandehi
email:
Omsatiya Rural Municipality
Office of the Rural Municipal Executive
Hati Pharsatikar
Rupandehi
Lumbini Province
Nepal
SALIENT FEATURES
2 Location:
Local Level Omsatiya Rural Municipality
Province: Lumbini Province
District: Rupandehi
Geographical feature:
i) Climate: Temperate climate with dry winter and warm summer
ii) Geology: Terai
iii) Meteorology: Unevenly distributed monsoon precipitation
3 Classification:
Classification: Class IV
Existing Surface: Earthen
Proposed Surface: Premix
4 Length Of Road
i) Starting Point: 0+000.00
ii) End Point: 2+040.64
iii) Total Road Length (Km): 2.04064
End Point
Latitude 27°32'53.47"N
Longitude 83°27'54.68"E
SALIENT FEATURES
Design Speed 25
Side Drain Shape rectangular
Maximum Grade 12%
7 Pavement Design:
Pavement Volume
Premix 239.98
Base 1,799.82
Sub base 2,907.91
Concrete -
SUMMARY OF COST
Name of the Road :Omsanti path(Farena chowk) Omsatiya
Chainage : 0+000 To 2+040.64
S.N. Description of works Unit Quantity Rate, (NRs) Amount (NRs) Remarks
A REF General Item
Insurance of works, plants, materials, loss and damage
to equipments, Contractor's workmen and employees
1.1 GCC 13 PS 1.00 100,000.00 100,000.00
and third party insurance against damage to other
persons and property.
Provide, operate and maintain Quality Control Laboratory
including but not limited to equipment (listed in Appendix
2 and 3 of SP/SS), accessories, personnel and
504
1.3 DoR
consumables for both field testing facilities and off-site PS 1.00 1,600,000.00 1,600,000.00
test with manpower and handing over to the Employer
after completion as per specification and instruction of
engineer all complete. [SP/SS-504]
Reallocation of services and minor infrastructures as per
111
1.4 DoR
specification and as instructed by the Project PS 1.00 150,000.00 150,000.00
Manager.[SP/SS-111]
Provide and maintain traffic safety, Occupation Health
104 and Safety (OHS) as per special provision,control
1.5 DoR
LS 1.00 100,000.00 100,000.00
measures and temporary diversions during construction
as instructed by the Engineer.[SP/SS-104]
Provide and installation of project information board of
size 1.80 m X 1.2 m along with iron posts including
110 (b)
1.6 DoR
excavation, concreting,backfillingetc all complete as per Nos. 2.00 6,228.48 12,456.95
DoR Standard Specifixcation for Road and Bridge
Works.[SS 110 (b) DoR]
Sub - Total (A) 1,962,456.95
B Site Clearance and Earthworks
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees
girth up to 300 mm, removal of stumps of trees cut earlier
201
0 DoR
and disposal of unserviceable materials and stacking of
serviceable Material to be used or auctioned, up to a lead
of 1000 meters including removal and disposal of top
organic soil not exceeding 150 mm in thickness.
(A) In area of light jungle (less than 15 number per 100
2.1 201 Sqm 1,500.00 6.45 9,679.32
sqm)
(B) In area of Thorny jungle (more than 15 number per
2.2 201 Sqm - 6.68 -
100 sqm)
Dismantling of existing stone masonry structures, sorting
the dismantled Material, disposal of unserviceable
2.4 202 cum - 1,832.30 -
Material and stacking the serviceable Material with all lifts
and lead of 1000 meters
Removal of telephone/Electric poles including excavation
and dismantling of foundation concreter and dlines under
2.1 202 the supervision of concerned department, dsiposal with all Nos. - 953.70 -
the lifts and upto a lead of 1000 meters and stacking the
serviceable and unserceable material separately
Sub - Total (B) 9,679.32
C Earthwork
S.N. Description of works Unit Quantity Rate, (NRs) Amount (NRs) Remarks
Structure foundation excavation for all types of soil/rock
by both manual and mechanical means as per drawing
3.2 907 and technical specification, including removal of stumps m3 45.33 126.13 5,717.17
and other deleterious matter, with all lifts and lead as
drawing and instruction of engineer. [SS-907]
S.N. Description of works Unit Quantity Rate, (NRs) Amount (NRs) Remarks
Providing mechanically woven double twisted crates /
mattress(Heavy Zinc coated Hexagonal mesh type
100X120 mm, mesh wire 3 mm, selvedge wire 3.90 mm,
SS DOR lacing wire 2.40 mm ) including rolling cutting and with
5.5 2402 lacing wire and binding wire and filling stone/boulder in
m3 - 4,163.11 -
gabion boxes/mattress etc. including dressing, bedding,
bonding all complete as per drawing and technical
specification[SS 2402]
Providing and laying, fitting and placing HYSD bar
SS DOR
5.6 2014
reinforcement in superstructure complete as per drawing Kg - 132.71 -
and technical specification [SS 2014]
SS DOR
7.3 1506
Supply and place 5th kilometer stone. [SS DOR1506] Nos. 1.00 10,408.63 10,408.63
S.N. Description of works Unit Quantity Rate, (NRs) Amount (NRs) Remarks
Cost Per Km of the road inclusive of VAT and Base Cost 18,089,514.37 IX=III/2.04064
1 General
1.1 GCC 13 Insurance of works, plants, materials, loss and damage
to equipments, Contractor's workmen and employees
and third party insurance against damage to other persons PS 1 1.00
and property.
1.2 SCC - Provide and maintain Site Office on rental basis (two
rooms Size (3mx4m)) at location acceptable to the
project manager with in the Contract package with
Mths 24 24.00
accomadation facilities for the Supervision Team as per
Project Manager instruction
201 DoR Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable Material to be used or auctioned, up to a lead
of 1000 meters including removal and disposal of top
organic soil not exceeding 150 mm in thickness.
2.1 201 (A) In area of light jungle (less than 15 number per 100
Sqm 1,500.00 1,500.00
sqm)
2.2 201 (B) In area of Thorny jungle (more than 15 number per 100
Sqm - -
sqm)
2.4 202 Dismantling of existing stone masonry structures, sorting
the dismantled Material, disposal of unserviceable Material
cum 0 -
and stacking the serviceable Material with all lifts and lead
of 1000 meters
2.1 202 Removal of telephone/Electric poles including excavation
and dismantling of foundation concreter and dlines under
the supervision of concerned department, dsiposal with all
Nos. 0 -
the lifts and upto a lead of 1000 meters and stacking the
serviceable and unserceable material separately
3 Earthwork
3.1 905 Roadway excavation in all types of soil/rock by both
manual and mechanical means as per drawing and
technical specification, including removal of stumps and
m3 693.43 - 693.43
other deleterious matter, with all lifts and lead as drawing
and instruction of engineer. [SS-905, SP/SS-903]
4.6 1302 Providing and applying Tack coat with Hot Bitumen at
Specified rate on the prepared non bituminous surfaces Ltr 7,199.27 7,199.27
including cleaning as per Technical Specification .
4.9 1310 Providing and laying close-graded premix surfacing cum
material of 20 mm thickness composed of 11.2 mm to 0.09
mm or 13.2 mm to 0.09 mm aggregates using bitumen as
239.98 239.98
wearing course on a previously prepared base, including
mixing in a suitable plant as per Drawing and Technical
Specifications.
5 Structural/ Side Drain/ Cross Drainage Works
5.1 SS DOR Providing and laying of Random rubble stone masonry
2600,2607 works in cement mortar MM7.5 including pipes for
& 3109
weepholes in foundation and in structure as per drawing m3 - - 20.10 - 20.10
and technical specification [SS DOR 2600,2607 & 3109]
5.2 SS DOR Providing and laying of stone pitching on slopes laid over
2416 prepared filter media including boulder apron laid dry in
m3 - -
front of toe of embankment complete as per drawing and
technical specification [ss 2416]
Prepared By: Checked By: Approved By:
12 of 90
5.4 1005 Providing and laying of hand packed stone solling with 150
to 200 mm thick stones and packing with smaller stones on
m3 - - - -
prepared surface as per drawing and technical
specifications [SS 1005]
5.5 SS DOR Providing mechanically woven double twisted crates /
2402 mattress(Heavy Zinc coated Hexagonal mesh type
100X120 mm, mesh wire 3 mm, selvedge wire 3.90 mm,
lacing wire 2.40 mm ) including rolling cutting and with
m3 - - - -
lacing wire and binding wire and filling stone/boulder in
gabion boxes/mattress etc. including dressing, bedding,
bonding all complete as per drawing and technical
specification[SS 2402]
5.6 SS DOR Providing and laying, fitting and placing HYSD bar
2014 reinforcement in superstructure complete as per drawing Kg - - - -
and technical specification [SS 2014]
7 Road Furnishing
7.2 SS Supply and place one kilometer stone [SS DOR1506]
DOR1506
Nos. 1.00 1.00
7.3 SS DOR Supply and place 5th kilometer stone. [SS DOR1506]
1506
Nos. 1.00 1.00
7.8 1504 Providing and laying of hot applied thermoplastic compound at least Sqm
2mm thick including reflectorizing glass beads as per DOR Traffic sign
manual/Specifications. The finished surface to be level, uniform and free 61.22 61.22
from streaks and holes.[SS DOR1504]
8 DAY WORKS
8.1 Supply of labour as required as per preamble and as
instructed by the Engineer.
Unskilled labour Nos 50.00
skilled labour Nos 50.00
8.2 Supply of excavator for maintenance of road or else as
required and instructed by engineer including operator and Hrs 100.00
other charges
8.3 Provide Built up Drawing as completed Nos 1.00 1.00
Total site
Total
clearance
Length Stte Clearance Width (m) Remarks
quantity
(m)
(m2)
A. Light Jungle 500.00 3 1500
B. Thorny Jungle 0.00 3 0
14 of 90
Omsatiya Rural Municipality
Office of the Rural Municipal Executive
Hati Pharsatikar
Rupandehi
Lumbini Province
Nepal
Name of the Road :Omsanti path(Farena chowk) Omsatiya
Chainage : 0+000 To 2+040.64
Contract No :
EARTHWORK CALCULATION SHEET FOR ROADWAY AND DRAIN
ROADWAY DRAIN
X- Area(m2) Mean Area(m2) Volume (m3) Soil Classification Drain
Length Cutting
Ch. Ordinary Soil Cutting Remarks
(m) Cutting Filling Area
Cutting Filling Cutting Vol Filling Vol volume
Area Area (m2)
% (m3) (m3)
Part 1
0+000.00 0 0.47 - 0.24 - - - 100% - - -
0+020.00 20 - 1.69 0.24 0.85 4.70 16.90 100% 4.70 - -
0+040.00 20 - 3.21 - 2.45 - 49.00 100% - - -
0+060.00 20 - 1.51 - 2.36 - 47.20 100% - - -
0+080.00 20 0.01 0.70 0.01 1.11 0.10 22.10 100% 0.10 - -
0+100.00 20 0.54 0.04 0.28 0.37 5.50 7.40 100% 5.50 - -
0+120.00 20 0.45 0.12 0.50 0.08 9.90 1.60 100% 9.90 - -
0+140.00 20 - 2.25 0.23 1.19 4.50 23.70 100% 4.50 - -
0+160.00 20 0.23 0.84 0.12 1.55 2.30 30.90 100% 2.30 - -
0+178.00 18 - 1.39 0.12 1.12 2.07 20.07 100% 2.07 - -
0+179.00 1 - - - 0.70 - 0.70 100% - - -
0+180.00 1 - 1.34 - 0.67 - 0.67 100% - - -
0+200.00 20 0.05 1.26 0.03 1.30 0.50 26.00 100% 0.50 - -
0+220.00 20 0.07 1.36 0.06 1.31 1.20 26.20 100% 1.20 - -
0+240.00 20 0.05 1.51 0.06 1.44 1.20 28.70 100% 1.20 - -
0+260.00 20 0.47 0.22 0.26 0.87 5.20 17.30 100% 5.20 - -
0+280.00 20 0.45 0.31 0.46 0.27 9.20 5.30 100% 9.20 - -
0+300.00 20 0.40 - 0.43 0.16 8.50 3.10 100% 8.50 - -
0+320.00 20 0.02 0.41 0.21 0.21 4.20 4.10 100% 4.20 - -
0+340.00 20 0.02 0.45 0.02 0.43 0.40 8.60 100% 0.40 - -
0+360.00 20 0.02 1.14 0.02 0.80 0.40 15.90 100% 0.40 - -
0+380.00 20 0.10 0.80 0.06 0.97 1.20 19.40 100% 1.20 - -
Page 15 of 90
ROADWAY DRAIN
X- Area(m2) Mean Area(m2) Volume (m3) Soil Classification Drain
Length Cutting
Ch. Ordinary Soil Cutting Remarks
(m) Cutting Filling Area
Cutting Filling Cutting Vol Filling Vol volume
Area Area (m2)
% (m3) (m3)
0+400.00 20 0.13 1.07 0.12 0.94 2.30 18.70 100% 2.30 - -
0+420.00 20 0.06 1.49 0.10 1.28 1.90 25.60 100% 1.90 - -
0+440.00 20 0.32 2.06 0.19 1.78 3.80 35.50 100% 3.80 - -
0+460.00 20 0.05 0.28 0.19 1.17 3.70 23.40 100% 3.70 - -
0+480.00 20 - 1.17 0.03 0.73 0.50 14.50 100% 0.50 - -
0+500.00 20 0.02 1.27 0.01 1.22 0.20 24.40 100% 0.20 - -
0+520.00 20 - 2.23 0.01 1.75 0.20 35.00 100% 0.20 - -
0+540.00 20 0.03 1.14 0.02 1.69 0.30 33.70 100% 0.30 - -
0+560.00 20 1.38 - 0.71 0.57 14.10 11.40 100% 14.10 - -
0+580.00 20 0.31 0.04 0.85 0.02 16.90 0.40 100% 16.90 - -
0+600.00 20 0.74 0.14 0.53 0.09 10.50 1.80 100% 10.50 - -
0+620.00 20 0.15 0.12 0.45 0.13 8.90 2.60 100% 8.90 - -
0+634.20 14.2 0.39 - 0.27 0.06 3.83 0.85 100% 3.83 - -
Part 2
0+000.00 0 0.22 0.20 0.31 0.10 - - 100% - - -
0+020.00 20 0.81 1.34 0.52 0.77 10.30 15.40 100% 10.30 - -
0+040.00 20 0.06 1.39 0.44 1.37 8.70 27.30 100% 8.70 - -
0+060.00 20 0.83 - 0.45 0.70 8.90 13.90 100% 8.90 - -
0+080.00 20 0.01 0.48 0.42 0.24 8.40 4.80 100% 8.40 - -
0+081.00 1 - - 0.01 0.24 0.01 0.24 100% 0.01 - -
0+082.00 1 0.04 0.43 0.02 0.22 0.02 0.22 100% 0.02 - -
0+100.00 18 0.06 1.29 0.05 0.86 0.90 15.48 100% 0.90 - -
0+120.00 20 0.26 0.83 0.16 1.06 3.20 21.20 100% 3.20 - -
0+140.00 20 0.60 0.45 0.43 0.64 8.60 12.80 100% 8.60 - -
0+160.00 20 0.75 0.03 0.68 0.24 13.50 4.80 100% 13.50 - -
0+180.00 20 0.98 0.05 0.87 0.04 17.30 0.80 100% 17.30 - -
0+200.00 20 0.84 0.02 0.91 0.04 18.20 0.70 100% 18.20 - -
0+220.00 20 0.71 0.04 0.78 0.03 15.50 0.60 100% 15.50 - -
0+240.00 20 0.44 0.09 0.58 0.07 11.50 1.30 100% 11.50 - -
0+260.00 20 0.33 0.16 0.39 0.13 7.70 2.50 100% 7.70 - -
0+280.00 20 0.33 0.46 0.33 0.31 6.60 6.20 100% 6.60 - -
0+300.00 20 0.81 1.01 0.57 0.74 11.40 14.70 100% 11.40 - -
0+320.00 20 0.63 0.40 0.72 0.71 14.40 14.10 100% 14.40 - -
0+340.00 20 0.29 0.97 0.46 0.69 9.20 13.70 100% 9.20 - -
0+360.00 20 1.18 0.27 0.74 0.62 14.70 12.40 100% 14.70 - -
0+380.00 20 0.45 0.46 0.82 0.37 16.30 7.30 100% 16.30 - -
0+400.00 20 0.08 0.50 0.27 0.48 5.30 9.60 100% 5.30 - -
Page 16 of 90
ROADWAY DRAIN
X- Area(m2) Mean Area(m2) Volume (m3) Soil Classification Drain
Length Cutting
Ch. Ordinary Soil Cutting Remarks
(m) Cutting Filling Area
Cutting Filling Cutting Vol Filling Vol volume
Area Area (m2)
% (m3) (m3)
0+420.00 20 - 0.79 0.04 0.65 0.80 12.90 100% 0.80 - -
0+421.00 1 - - - 0.40 - 0.40 100% - - -
0+422.00 1 - 0.86 - 0.43 - 0.43 100% - - -
0+440.00 18 - 1.57 - 1.22 - 21.87 100% - - -
0+460.00 20 - 1.60 - 1.59 - 31.70 100% - - -
0+480.00 20 - 1.17 - 1.39 - 27.70 100% - - -
0+500.00 20 0.35 1.29 0.18 1.23 3.50 24.60 100% 3.50 - -
0+520.00 20 - 2.10 0.18 1.70 3.50 33.90 100% 3.50 - -
0+540.00 20 - 2.46 - 2.28 - 45.60 100% - - -
0+560.00 20 - 1.83 - 2.15 - 42.90 100% - - -
0+580.00 20 - 2.02 - 1.93 - 38.50 100% - - -
0+600.00 20 0.65 1.35 0.33 1.69 6.50 33.70 100% 6.50 - -
0+620.00 20 1.21 0.22 0.93 0.79 18.60 15.70 100% 18.60 - -
0+640.00 20 1.43 - 1.32 0.11 26.40 2.20 100% 26.40 - -
0+660.00 20 1.89 0.14 1.66 0.07 33.20 1.40 100% 33.20 - -
0+680.00 20 1.14 0.42 1.52 0.28 30.30 5.60 100% 30.30 - -
0+700.00 20 0.01 0.50 0.58 0.46 11.50 9.20 100% 11.50 - -
0+720.00 20 - 1.63 0.01 1.07 0.10 21.30 100% 0.10 - -
0+740.00 20 0.01 1.22 0.01 1.43 0.10 28.50 100% 0.10 - -
0+760.00 20 - 1.30 0.01 1.26 0.10 25.20 100% 0.10 - -
0+780.00 20 - 1.04 - 1.17 - 23.40 100% - - -
0+800.00 20 - 1.64 - 1.34 - 26.80 100% - - -
0+820.00 20 0.26 0.29 0.13 0.97 2.60 19.30 100% 2.60 - -
0+840.00 20 0.42 0.20 0.34 0.25 6.80 4.90 100% 6.80 - -
0+860.00 20 0.85 0.16 0.64 0.18 12.70 3.60 100% 12.70 - -
0+880.00 20 0.77 0.04 0.81 0.10 16.20 2.00 100% 16.20 - -
0+900.00 20 0.95 0.03 0.86 0.04 17.20 0.70 100% 17.20 - -
0+920.00 20 0.73 0.01 0.84 0.02 16.80 0.40 100% 16.80 - -
0+940.00 20 0.11 0.51 0.42 0.26 8.40 5.20 100% 8.40 - -
0+960.00 20 0.27 0.49 0.19 0.50 3.80 10.00 100% 3.80 - -
0+980.00 20 0.61 0.02 0.44 0.26 8.80 5.10 100% 8.80 - -
1+000.00 20 1.71 - 1.16 0.01 23.20 0.20 100% 23.20 - -
1+020.00 20 0.82 - 1.27 - 25.30 - 100% 25.30 - -
1+040.00 20 0.21 0.25 0.52 0.13 10.30 2.50 100% 10.30 - -
1+060.00 20 0.02 0.38 0.12 0.32 2.30 6.30 100% 2.30 - -
1+080.00 20 - 1.13 0.01 0.76 0.20 15.10 100% 0.20 - -
1+100.00 20 0.18 0.17 0.09 0.65 1.80 13.00 100% 1.80 - -
Page 17 of 90
ROADWAY DRAIN
X- Area(m2) Mean Area(m2) Volume (m3) Soil Classification Drain
Length Cutting
Ch. Ordinary Soil Cutting Remarks
(m) Cutting Filling Area
Cutting Filling Cutting Vol Filling Vol volume
Area Area (m2)
% (m3) (m3)
1+120.00 20 0.71 0.09 0.45 0.13 8.90 2.60 100% 8.90 - -
1+140.00 20 0.18 0.24 0.45 0.17 8.90 3.30 100% 8.90 - -
1+149.24 9.24 0.06 0.28 0.12 0.26 1.11 2.40 100% 1.11 - -
Part 3
0+000.00 0 0.42 - 0.21 - - - 100% - - -
0+020.00 20 0.75 0.19 0.59 0.10 11.70 1.90 100% 11.70 - -
0+040.00 20 0.39 0.36 0.57 0.28 11.40 5.50 100% 11.40 - -
0+060.00 20 0.34 0.37 0.37 0.37 7.30 7.30 100% 7.30 - -
0+080.00 20 0.23 0.36 0.29 0.37 5.70 7.30 100% 5.70 - -
0+100.00 20 0.19 0.48 0.21 0.42 4.20 8.40 100% 4.20 - -
0+120.00 20 - 0.87 0.10 0.68 1.90 13.50 100% 1.90 - -
0+140.00 20 - 1.00 - 0.94 - 18.70 100% - - -
0+160.00 20 - 0.69 - 0.85 - 16.90 100% - - -
0+180.00 20 - 1.24 - 0.97 - 19.30 100% - - -
0+200.00 20 - 3.17 - 2.21 - 44.10 100% - - -
0+220.00 20 - 3.47 - 3.32 - 66.40 100% - - -
0+240.00 20 - 2.56 - 3.02 - 60.30 100% - - -
0+257.20 17.2 0.29 0.04 0.15 1.30 2.49 22.36 100% 2.49 - -
Page 18 of 90
Omsatiya Rural Municipality
Office of the Rural Municipal Executive
Hati Pharsatikar
Rupandehi
Lumbini Province
Nepal
Name of the Road :Omsanti path(Farena chowk) Omsatiya
Chainage : 0+000 To 2+040.64
Premix carpet BASE Subbase Prime coat Tack Coat
Total Width
Carriage Extra antistripping
Chainage Length Total Width Including
way Width Widening Area Volume Area Volume Area Volume Volume agent (kg)
Shoulder Area (m2) Volume( Area (m2)
(m2) (m3) (m2) (m3) (m2) (lit) (lit)
m3)
Part 1
0+000.00 0.00 5.5 - 5.50 7.50 0.11 - 0.83 - 1.425 - - - - - -
0+020.00 20.00 5.5 0.25 5.75 7.75 0.12 2.30 0.86 17.25 1.425 28.50 115.0 115.0 115.0 69.0 0.3
0+040.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+060.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+080.00 20.00 5.5 0.35 5.85 7.85 0.12 2.34 0.88 17.55 1.425 28.50 117.0 117.0 117.0 70.2 0.4
0+100.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+120.00 20.00 5.5 0.91 6.41 8.41 0.13 2.57 0.96 19.24 1.425 28.50 128.3 128.3 128.3 77.0 0.4
0+140.00 20.00 5.5 0.86 6.36 8.36 0.13 2.54 0.95 19.07 1.425 28.50 127.2 127.2 127.2 76.3 0.4
0+160.00 20.00 5.5 0.58 6.08 8.08 0.12 2.43 0.91 18.23 1.425 28.50 121.6 121.6 121.6 72.9 0.4
0+178.00 18.00 5.5 0.62 6.12 8.12 0.12 2.20 0.92 16.52 1.425 25.65 110.2 110.2 110.2 66.1 0.3
0+179.00 1.00 5.5 0.62 6.12 8.12 0.12 0.12 0.92 0.92 1.425 1.43 6.1 6.1 6.1 3.7 0.0
0+180.00 1.00 5.5 0.62 6.12 8.12 0.12 0.12 0.92 0.92 1.425 1.43 6.1 6.1 6.1 3.7 0.0
0+200.00 20.00 5.5 0.73 6.23 8.23 0.12 2.49 0.93 18.68 1.425 28.50 124.5 124.5 124.5 74.7 0.4
0+220.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+240.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+260.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+280.00 20.00 5.5 0.25 5.75 7.75 0.11 2.30 0.86 17.24 1.425 28.50 114.9 114.9 114.9 69.0 0.3
0+300.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+320.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+340.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+360.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
Premix carpet BASE Subbase Prime coat Tack Coat
Total Width
Carriage Extra antistripping
Chainage Length Total Width Including
way Width Widening Area Volume Area Volume Area Volume Volume agent (kg)
Shoulder Area (m2) Volume( Area (m2)
(m2) (m3) (m2) (m3) (m2) (lit) (lit)
m3)
0+380.00 20.00 5.5 0.01 5.51 7.51 0.11 2.21 0.83 16.54 1.425 28.50 110.3 110.3 110.3 66.2 0.3
0+400.00 20.00 5.5 0.06 5.56 7.56 0.11 2.22 0.83 16.68 1.425 28.50 111.2 111.2 111.2 66.7 0.3
0+420.00 20.00 5.5 0.55 6.05 8.05 0.12 2.42 0.91 18.15 1.425 28.50 121.0 121.0 121.0 72.6 0.4
0+440.00 20.00 5.5 1.20 6.70 8.70 0.13 2.68 1.01 20.10 1.425 28.50 134.0 134.0 134.0 80.4 0.4
0+460.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+480.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+500.00 20.00 5.5 0.45 5.95 7.95 0.12 2.38 0.89 17.85 1.425 28.50 119.0 119.0 119.0 71.4 0.4
0+520.00 20.00 5.5 1.20 6.70 8.70 0.13 2.68 1.01 20.10 1.425 28.50 134.0 134.0 134.0 80.4 0.4
0+540.00 20.00 5.5 0.32 5.82 7.82 0.12 2.33 0.87 17.46 1.425 28.50 116.4 116.4 116.4 69.8 0.3
0+560.00 20.00 5.5 0.32 5.82 7.82 0.12 2.33 0.87 17.46 1.425 28.50 116.4 116.4 116.4 69.8 0.3
0+580.00 20.00 5.5 0.24 5.74 7.74 0.11 2.30 0.86 17.23 1.425 28.50 114.9 114.9 114.9 68.9 0.3
0+600.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+620.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+634.20 14.20 5.5 - 5.50 7.50 0.11 1.56 0.83 11.71 1.425 20.23 78.1 78.1 78.1 46.9 0.2
Part 2
0+000.00 0.00 5.5 0.06 5.56 7.56 0.11 - 0.83 - 1.425 - - - - - -
0+020.00 20.00 5.5 0.55 6.05 8.05 0.12 2.42 0.91 18.15 1.425 28.50 121.0 121.0 121.0 72.6 0.4
0+040.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+060.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+080.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+081.00 1.00 5.5 - 5.50 7.50 0.11 0.11 0.83 0.83 1.425 1.43 5.5 5.5 5.5 3.3 0.0
0+082.00 1.00 5.5 - 5.50 7.50 0.11 0.11 0.83 0.83 1.425 1.43 5.5 5.5 5.5 3.3 0.0
0+100.00 18.00 5.5 0.99 6.49 8.49 0.13 2.34 0.97 17.54 1.425 25.65 116.9 116.9 116.9 70.1 0.4
0+120.00 20.00 5.5 2.30 7.80 9.80 0.16 3.12 1.17 23.40 1.425 28.50 156.0 156.0 156.0 93.6 0.5
0+140.00 20.00 5.5 0.82 6.32 8.32 0.13 2.53 0.95 18.96 1.425 28.50 126.4 126.4 126.4 75.9 0.4
0+160.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+180.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+200.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+220.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+240.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
Premix carpet BASE Subbase Prime coat Tack Coat
Total Width
Carriage Extra antistripping
Chainage Length Total Width Including
way Width Widening Area Volume Area Volume Area Volume Volume agent (kg)
Shoulder Area (m2) Volume( Area (m2)
(m2) (m3) (m2) (m3) (m2) (lit) (lit)
m3)
0+260.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+280.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+300.00 20.00 5.5 1.59 7.09 9.09 0.14 2.83 1.06 21.26 1.425 28.50 141.7 141.7 141.7 85.0 0.4
0+320.00 20.00 5.5 2.30 7.80 9.80 0.16 3.12 1.17 23.40 1.425 28.50 156.0 156.0 156.0 93.6 0.5
0+340.00 20.00 5.5 1.29 6.79 8.79 0.14 2.72 1.02 20.36 1.425 28.50 135.8 135.8 135.8 81.5 0.4
0+360.00 20.00 5.5 2.95 8.45 10.45 0.17 3.38 1.27 25.35 1.425 28.50 169.0 169.0 169.0 101.4 0.5
0+380.00 20.00 5.5 1.41 6.91 8.91 0.14 2.76 1.04 20.72 1.425 28.50 138.2 138.2 138.2 82.9 0.4
0+400.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+420.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+421.00 1.00 5.5 - 5.50 7.50 0.11 0.11 0.83 0.83 1.425 1.43 5.5 5.5 5.5 3.3 0.0
0+422.00 1.00 5.5 - 5.50 7.50 0.11 0.11 0.83 0.83 1.425 1.43 5.5 5.5 5.5 3.3 0.0
0+440.00 18.00 5.5 - 5.50 7.50 0.11 1.98 0.83 14.85 1.425 25.65 99.0 99.0 99.0 59.4 0.3
0+460.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+480.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+500.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+520.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+540.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+560.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+580.00 20.00 5.5 0.12 5.62 7.62 0.11 2.25 0.84 16.85 1.425 28.50 112.3 112.3 112.3 67.4 0.3
0+600.00 20.00 5.5 2.12 7.62 9.62 0.15 3.05 1.14 22.85 1.425 28.50 152.3 152.3 152.3 91.4 0.5
0+620.00 20.00 5.5 2.61 8.11 10.11 0.16 3.24 1.22 24.33 1.425 28.50 162.2 162.2 162.2 97.3 0.5
0+640.00 20.00 5.5 0.71 6.21 8.21 0.12 2.48 0.93 18.63 1.425 28.50 124.2 124.2 124.2 74.5 0.4
0+660.00 20.00 5.5 2.71 8.21 10.21 0.16 3.28 1.23 24.63 1.425 28.50 164.2 164.2 164.2 98.5 0.5
0+680.00 20.00 5.5 1.97 7.47 9.47 0.15 2.99 1.12 22.41 1.425 28.50 149.4 149.4 149.4 89.7 0.4
0+700.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+720.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+740.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+760.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+780.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+800.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
Premix carpet BASE Subbase Prime coat Tack Coat
Total Width
Carriage Extra antistripping
Chainage Length Total Width Including
way Width Widening Area Volume Area Volume Area Volume Volume agent (kg)
Shoulder Area (m2) Volume( Area (m2)
(m2) (m3) (m2) (m3) (m2) (lit) (lit)
m3)
0+820.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+840.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+860.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+880.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+900.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+920.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+940.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+960.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+980.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
1+000.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
1+020.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
1+040.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
1+060.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
1+080.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
1+100.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
1+120.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
1+140.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
1+149.24 9.24 5.5 - 5.50 7.50 0.11 1.02 0.83 7.62 1.425 13.17 50.8 50.8 50.8 30.5 0.2
Part 3
0+000.00 0.00 5.5 - 5.50 7.50 0.11 - 0.83 - 1.425 - - - - - -
0+020.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+040.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+060.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+080.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+100.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+120.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+140.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+160.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+180.00 20.00 5.5 - 5.50 7.50 0.11 2.20 0.83 16.50 1.425 28.50 110.0 110.0 110.0 66.0 0.3
0+200.00 20.00 5.5 1.73 7.23 9.23 0.14 2.89 1.08 21.68 1.425 28.50 144.5 144.5 144.5 86.7 0.4
Premix carpet BASE Subbase Prime coat Tack Coat
Total Width
Carriage Extra antistripping
Chainage Length Total Width Including
way Width Widening Area Volume Area Volume Area Volume Volume agent (kg)
Shoulder Area (m2) Volume( Area (m2)
(m2) (m3) (m2) (m3) (m2) (lit) (lit)
m3)
0+220.00 20.00 5.5 2.90 8.40 10.40 0.17 3.36 1.26 25.21 1.425 28.50 168.1 168.1 168.1 100.8 0.5
0+240.00 20.00 5.5 0.90 6.40 8.40 0.13 2.56 0.96 19.21 1.425 28.50 128.1 128.1 128.1 76.8 0.4
0+257.20 17.20 5.5 - 5.50 7.50 0.11 1.89 0.83 14.19 1.425 24.51 94.6 94.6 94.6 56.8 0.3
Type of outlet
Proposed
protection work
Chainage Cross Drain Remarks
Pipe Slab Box
Causeway Bridge
Culvert Culvert Culvert I II
Part 1
0+179.00 Pipe Culvert 0.6
Part 2
0+081.00 Pipe Culvert 0.6
0+421.00 Pipe Culvert 0.6
Omsatiya Rural Municipality
Office of the Rural Municipal Executive
Hati Pharsatikar
Rupandehi
Lumbini Province
Nepal
NAME OF WORK : PIPE CULVERT (Dia 600 mm )
Diameter of Pipe culvert= 0.6 m
Number= 3.00 No.
Pipe length= 10.00 m Slope =1:100(V:H)
Height of Head wall= 1.6 m clear cover=0.6m
Length Breadth Height
S.N. Description of Items No. Quantity Unit Remarks
(m.) (m.) (m.)
1 Earthwork in excavation in foundation
Inlet Catchpit 0 3.50 3.50 1.30 0.00 cu.m. The Quantities of
Head Wall 1 3.30 1.10 1.60 5.81 cu.m. estimated items may
gabion apron 0 4.00 2.50 0.50 0.00 cu.m. vary as per actual
Pipe Bed 1 7.95 0.90 1.30 9.30 site condition.
Total = 15.11 cu.m.
2 Stone Soling Work
Catchpit 0 3.30 3.30 0.15 0.00 cu.m.
Pipe Bed 0 7.95 0.90 0.15 0.00 cu.m.
Total = 0.00 cu.m.
3 PCC 1:3:6 in foundation bed
Catchpit 0 3.30 3.30 0.10 0.00 cu.m
Pipe Bed 1 7.95 0.90 0.10 0.72
Headwall 1 3.30 1.02 0.10 0.34 cu.m
Total = 1.05 cu.m.
4 Random rubble stone masonry in 1:4 c/s mortar
Kilometer Post, Traffic Sign, Sign board and RCC Delineators Detail
Pay SPEC
S. No. Description Unit Rate Remarks
Item No. REF
1 General
3.0 Earthworks
Roadway excavation in all types of soil/rock by both manual and
mechanical means as per drawing and technical specification,
17 3.1 905 including removal of stumps and other deleterious matter, with all m3 72.35
lifts and lead as drawing and instruction of engineer. [SS-905,
SP/SS-903]
Structure foundation excavation for all types of soil/rock by both
manual and mechanical means as per drawing and technical
18 3.2 907 specification, including removal of stumps and other deleterious m3 126.13
matter, with all lifts and lead as drawing and instruction of
engineer. [SS-907]
Construction of embankments with material deposited from
Roadway Cutting: Providing, laying, spreading and compacting
19 3.3 909, 910 embankment with roadway cutting material and compact to the m3 286.07
required density as per drawing and Tech, specification. [SS-909.
910]
Providing suitable material and backfilling behind abutment,
20 3.4 908 wingwall, return wall and other retaining structures complete as m3 430.75
per drawing and technical specification [SS-908]
4 Pavement Works
Scarifying the existing road surface to a depth of 50 mm and
4.1 1003 disposal of scarified Material with in all lifts and lead as per m2 12.99
Drawing and Technical Specifications.[SS-1003]
Loosening, leveling and Compacting original ground supporting
embankment to facilitate placement of first layer of embankment,
1003,
4.2 scarified to a depth of 150 mm, mixed with water at OMC and cum 69.65
1005
then compacted by rolling so as to achieve dry density as per
Drawing and Technical Specifications.[SS 1003,1005]
Construction of subgrade and earthen shoulders with approved
material (capping layer) obtained from borrow pits with with all
14 4.2 1004 m3 2406.90
lifts & leads lead as per drawing and technical spacification [SS-
1004]
Providing and laying granular Sub base material by mechanical
means on prepared surface, mixing at OMC, and compacting to
15 4.3 1201 m3 2737.23
achieve the desired density, complete as per Drawing and
Technical Specifications [SS-1201]
Providing and laying crusher run macadam on a prepared surface,
spreading and mixing, watering and compacting to form a layer of
16 4.4 1204 m3 4011.90
sub base/base course as per drawing and technical specifications.
(by mix in place method)[SS-1204]
Norms
Serial Laying of single/double /multiple bituminous coats for surface
4.90 No:13.05.01 dressing using river gravels ( grits) , shingles or 'broken stone chips litre 238.39
(Previous including compactation.
DoR Norms
Providing and laying of Reinforced/prestressed cement concrete
4.14 in superstructure as per Drawing and Technical Specification : m3 13614.24
PCC Grade M 20
Providing and laying of hand packed stone solling with 150 to 200
4.15 mm thick stones and packing with smaller stones on prepared m3 5594.56
surface as per drawing and technical specifications(SS….)
Providing and laying, fitting and placing HYSD bar reinforcement
4.16 in superstructure complete as per drawing and technical kg 132.71
specification
providing and fixing of Separation Membrane of impermeable
4.17 plastic sheeting 125 micron thick as per drawing and technical Sqm 175.00
specifications
Providing & fixing 20 mm thick compressible fibre board in
4.18 expansion joint complete as per drawing & Technical rm 435.48
Specification.
Providing and fixing in position 20 mm thick premoulded joint
4.19 filler in expansion joint to cater for a horizontal movement upto rm 445.37
20 mm, complete as per drawing and technical specifications.
Providing and filling joint sealing compound including sealant
4.20 primer as per drawings and technical specifications with coarse rm 50.74
sand and 6 per cent bitumen by weight
5.0 Structural/ Side Drain/ Cross Drainage Works
2500 of SS
Providing and Applying 12mm thick Plaster with Cement
DoR & S.N.
5.20 Mortar on Brick work Structure as per Technical sqm 3996.01
25.4 A of
Norms DoR Specification.(1:2) [2500 of SS DoR]
Rate Analysis
Ref. to Amount
S No Description of Works / Resources Unit Quantity Rate (NRs.) Unit Rate
SS (NRs.)
SECTION 100 - GENERAL
1.3 110 Providing and installation of project signboards with size of 1.8 x 1.2
m as per specification and instruction of engineer.
Unit = Nos
a) Labour
Skilled day 0.10 965.00 96.50
Unskilled day 0.50 652.00 326.00
b) Material
Project signboards with size of 1.8 x 1.2 m having details of contract nos 1.00 4,993.57 4,993.57
in the format and wording as directed by the Engineer
Sub-total 5,416.07
Overhead 15% 812.41
Total 6,228.48 6,228.48
II By Mechanical Means
A Cement Concrete Grade M-15 & M-20
Unit = cum, (for 10 cum)
a) Labour
Skilled day 1.00 965.00 965.00
Unskilled day 6.00 652.00 3,912.00
Sub-total(A) 4,877.00
b) Equipment
Air Compressor hour 6.00 1,234.00 7,404.00
Drilling machine with bit and accessories hour 6.00 620.00 3,720.00
Tractor-trolley hour 6.00 1,408.00 8,448.00
Sub-total(B) 19,572.00
Total (A+B) 24,449.00
Overhead 15% 3,667.35
Total 28,116.35 2,811.64
a) Labour
Skilled day 15.00 965.00 14,475.00
Unskilled day 3.00 652.00 1,956.00
Sub-total(A) 16,431.00
b) Equipment
Tractor-trolley hour 6.00 1,408.00 8,448.00
Sub-total(B) 8,448.00
Total (A+B) 24,879.00
Overhead 15% 3,731.85
Total 28,610.85 953.70
A &B 905 Road way and drain excavation for all types of soil with
combination of Manual and Mechanical means
Manual Excavation 5% 30.51
Mechanical Excavation 95% 68.73
Total 99.24 99.24
A &B 905 Road way and drain excavation for all types of soil with
combination of Manual and Mechanical means
Manual Excavation 0% -
Mechanical Excavation 100% 3,013.89
Total 3,013.89 3,013.89
I Ordinary soil
A Manual Means
Unit = cum (For 10 cum)
(i) Depth upto 3 m
a) Labour
Skilled day 1.00 965.00 965.00
Unskilled day 8.00 652.00 5,216.00
Sub-total (A) 6,181.00
Total (A) 6,181.00
Overhead 15% 927.15
Total 7,108.15 710.82
B Mechanical Means
(i) Depth upto 3 m
Unit = cum (For 240 cum)
a) Labour
Skilled day 1.00 965.00 965.00
Unskilled day 3.00 652.00 1,956.00
Sub-total (A) 2,921.00
b) Equipment
Hydraulic excavator hour 6.00 3,288.00 19,728.00
Sub-total (B) 19,728.00
Total (A+B) 22,649.00
Overhead 15% 3,397.35
Total 26,046.35 108.53
10.8 Providing and laying of hand pack Stone soling with 150 to 200
mm thick stones and packing with smaller stone on prepared
surface as per Drawing and Technical Specifications.
B 75 mm thick
Unit = sqm (For 4,500 sqm(337.5cum compacted))
a) Labour
Unskilled day 12.00 652.00 7,824.00
Skilled day 3.00 965.00 2,895.00
Sub-total (A) 10,719.00
b) Material
Bitumen tonne 22.70 113,705.00 2,581,103.50
Coarse aggregate ( 63 - 2.8 mm) cum 405.00 2,051.14 830,711.66
Key aggregates ( 26.5 - 2.8 mm) cum 81.00 2,051.14 166,142.33
Sub-total (B) 3,577,957.49
c) Equipment
Chip Spreader (with Truck) hour 6.00 5,294.00 31,764.00
Bitumen distributor hour 6.00 2,803.00 16,818.00
Vibratory roller hour 12.00 1,861.00 22,332.00
Sub-total (C) 70,914.00
Total (A+B+C) 3,659,590.49
Overhead 15% 548,938.57
Total 4,208,529.06 935.23
Unit Rate Per sqm 935.23
Unit Rate Per cum 12,469.72
c) Equipment
Boiler hr 0.0025 1,060.00 2.65
Distributor hr 0.0025 2,803.00 7.01
Air compresser hr 0.0025 1,234.00 3.09
Sub-total 207.30
Overhead 15% 31.09
Total 238.39 238.39
Add 2 per cent of cost of angle iron towards cost of drilling 426.00
holes, nuts, bolts etc.
(i) 90 cm height equilateral triangle sqm 2.40 1,569.00 3,765.60
OR
( ii ) 60 cm height equilateral triangle sqm 1.04
OR
( iii ) 60 cm circular sqm 2.83
OR
( iv ) 80 mm x 60 mm rectangular sqm 4.80
OR
(v) 60 cm x 45 cm rectangular sqm 2.70
Sub-total (B) 25,491.65
c) Equipment
Tractor-trolley hour 3.00 1,408.00 4,224.00
Sub-total (C) 4,224.00
Total (A+B+C) 36,559.10
Overhead 15% 5,483.87
Total 42,042.97 4,204.30
Add @ 5 per cent cost of Labour and Materials to prepare the 373.54
surface by filling minutes roughness on the surface and priming
the surface before laying 2 coats of painting.
Total (A+B) 7,886.39
Overhead 15% 1,182.96
Total 9,069.34 906.93
15.7 1503 Painting Lines, Dashes, Arrows etc. on Roads in Two Coats
Providing required material and Painting lines, dashes, arrows
etc. on roads in two coats on new work with ready mixed road
marking paint conforming to NS 408/ IS 164 on bituminous
surface, including cleaning the surface of all dirt, dust and
other foreign matter, demarcation at site and traffic control as
per Drawing and Technical Specifications.
SECTION 1800 - FALSEWORK, FORMWORK AND SURFACE FINISH FOR CONCRETE STRUCTURES
1804, Providing , Preparing and Installing form work including
1805 necessary supports and removing after completion for walls.
18.3
Class F2 Finish
Vertical Plain surface
a Using timber(Soft wood)
Unit =sqm ( For 10 sqm)
i Height upto 3 m
a) Labour
Skilled day 3.0 965.00 2,895.00
Unskilled day 3.0 652.00 1,956.00
b) Material
Ref. to Amount
S No Description of Works / Resources Unit Quantity Rate (NRs.) Unit Rate
SS (NRs.)
Ply wood 10 mm thick. sqm 11.0 60.00 660.00
Timber cum 0.6 5,775.85 3,465.51 Eight Times
Nails, spikes, etc. kg 4.0 120.00 480.00 use
Total (A-B) 9,456.51
Overhead 15% 1,418.48
Total 10,874.99 1,087.50
B PCC Grade M 30
Unit = cum (For 15 cum)
a) Labour
Skilled day 3 965.00 2,895.00
Unskilled day 30 652.00 19,560.00
Total (A) 22,455.00
b) Material
Cement tonne 6.08 15,899.19 96,667.05
Coarse sand cum 6.75 1,415.93 9,557.51
40 mm Aggregate cum 5.4 2,545.55 13,745.95
20 mm Aggregate cum 5.4 2,545.55 13,745.95
10 mm Aggregate cum 2.7 2,545.55 6,872.97
Cost of water KL 2.5 189.10 472.76
Total (B) 141,062.19
c) Equipment
Concrete mixer hour 6 323.00 1,938.00
Generator hour 6 882.00 5,292.00
Total (C) 7,230.00
d) Formwork @ 4 per cent on cost of concrete i.e. cost of 6,829.89
Material, Labour and Equipment
Total (A-C) 177,577.08
Overhead 15% 26,636.56
Total 204,213.64 13,614.24
C RCC Grade M 20
Unit = cum (For 15 cum)
a) Labour
Skilled day 3 965.00 2,895.00
Ref. to Amount
S No Description of Works / Resources Unit Quantity Rate (NRs.) Unit Rate
SS (NRs.)
Unskilled day 30 652.00 19,560.00
Total (A) 22,455.00
b) Material
Cement tonne 5.21 15,899.19 82,834.75
Coarse sand cum 6.75 1,415.93 9,557.51
20 mm Aggregate cum 8.1 2,545.55 20,618.92
10 mm Aggregate cum 5.4 2,545.55 13,745.95
Cost of water KL 2.5 189.10 472.76
Total (B) 127,229.90
c) Equipment
Concrete mixer hour 6 323.00 1,938.00
Generator hour 6 882.00 5,292.00
Total (C) 7,230.00
d) Formwork @ 4 per cent on (a+b+c) 6,276.60
Total (A-C) 163,191.50
Overhead 15% 24,478.72
Total 187,670.22 12,511.35
B Machine made gabion boxes (Hexagonal Mesh size 100 mm x cum 3,620.09
120 mm, Mesh wire 3mm, Selvedge wire 3.9 mm & Bending wire
2.64 mm) including stone filling and all complete
25.2 2500 Providing and laying Brick masonry work in superstructure/ sub-
structure complete excluding pointing and plastering, as per
drawing and Technical Specifications
Unit = cum (For 5 cum)
C Cement sand mortar (1:4)
a) Labour
Skilled day 7.00 965.00 6,755.00
Unskilled day 14.00 652.00 9,128.00
Total (A) 15,883.00
b) Material
Ref. to Amount
S No Description of Works / Resources Unit Quantity Rate (NRs.) Unit Rate
SS (NRs.)
Bricks Ist class nos 2800.00 14.47 40,522.39
Cement tonne 0.48 15,899.19 7,631.61
Sand cum 1.35 1,415.93 1,911.50
Cost of water KL 0.10 189.10 18.91
Add 5 per cent of cost of Labour and material for scaffolding 3,298.37
Total (B) 53,382.78
Total (A-B) 69,265.78
Overhead 15% 10,389.87
Total 79,655.65 15,931.13
25.3 2500 Providing, and applying Pointing with cement mortar (1:3 ) on
brick work in structure as per Technical Specifications .
Unit = sqm (For 100 sqm)
a) Labour
Skilled day 10.00 965.00 9,650.00
Unskilled day 12.00 652.00 7,824.00
Total (A) 17,474.00
b) Material
Cement tonne 0.15 15,899.19 2,384.88
Sand cum 0.32 1,415.93 453.10
Cost of water KL 1.00 189.10 189.10
Total (B) 3,027.08
Total (A-B) 20,501.08
Overhead 15% 3,075.16
Total 23,576.24 235.76
25.4 2500 Providing and applying 12.5 mm thick Plaster with cement
mortar on brick work structure as per technical specification.
26.5 2600 Providing and laying Stone Masonry work in cement mortar 1:4
in structure complete as per Drawing and Technical
Specifications
A 2607 Random Rubble Masonry
( coursed/uncoursed )
Unit= cum (For 5 cum)
a) Labour
Skilled day 7.00 965.00 6,755.00
Unskilled day 20.00 652.00 13,040.00
b) Material
Stone cum 5.75 1,785.03 10,263.91
Cement tonne 0.66 15,899.19 10,493.46
Sand cum 1.85 1,415.93 2,619.47
Cost of water KL 1.00 189.10 189.10
Add 5 per cent of cost of Labour and material for scaffolding 989.75
Total (A+B) 44,350.69
Overhead 15% 6,652.60
Total 51,003.30 10,200.66
28.8 2807 Planting rooted grass slips on the slopes <45o including
preparation of slips on site. a max of 5 cm depth with metal rod
E or Operation includes digging planting hole to hard-wood peg,
depending on the nature of the soil. The planting drills should
be space [SS DOR 2807]
Unit = sqm ( For 1 sqm)
a) Labour
Unskilled day 0.20 652.00 130.40
b) Material
Grass slips/ no of drills Cuttings nos 100.00 3.30 330.00
Hessian Jute sqm 0.27 60.00 16.20
2807 c) Equipment
Add 3 % of Labour cost for Ms rod or hard wood peg and other T&P 3.91
Sub-Total 480.51
Overhead 15% 72.08
Total 552.59 552.59
Sub-Total 547.67
Overhead 15% 82.15
Total 629.82 629.82
28.9 2807 Planting shrub and tree seedling and cutting on site
Planting containerized tree and shrub seedlings, including
pitting, transplanting, composting and mulching, on slopes <
B 30o . Pit size 30 cm diameter x depth mix Compost with soil
and back fill into pit to 1/4 of the pit volume [SS DOR 2807]
31.7 3105 Tubular Steel Railing on Precast RCC Posts ,1.2m High Above
Ground Level
Providing, fencing and erecting 50mm dia painted steel pipe
railing in 3 rows on precast M20 grade RCC vertical posts 1.8
metres high (1.2m above GL) with 3 holes 50mm dia for pipe,
fixed 2 metres center to, complete as pe rDrawing and
Technical Specifications.
Unit = meter ( For 100 meter)
i) Excavation for foundation cum 12.96 107.21 1,389.42
ii) Foundation concrete M-15 cum 6.48 9,682.35 62,741.61
iii) Painting of pipe sqm 47.10 157.27 7,407.55
a) Labour (For fixing at site)
Unskilled day 6.00 652.00 3,912.00
Plumber / skilled day 1.00 965.00 965.00
Sub-Total (A) 76,415.58
b) Material
Steel pipe 50 mm external dia as per IS: 1239 meter 300.00 644.87 193,461.00
Sub-Total (B) 193,461.00
c) Equipment
Tractor-trolley hour 6.00 1,408.00 8,448.00
Sub-Total (C) 8,448.00
Total (A-C) 278,324.58
Overhead 15% 41,748.69
Total 320,073.26 3,200.73
Energy Source Rate
Description of Energy
S.No. Unit Rate
Source
1 Diesel Litre 145.00
2 Kerosene Litre 145.00
3 Petrol Litre 150.00
4 Lubricant Litre 530.97
Electricity Less than
5 Unit 12.50
25KWH
Electricity more than
6 Unit 13.50
25KWH
Operation Charges in NRs. Per Hour Energy Source for Output in Unit per Hour
Ownership Amount of Electricity Amount of Heating
Charge in Fuel Fuel in Rate in Electricity Fuel in Fuel Rate Amount of
Equipment Description of Capacity/ NRs. Per Operator Maintenan Consumption Fuel Rate in NRs. Per Electricity NRs. Per in NRs. Per Litre per in NRs. Fuel in NRs. Total Rate of
Item No. Equipment Activity Usage Output Output Unit Hour (Crew) Servicing ce Litre per Unit NRs. Per Litre Unit Unit per Unit Unit Unit Unit Per Litre Per Unit Equipment Remarks
P&M-001 Air Compressor General Purpose cfm 170/250 Hour 192 120.625 42 50 5.73 145 830 12.5 0 145 0 1234
Batching and Mixing
P&M-002 Plant Concrete Mixing cu.m. 30 Hour 1221 600 530 408 16.38 145 2375 12.5 0 145 0 5134
Batching and Mixing 15.00-
P&M-003 Plant Concrete Mixing cu.m. 20.00 Hour 651 480 132 218 4.1 145 594 12.5 0 145 0 2075
Bitumen Pressure sqm. Per
P&M-006 Distributor Spraying Bitumen Hour 1750 Hour 443 202.125 63 176 10.24 145 1484 0 12.5 0 3 145 435 2803
Decanter( Bitumen
P&M-005 Bitumen Boiler Oil Fired Spreying) Litre 1500 Hour 40 0 3 8 1.96 145 284 12.5 0 5 145 725 1060
Concrete Paver Paving Concrete cu.m. per
P&M-006 Finisher Surface Hour 20 Hour 472 360 567 163 145 0 26.86 13.5 362 145 0 1924
cu.m. per
P&M-007 Concrete Pump Concrete Pumping Hour 33.00/22.00 Hour 740 450 198 163 6.12 145 887 12.5 0 145 0 2438
P&M-008 Concrete Bucket Concrete Pouring cu.m. 1 Hour 12 5 145 0 12.5 0 145 0 17
P&M-009 Concrete Mixer Concrete Mixing cu.m. 0.4 Hour 49 240 17 16 0.51 145 73 12.5 0 145 0 395
P&M-010 Concrete Mixer Concrete Mixing cu.m. 1 Hour 31 0 3 11 1.92 145 278 0 0 145 0 323
P&M-011 Crane Mobile Lifting Purpose Ton 80 Hour 7833 480 582 2696 18 145 2610 12.5 0 145 0 14201
P&M-012 Crane Mobile Lifting Purpose Ton 35 Hour 2844 360 378 977 11.7 145 1696 12.5 0 145 0 6255
P&M-013 Crane Mobile Lifting Purpose Ton 3 Hour 1176 300 175 389 5.4 145 783 12.5 0 145 0 2823
Spreading, Cutting
P&M-014 Track Dozer and Clearing cu.m. 100/150/250 Hour 1300 120.625 330 550 14.14 145 2050 12.5 0 145 0 4350
Spreading, Cutting
P&M-015 Track Dozer and Clearing cu.m. 100/120/150 Hour 2960 360 457 990 14.14 145 2050 12.5 0 145 0 6817
Application of sqm. Per
P&M-016 Emulsion Distributor Emulsion Tack Hour 1750 Hour 559 480 132 182 4.1 145 594 12.5 0 145 0 1947
Wheeled Front End Soil/ Aggregate cu.m. per
P&M-027 Loader Loading Hour 60/25/ Hour 543 120.625 136 227 9.79 145 1419 12.5 0 145 0 2445
P&M-018 Generator Electric Generation KVA 125 Hour 488 180 419 163 12.96 145 1879 12.5 0 145 0 3129
P&M-019 Generator Electric Generation KVA 63 Hour 77 120.625 10 17 4.54 145 658 12.5 0 145 0 882
Gravel Screening Sub Producing Gravel Sub
P&M-020 Base Plant Base cu.m. 40 Hour 1302 120 70 436 145 0 25 12.5 312 145 0 2240
BM/ DBM/SDC/
P&M-021 Hot Mix Plant Premix Production Ton per Hour 120 Hour 4026 600 20316 1346 145 0 325 13.5 4387 600 145 87000 117675
BM/ DBM/SDC/
P&M-022 Hot Mix Plant Premix Production Ton per Hour 100 Hour 3315 600 16871 1109 145 0 250 13.5 3375 500 145 72500 97770
BM/ DBM/SDC/
P&M-023 Hot Mix Plant Premix Production Ton per Hour 60 Hour 2131 480 10263 713 145 0 200 13.5 2700 300 145 43500 59787
BM/ DBM/SDC/
P&M-024 Hot Mix Plant Premix Production Ton per Hour 40 Hour 1658 360 6811 554 145 0 170 13.5 2295 200 145 29000 40678
BM/ DBM/SDC/
P&M-025 Hot Mix Plant Premix Production Ton per Hour 20 Hour 693 283.625 108 173 6.91 145 1001 15 12.5 187 200 145 29000 31445
Hydraulic Chips Surface Dressing and sqm. Per
P&M-026 Spreader Otta Sealing Hour 1500 Hour 1877 360 440 645 13.6 145 1972 12.5 0 145 0 5294
Soil/ Aggregate cu.m. per
P&M-020 Hydraulic Excavator Excavation Hour 60 Hour 620 120.625 185 275 14.4 145 2088 12.5 0 145 0 3288
Excavation and
Backhoe Loader (0.2 Loading of Earth and cu.m. per
P&M-028 cu.m. Bucket Capacity) Rock Materials Hour 26 Hour 581 300 258 189 7.99 145 1158 12.5 0 145 0 2486
Integrated Stone
P&M-029 Crusher Stone Crushing Plant Ton per Hour 100 Hour 977 240 99 327 3.06 145 443 12.5 0 145 0 2086
Integrated Stone
P&M-030 Crusher Stone Crushing Plant Ton per Hour 200 Hour 1465 360 178 490 5.51 145 798 12.5 0 145 0 3291
Operation Charges in NRs. Per Hour Energy Source for Output in Unit per Hour
Ownership Amount of Electricity Amount of Heating
Charge in Fuel Fuel in Rate in Electricity Fuel in Fuel Rate Amount of
Equipment Description of Capacity/ NRs. Per Operator Maintenan Consumption Fuel Rate in NRs. Per Electricity NRs. Per in NRs. Per Litre per in NRs. Fuel in NRs. Total Rate of
Item No. Equipment Activity Usage Output Output Unit Hour (Crew) Servicing ce Litre per Unit NRs. Per Litre Unit Unit per Unit Unit Unit Unit Per Litre Per Unit Equipment Remarks
Kerb Casting
P&M-031 Equipment Kerb Block Making RM per Hour 80 Hour 710 300 79 238 2.45 145 355 12.5 0 145 0 1682
Mastic Wearing
P&M-032 Mastic Cooker Surface Ton per Hour 1 Hour 95 180 414 32 1.15 145 166 125 13.5 1687 5 145 725 3299
Clearing/ Spreading/ cu.m. per
P&M-033 Motor Grader Grading Hour 100/200/50 Hour 1016 120.625 256 351 6.67 145 967 12.5 0 145 0 2710
Hydraulic Broomer Surface Clearing and sqm. Per
P&M-038 Mechanical Brooming Hour 1250 Hour 297 202.125 34 68 6.4 145 928 12.5 0 145 0 1529
Mobile Slurry Seal Mixing and Laying sqm. Per
P&M-035 Equipment Slurry Hour 2700 Hour 877 300 224 288 6.94 145 1006 12.5 0 145 0 2695
Paving
Paver Finisher DBM/BM/Premix/Asph cu.m. per
P&M-036 Hydrostatic alt Hour 40 Hour 2505 300 449 833 13.87 145 2011 12.5 0 145 0 6098
Paving
Paver Finisher DBM/BM/Premix/Asph cu.m. per
P&M-037 Mechanical alt Hour 30 Hour 2357 300 374 783 11.56 145 1676 12.5 0 145 0 5490
Piling Rig with 0.7m Boring
P&M-038 Bentonite Pump Attachment RM per Hour 2 to 3 Hour 814 360 224 272 6.94 145 1006 12.5 0 145 0 2676
Bituminous Surface cu.m. per
P&M-039 Pneumatic Roller Rolling Hour 25 Hour 1552 240 265 527 8.19 145 1187 12.5 0 145 0 3771
Pot Hole Repair cu.m. per
P&M-040 Equipment Potholes Repairing Hour 4 Hour 877 300 224 288 6.94 145 1006 12.5 0 145 0 2695
Prestressing Jack with Stressing of Steel
P&M-041 Pump wires/ Stands Hour 326 180 28 109 145 0 10 12.5 125 145 0 768
Ripper attached with cu.m. per
P&M-042 Tractor Scarifying Hour 40 Hour 83 202.125 13 33 4.5 145 652 12.5 0 145 0 983
Rotavator attached with cu.m. per
P&M-043 Tractor Scarifying Hour 25 Hour 17 60 0 6 145 0 12.5 0 145 0 83
sqm. Per
P&M-044 Road Marking Machine Road Marking Hour 100 Hour 242 240 65 22 145 0 12.5 0 145 0 569
cu.m. per
P&M-045 Smooth Wheeled Roller Soil compaction/ BM Hour 70/25/ Hour 437 300 203 143 6.27 145 909 12.5 0 145 0 1992
Bituminous Surface cu.m. per
P&M-046 Tandem Road Roller Rolling Hour 30 Hour 592 300 177 198 5.49 145 796 12.5 0 145 0 2063
Tipper of 5 cu.m. Earth Mass cu.m. per
P&M-047 Capacity Transportation Hour 5.5 Hour 148 202.125 23 55 6.76 145 980 12.5 0 145 0 1408
Transit Mixer 4/4.5 Transportation of cu.m. per
P&M-048 cu.m. Concrete Hour 4.5 Hour 542 240 163 188 5.88 145 852 12.5 0 145 0 1985
Transit Mixer 4/4.5 Transportation of cu.m. per Ton
P&M-049 cu.m. Concrete Hour 4.5 Km 542 7 0 5 0.19 145 27 12.5 0 145 0 581
P&M-042 Tractor Pulling HP 50 Hour 148 202.125 23 55 6.76 145 980 12.5 0 145 0 1408
P&M-051 Tractor with Rotevator Tractor+Rotevator Hour 265 240 125 87 4.5 145 652 12.5 0 145 0 1369
P&M-052 Tractor with Ripper Tractor+Ripper Hour 272 240 125 90 4.5 145 652 12.5 0 145 0 1379
Truck 5.5 cu.m. per 10
P&M-053 Tonne Materials Transport cu.m. 20 KM 25 12 1 8 0.47 145 68 12.5 0 145 0 114
Truck 5.5 cu.m. per 10
P&M-054 Tonne Materials Transport cu.m. 4.5 Hour 496 240 263 165 9.46 145 1371 12.5 0 145 0 2535
Truck 5.5 cu.m. per 10 Ton
P&M-055 Tonne Materials Transport cu.m. 200 Km 2 1 0 1 0.04 145 5 12.5 0 145 0 9
Vibratory Roller 8 Compaction of Earth/ cu.m. per
P&M-056 Tonne GSB/ WBM Hour 100/60/60 Hour 461 120.625 66 159 7.28 145 1055 12.5 0 145 0 1861
Capacity in
P&M-057 Water Tanker Water Transport KL 6 Hour 529 240 200 177 7.2 145 1044 12.5 0 145 0 2190
For cutting Hard Strata
Air Compressor with such as Hard Clay or
P&M-058 Pneumatic Jack Rock Hour 539 180 64 149 2.3 145 333 12.5 0 145 0 1265
Batch type Cold Mixing
P&M-059 Plant Ton per Hour 75 Hour 592 480 277 198 9.99 145 1448 12.5 0 145 0 2995
cu.m. per
P&M-060 Cold Milling Machine Hour 20 Hour 715 360 256 248 9.22 145 1336 12.5 0 145 0 2915
P&M-061 Crane 5 Ton Capacity Ton Hour 1276 240 275 437 9.9 145 1435 12.5 0 145 0 3663
P&M-062 Crane 10 Ton Capacity Ton Hour 1768 300 325 602 11.7 145 1696 12.5 0 145 0 4691
P&M-063 Crane 15 Ton Capacity Ton 15 Hour 1989 360 375 682 13.5 145 1957 12.5 0 145 0 5363
P&M-064 Crane 20 Ton Capacity Ton 20 Hour 2275 420 400 781 14.4 145 2088 12.5 0 145 0 5964
P&M-065 Crane 40 Ton Capacity Ton 40 Hour 3126 360 449 1073 16.2 145 2349 12.5 0 145 0 7357
Operation Charges in NRs. Per Hour Energy Source for Output in Unit per Hour
Ownership Amount of Electricity Amount of Heating
Charge in Fuel Fuel in Rate in Electricity Fuel in Fuel Rate Amount of
Equipment Description of Capacity/ NRs. Per Operator Maintenan Consumption Fuel Rate in NRs. Per Electricity NRs. Per in NRs. Per Litre per in NRs. Fuel in NRs. Total Rate of
Item No. Equipment Activity Usage Output Output Unit Hour (Crew) Servicing ce Litre per Unit NRs. Per Litre Unit Unit per Unit Unit Unit Unit Per Litre Per Unit Equipment Remarks
Crane with Grab 0.75
cu.m. Capacity Grab 0.75 cu.m.
P&M-066 (Clamshell Crane) Capacity cu.m. Hour 1419 240 275 486 9.9 145 1435 12.5 0 145 0 3855
Crane with Grab 0.75
cu.m. Capacity
P&M-067 (Clamshell Crane) cu.m. Hour 572 240 114 198 4.1 145 594 12.5 0 145 0 1718
Drum Mix Plant for Cold
Mixes of Appropriate
P&M-068 Capacity cu.m. Hour 715 240 128 248 4.61 145 668 12.5 0 145 0 1999
P&M-069 Epoxy Injection Gun cu.m. Hour 323 180 59 59 145 0 14.48 12.5 181 145 0 802
P&M-070 Generator 33 KVA Hour 172 120 144 59 5.18 145 751 12.5 0 145 0 1246
P&M-071 Generator 100 KVA Hour 286 120 336 99 12.1 145 1754 12.5 0 145 0 2595
P&M-072 Generator 250 KVA Hour 644 240 839 223 30.24 145 4384 12.5 0 145 0 6330
P&M-074 Jack for Lifting Purpose Lifting Purpose Hour 11 120 4 145 0 12.5 0 145 0 135
Piling Rig including
Double Acting Pile
P&M-075 Driving Hammer Hour 2622 400 479 756 17.28 145 2505 12.5 0 145 0 6762
P&M-076 Plate Compactor Hour 72 120 18 25 0.65 145 94 12.5 0 145 0 329
Snow Blowing
P&M-077 Equipment Hour 429 480 423 149 15.23 145 2208 12.5 0 145 0 3689
P&M-078 Truck Trailer 30 Ton Hour 1267 360 586 429 21.12 145 3062 12.5 0 145 0 5704
Ton
P&M-079 Truck Trailer 30 Ton Km 2 1 0 1 0.04 145 5 12.5 0 145 0 9
Vibratory Pile Driving
Hammer Complete with
P&M-080 Accessories Hour 2979 400 479 859 17.28 145 2505 12.5 0 145 0 7222
P&M-081 Wet Mix Plant 75TPH Hour 644 240 128 223 4.61 145 668 12.5 0 145 0 1903
P&M-082 Jeep Utility Vehicle Hour 712 150 196 204 7.06 145 1023 12.5 0 145 0 2285
P&M-083 Weigh Bridge Hour 215 120 0 74 0 145 0 12.5 0 145 0 409
P&M-084 Sand Blasting Machine Hour 848 320 38 248 145 0 1.22 12.5 15 145 0 1469
P&M-085 Generator Hour 10 60 11 3 0.39 145 56 12.5 0 145 0 140
P&M-086 Screw Jack Hour 9 5 0 1 145 0 12.5 0 145 0 15
P&M-087 Electric Heating Plate Hour 3 5 0 1 145 0 1.38 12.5 17 145 0 26
P&M-088 Electric Hand Driller Hour 3 5 3 0 145 0 0.72 12.5 9 145 0 20
Bitumen/ Emulsion
P&M-089 Sprayer Hour 358 120 69 124 1.15 145 166 12.5 0 2.5 145 362 1199
P&M-090 Mixer Machine Hour 436 60 36 124 1.3 145 188 12.5 0 145 0 844
Humus Sprayig
Equipment, Truck
P&M-091 Mounted Hour 1780 360 313 612 11.26 145 1632 12.5 0 145 0 4697
Jack Hammer/ Rock
P&M-092 Drill Hour 349 60 18 99 0.65 145 94 12.5 0 145 0 620
Hand Boring Set/ Augur
P&M-093 Drill Machine Hour 87 144 7 24 0.39 145 56 12.5 0 145 0 318
P&M-094 Percusion Drill Set Hour 83 144 7 24 0.26 145 37 12.5 0 145 0 295
P&M-095 Rotary Drill Hour 524 180 54 149 1.94 145 281 12.5 0 145 0 1188
P&M-096 Peizometer Hour 5 5 145 0 12.5 0 145 0 10
P&M-097 Water Pump Hour 3 1 10 1 145 0 2.33 12.5 29 145 0 44
P&M-098 Hacking Machine Hour 524 144 32 149 145 0 7.2 12.5 90 145 0 939
Bridge Inspection
P&M-099 Vehicle Hour 5086 240 549 2963 19.8 145 2871 12.5 0 145 0 11709
Concrete Needle Extracted
P&M-100 Vibrator Hour 461 120.625 25 34 0.51 145 73 12.5 0 145 0 713 Norms
Extracted
P&M-101 Mini Dumper Hour 250 417 62 85 1.21 145 175 12.5 0 145 0 989 Norms
Omsatiya Rural Municipality
Office of the Rural Municipal Executive
Hati Pharsatikar
Rupandehi
Lumbini Province
Nepal
Activity
Description of Works/ Analyzed Quantity
S.No. Norms Unit Unit Rate Amount Remarks
Resource Type Quantity per Unit
No.
Loading and Unloading
Stone Boulder/
1 8.9A aggregates/ Sand/ cu.m. 5.50
excavated earth etc.
Tipper/Truck Hour 0.33 0.06 1,408.00 84.48
Loader Hour 0.33 0.06 2,445.00 146.70
Sum 231.18
Loading and Unloading
2 8.10 Cement and Steel Tonne 10.00
Unskilled Labour pd 2.00 0.20 652.00 130.40
Tipper/Truck Hour 2.00 0.20 1,408.00 281.60
Sum 412.00
Loading and Unloading
3 8.11 Bricks Nos. 16,000.00
Unskilled Labour pd 3.00 0.00 652.00 0.12
Tipper/Truck Hour 6.00 0.00 1,408.00 0.53
Sum 0.65
Loading and Unloading
4 8.12 Bitumen/ Water/ Paints Kg 40,000.00
Unskilled Labour pd 6.00 0.00 652.00 0.10
Tipper/Truck Hour 6.00 0.00 1,408.00 0.21
Sum 0.31
Loading and Unloading
5 8.13 Timber Kg 30,000.00
Skilled Labour pd 1.00 0.00 965.00 0.03
Unskilled Labour pd 8.00 0.00 652.00 0.17
Tipper/Truck Hour 6.00 0.00 1,408.00 0.28
Sum 0.49
Loading and Unloading
Density of
Timber
5 8.13 Timber cu.m. 33.33 considered
900 Kg per
cu.m.
Skilled Labour pd 1.00 0.03 965.00 28.95
Unskilled Labour pd 8.00 0.24 652.00 156.50
Tipper/Truck Hour 6.00 0.18 1,408.00 253.47
Sum 438.91
Loading and Unloading
5 8.14 Concrete Blocks cu.m. 20.00
Skilled Labour pd 1.00 0.05 965.00 48.25
Unskilled Labour pd 8.00 0.40 652.00 260.80
Tipper/Truck Hour 6.00 0.30 1,408.00 422.40
Sum 731.45
Loading and Unloading
6 Loading
900/1000/1200 mm Dia
8.15.iii.A m 15.00
RCC Pipe
Skilled Labour pd 0.30 0.02 965.00 19.30
Unskilled Labour pd 3.00 0.20 652.00 130.40
Tipper/Truck Hour 4.00 0.27 1,408.00 375.47
3% for Tools and Plants 4.49
8.15.iv.A Unloading
Skilled Labour pd 0.30 0.02 965.00 19.30
Unskilled Labour pd 1.50 0.10 652.00 65.20
Tipper/Truck Hour 3.00 0.20 1,408.00 281.60
3% for Tools and Plants 2.53
Sum 898.29
Loading and Unloading
8 Loading
750/600 mm Dia RCC
8.15.iii.B m 25.00
Pipe
Skilled Labour pd 0.30 0.01 965.00 11.58
Unskilled Labour pd 4.00 0.16 652.00 104.32
Tipper/Truck Hour 4.00 0.16 1,408.00 225.28
3% for Tools and Plants 3.47
8.15.iv.B Unloading
Skilled Labour pd 0.30 0.01 965.00 11.58
Unskilled Labour pd 1.50 0.06 652.00 39.12
Tipper/Truck Hour 3.00 0.12 1,408.00 168.96
3% for Tools and Plants 1.52
Sum 565.83
Loading and Unloading
9 Loading
450/300 mm Dia RCC
8.15.iii.C m 37.50
Pipe
Skilled Labour pd 0.30 0.01 965.00 7.72
]
Unskilled Labour pd 5.00 0.13 652.00 86.93
Tipper/Truck Hour 4.00 0.11 1,408.00 150.19
3% for Tools and Plants 2.83
8.15.iv.C Unloading
Skilled Labour pd 0.30 0.01 965.00 7.72
Unskilled Labour pd 1.50 0.04 652.00 26.08
Tipper/Truck Hour 3.00 0.08 1,408.00 112.64
3% for Tools and Plants 1.01
Sum 395.12
]
References Page 1 of 90
References
Descripti
Activity on of
Quantity Net
S.No. Resource No. Norms Works/ Unit Unit Rate Amount Remarks
per Unit Amount
No. Resource
Type
Transport vol=(mass
8.16
ation of /Density)
Materials
Tipper/Tr
Hour 0.63 1,408.00 887.04 887.04 5
uck
177.408 for 1m3
2 Transportation of Soil by Truck
Plain( Terai) Hilly/Mountain
Distance Distance in
Route Route
in Km Km
Earthen 0 Earthen 1
Gravelled 0 Gravelled 0
Blacktop 0 Blacktop 0
Travelling out of Site
Plain Route Hilly/ Mountainous Terrain Route
Type of Total
Speed of Speed of Speed of
S.No. Travelling Speed of Distance Duration Distance Duration, Remarks
Unit Vehicle Vehicle Vehicle Duration of
Surface Vehicle of Travel of Travel of Travel (T1)+(T2)
(Loaded), (Loaded), (Empty), Travel (T2)
(Empty), V2 (D) (T1) (D)
V1 V1 V2
1 Earthen Route 20.00 25.00 - - 10.00 12.50 1.00 0.18 0.18
2 Gravelled Route 30.00 37.50 - - 15.00 18.75 - - -
Blacktopped
3 40.00 50.00 - - 20.00 25.00 - - -
Surface Route
Total Duration of
- - - 0.18
Travel
Descripti
Activity on of
Quantity Net
S.No. Resource No. Norms Works/ Unit Unit Rate Amount Remarks
per Unit Amount
No. Resource
Type
Transport
8.16
ation of
Materials
Tipper/Tr
Hour 0.18 1,408.00 253.44 253.44 5.71428571
uck
44.352 for 1m3
3 Transportation of Sub base by Truck
Plain( Terai) Hilly/Mountain
Distance Distance in
Route Route
in Km Km
Earthen 0 Earthen 0
Gravelled 0 Gravelled 0
Blacktop 0 Blacktop 7
Travelling out of Site
Plain Route Hilly/ Mountainous Terrain Route
Type of Total
Speed of Speed of Speed of
S.No. Travelling Speed of Distance Duration Distance Duration, Remarks
Unit Vehicle Vehicle Vehicle Duration of
Surface Vehicle of Travel of Travel of Travel (T1)+(T2)
(Loaded), (Loaded), (Empty), Travel (T2)
(Empty), V2 (D) (T1) (D)
V1 V1 V2
1 Earthen Route 20.00 25.00 - - 10.00 12.50 - - -
2 Gravelled Route 30.00 37.50 - - 15.00 18.75 - - -
Blacktopped
3 40.00 50.00 - - 20.00 25.00 7.00 0.63 0.63
Surface Route
Total Duration of
- - - 0.63
Travel
Descripti
Activity on of
Quantity Net
S.No. Resource No. Norms Works/ Unit Unit Rate Amount Remarks
per Unit Amount
No. Resource
Type
Transport
8.16
ation of
Materials
Tipper/Tr
Hour 0.63 1,408.00 887.04 887.04 4.44444444
uck
199.584 for 1m3
4 Transportation of Base & Aggregate by Truck
Plain( Terai) Hilly/Mountain
Distance Distance in
Route Route
in Km Km
Earthen 0 Earthen 0
Gravelled 0 Gravelled 0
Blacktop 0 Blacktop 7
Travelling out of Site
Plain Route Hilly/ Mountainous Terrain Route
Type of Total
Speed of Speed of Speed of
S.No. Travelling Speed of Distance Duration Distance Duration, Remarks
Unit Vehicle Vehicle Vehicle Duration of
Surface Vehicle of Travel of Travel of Travel (T1)+(T2)
(Loaded), (Loaded), (Empty), Travel (T2)
(Empty), V2 (D) (T1) (D)
V1 V1 V2
1 Earthen Route 20.00 25.00 - - 10.00 12.50 - - -
2 Gravelled Route 30.00 37.50 - - 15.00 18.75 - - -
Blacktopped
3 40.00 50.00 - - 20.00 25.00 7.00 0.63 0.63
Surface Route
Total Duration of
- - - 0.63
Travel
Descripti
Activity on of
Quantity Net
S.No. Resource No. Norms Works/ Unit Unit Rate Amount Remarks
per Unit Amount
No. Resource
Type
Transport
8.16
ation of
Materials
Tipper/Tr
Hour 0.63 1,408.00 887.04 887.04 3.33333333
uck
266.11 for 1m3
5 Transportation of Brick by Truck
Plain( Terai) Hilly/Mountain
Distance Distance in
Route Route
in Km Km
Earthen 0 Earthen 0
Gravelled 0 Gravelled 0
Blacktop 0 Blacktop 10
Travelling out of Site
Plain Route Hilly/ Mountainous Terrain Route
Type of Total
Speed of Speed of Speed of
S.No. Travelling Speed of Distance Duration Distance Duration, Remarks
Unit Vehicle Vehicle Vehicle Duration of
Surface Vehicle of Travel of Travel of Travel (T1)+(T2)
(Loaded), (Loaded), (Empty), Travel (T2)
(Empty), V2 (D) (T1) (D)
V1 V1 V2
1 Earthen Route 20.00 25.00 - - 10.00 12.50 - - -
2 Gravelled Route 30.00 37.50 - - 15.00 18.75 - - -
Blacktopped
3 40.00 50.00 - - 20.00 25.00 10.00 0.90 0.90
Surface Route
Total Duration of
- - - 0.90
Travel
Descripti
Activity on of
Quantity Net
S.No. Resource No. Norms Works/ Unit Unit Rate Amount Remarks
per Unit Amount
No. Resource
Type
Transport
8.16
ation of
Materials
Tipper/Tr
Hour 0.90 1,408.00 1,267.20 1,267.20 8000
uck
0.47 for 1nos
6 Transportation of Cement by Truck
Plain( Terai) Hilly/Mountain
Distance Distance in
Route Route
in Km Km
Earthen 0 Earthen 0
Gravelled Gravelled 0
Blacktop 0 Blacktop 10
Travelling out of Site
Plain Route Hilly/ Mountainous Terrain Route
Type of Total
Speed of Speed of Speed of
S.No. Travelling Speed of Distance Duration Distance Duration, Remarks
Unit Vehicle Vehicle Vehicle Duration of
Surface Vehicle of Travel of Travel of Travel (T1)+(T2)
(Loaded), (Loaded), (Empty), Travel (T2)
(Empty), V2 (D) (T1) (D)
V1 V1 V2
1 Earthen Route 20.00 25.00 - - 10.00 12.50 - - -
2 Gravelled Route 30.00 37.50 - - 15.00 18.75 - - -
Blacktopped
3 40.00 50.00 - - 20.00 25.00 10.00 0.90 0.90
Surface Route
Total Duration of
- - - 0.90
Travel
Descripti
Activity on of
Quantity Net
S.No. Resource No. Norms Works/ Unit Unit Rate Amount Remarks
per Unit Amount
No. Resource
Type
Transport
8.16
ation of
Materials
Tipper/Tr
Hour 0.90 1,408.00 1,267.20 1,267.20 8000
uck
7.92 for 50 Kg
7 Transportation of Reinforcement Bar by Truck
Plain( Terai) Hilly/Mountain
Distance Distance in
Route Route
in Km Km
Earthen 0 Earthen 0
Gravelled 0 Gravelled 0
Blacktop 0 Blacktop 10
Travelling out of Site
Plain Route Hilly/ Mountainous Terrain Route
Type of Total
Speed of Speed of Speed of
S.No. Travelling Speed of Distance Duration Distance Duration, Remarks
Unit Vehicle Vehicle Vehicle Duration of
Surface Vehicle of Travel of Travel of Travel (T1)+(T2)
(Loaded), (Loaded), (Empty), Travel (T2)
(Empty), V2 (D) (T1) (D)
V1 V1 V2
1 Earthen Route 20.00 25.00 - - 10.00 12.50 - - -
2 Gravelled Route 30.00 37.50 - - 15.00 18.75 - - -
Blacktopped
3 40.00 50.00 - - 20.00 25.00 10.00 0.90 0.90
Surface Route
Total Duration of
- - - 0.90
Travel
Descripti
Activity on of
Quantity Net
S.No. Resource No. Norms Works/ Unit Unit Rate Amount Remarks
per Unit Amount
No. Resource
Type
Transport
8.16
ation of
Materials
Tipper/Tr
Hour 0.90 1,408.00 1,267.20 1,267.20 8000
uck
0.16 for 1Kg
8 Transportation of Gabion Wire by Truck
Plain( Terai) Hilly/Mountain
Distance Distance in
Route Route
in Km Km
Earthen 0 Earthen 0
Gravelled 0 Gravelled 0
Blacktop 0 Blacktop 10
Travelling out of Site
Plain Route Hilly/ Mountainous Terrain Route
Type of Total
Speed of Speed of Speed of
S.No. Travelling Speed of Distance Duration Distance Duration, Remarks
Unit Vehicle Vehicle Vehicle Duration of
Surface Vehicle of Travel of Travel of Travel (T1)+(T2)
(Loaded), (Loaded), (Empty), Travel (T2)
(Empty), V2 (D) (T1) (D)
V1 V1 V2
1 Earthen Route 20.00 25.00 - - 10.00 12.50 - - -
2 Gravelled Route 30.00 37.50 - - 15.00 18.75 - - -
Blacktopped
3 40.00 50.00 - - 20.00 25.00 10.00 0.90 0.90
Surface Route
Total Duration of
- - - 0.90
Travel
Descripti
Activity on of
Quantity Net
S.No. Resource No. Norms Works/ Unit Unit Rate Amount Remarks
per Unit Amount
No. Resource
Type
Transport
8.16
ation of
Materials
Tipper/Tr
Hour 0.90 1,408.00 1,267.20 1,267.20 8000
uck
0.1584 for 1kg
9 Transportation of Bitumen by Truck
Plain( Terai) Hilly/Mountain
Distance Distance in
Route Route
in Km Km
Earthen 0 Earthen 0
Gravelled 0 Gravelled 0
Blacktop 0 Blacktop 25
Travelling out of Site
Plain Route Hilly/ Mountainous Terrain Route
Type of Total
Speed of Speed of Speed of
S.No. Travelling Speed of Distance Duration Distance Duration, Remarks
Unit Vehicle Vehicle Vehicle Duration of
Surface Vehicle of Travel of Travel of Travel (T1)+(T2)
(Loaded), (Loaded), (Empty), Travel (T2)
(Empty), V2 (D) (T1) (D)
V1 V1 V2
1 Earthen Route 20.00 25.00 - - 10.00 12.50 - - -
2 Gravelled Route 30.00 37.50 - - 15.00 18.75 - - -
Blacktopped
3 40.00 50.00 - - 20.00 25.00 25.00 2.25 2.25
Surface Route
Total Duration of
- - - 2.25
Travel
Descripti
Activity on of
Quantity Net
S.No. Resource No. Norms Works/ Unit Unit Rate Amount Remarks
per Unit Amount
No. Resource
Type
Transport
8.16
ation of
Materials
Tipper/Tr
Hour 2.25 1,408.00 3,168.00 3,168.00 8000
uck
0.396 for 1Kg
10 Transportation of RCC Humepipe by Truck
Plain( Terai) Hilly/Mountain
Distance Distance in
Route Route
in Km Km
Earthen 0 Earthen 0
Gravelled 0 Gravelled 0
Blacktop 0 Blacktop 5
Travelling out of Site
Plain Route Hilly/ Mountainous Terrain Route
Type of Total
Speed of Speed of Speed of
S.No. Travelling Speed of Distance Duration Distance Duration, Remarks
Unit Vehicle Vehicle Vehicle Duration of
Surface Vehicle of Travel of Travel of Travel (T1)+(T2)
(Loaded), (Loaded), (Empty), Travel (T2)
(Empty), V2 (D) (T1) (D)
V1 V1 V2
1 Earthen Route 20.00 25.00 - - 10.00 12.50 - - -
2 Gravelled Route 30.00 37.50 - - 15.00 18.75 - - -
Blacktopped
3 40.00 50.00 - - 20.00 25.00 5.00 0.45 0.45
Surface Route
Total Duration of
- - - 0.45
Travel
Descripti
Activity on of
Quantity Net
S.No. Resource No. Norms Works/ Unit Unit Rate Amount Remarks
per Unit Amount
No. Resource
Type
Transport
8.16
ation of
Materials
Tipper/Tr
Hour 0.45 1,408.00 633.60 633.60 8000
uck
Diameter Transportation
(mm) Cost per meter
300 20.21
450 39.00
600 59.45
900 118.13
1000 151.22
1200 196.23
Omsatiya Rural Municipality
Office of the Rural Municipal Executive
Hati Pharsatikar
Rupandehi
Lumbini Province
Collection of Materials
S No Description Unit Qty. Rate Amount Total Amount Remarks
8.1 Collection and sieving gravel including stacking within 10 m. Hauling distance.
8.1 A 5 - 70 mm size Unit = cum(for 1 cum) Unskilled day 2.00 652.00 1,304.00 1,343.12 T&P 3% of labour
8.1 B 5 - 40 mm size Unit = cum(for 1 cum) Unskilled day 3.00 652.00 1,956.00 2,014.68 T&P 3% of labour
8.1 C 5 - 20 mm size Unit = cum(for 1 cum) Unskilled day 4.00 652.00 2,608.00 2,686.24 T&P 3% of labour
8.1 D 5 - 08 mm size Unit = cum(for 1 cum) Unskilled day 6.00 652.00 3,912.00 4,029.36 T&P 3% of labour
8.1 E 40 - 70 mm size Unit = cum(for 1 cum) Unskilled day 4.00 652.00 2,608.00 2,686.24 T&P 3% of labour
8.1 F 70 - 100 mm size Unit = cum(for 1 cum) Unskilled day 3.00 652.00 1,956.00 2,014.68 T&P 3% of labour
Collection of rubble of required size,
8.2 Unit = cum(for 1 cum) Unskilled day 1.40 652.00 912.80 940.18 T&P 3% of labour
hauling distance 10 m. and stacking.
8.3 Collection and sieving sand .
8.3 A Quarry output less than 33% Unit = cum(for 1 cum) Unskilled day 4.00 652.00 2,608.00 2,686.24 T&P 3% of labour
8.3 B Quarry output 33 - 66 % Unit = cum(for 1 cum) Unskilled day 3.00 652.00 1,956.00 2,014.68 T&P 3% of labour
8.3 C Quarry output more than 66% Unit = cum(for 1 cum) Unskilled day 1.50 652.00 978.00 1,007.34 T&P 3% of labour
Collection, quarrying and sieving sand in
8.3 D Unit = cum(for 1 cum) Unskilled day 1.50 652.00 978.00 1,007.34 T&P 3% of labour
local river
8.4 Washing of Construction Material
8.4 A Washing broken stone, gravel and sand. Unit = cum(for 1 cum) Unskilled day 0.50 652.00 326.00 335.78 T&P 3% of labour
8.4 B Washing rubble Unit = cum(for 1 cum) Unskilled day 0.20 652.00 130.40 134.31 T&P 3% of labour
8.5 Manually Breaking stones ( excluding Collection of Rubble)
8.5 A 70 - 100 mm size Unit = cum(for 1 cum) Unskilled day 1.50 652.00 978.00 1,007.34 T&P 3% of labour
8.5 B 40 - 70 mm size Unit = cum(for 1 cum) Unskilled day 2.00 652.00 1,304.00 1,343.12 T&P 3% of labour
8.5 C 20 - 40 mm size Unit = cum(for 1 cum) Unskilled day 3.00 652.00 1,956.00 2,014.68 T&P 3% of labour
8.5 D 10 - 20 mm size Unit = cum(for 1 cum) Unskilled day 4.00 652.00 2,608.00 2,686.24 T&P 3% of labour
8.5 E 5 - 10 mm size Unit = cum(for 1 cum) Unskilled day 6.00 652.00 3,912.00 4,029.36 T&P 3% of labour
8.6 Mechanically Crushing of Stone Aggregates
13.2 mm Nominal Size Unit = cum(for 600 cum)
a) Labour at crusher location.
Skill day 2.00 965.00 1,930.00
Unskilled day 18.00 652.00 11,736.00
b) Material
8.6 A Stone boulder size 150mm cum 800 947.17 757,734.15
c) Equipment
Stone crusher with screen hour 12 2,086.00 25,032.00
Loader hour 18 2,445.00 44,010.00
Tipper hour 19 1,408.00 26,752.00
Total 867,194.15 1,445.32
20 mm Nominal Size for 670 cum Unit = cum(for 670 cum)
a) Labour at crusher location.
Skill day 2.00 965.00 1,930.00
Unskilled day 18.00 652.00 11,736.00
b) Material
Stone boulder size 150mm cum 800 947.17 757,734.15
8.6 B
c) Equipment
Stone crusher with screen hour 18 2,086.00 37,548.00
Loader hour 18 2,445.00 44,010.00
Tipper hour 18 1,408.00 25,344.00
Total 878,302.15 1,310.90
1 Stone(Rubble) 947.17
2 Sub Base Aggregate 1,250.64 According to
3 Base Aggregate 1,325.63 Standard
4 Capping Layer 1,182.38 Specification
5 Well Graded Filter Materials 1,180.03
8.04.0 Collection of Water from Local River
Unit = Liter (for 1,000 Liter)
2.17 into the Water Bowser
Skilled Labour day 0.01 965.00 9.65
Unskilled Labour day 0.10 652.00 65.20
Hou
Water Browser 0.05 2,190.00 109.50
r Previous Norms
Hou
Water Pump 0.05 44.00 2.20
r
3% of Labor Cost Tools and Plants 2.25
Total 188.80 0.19
Rate Analyis_Laboratory 15 of
1. Laboratory Setup including Supply of Electricity, Water, Gas and Heating etc.
Rate Amount
S.N. Description Unit Quantity Remarks
NRs. NRs.
A Laboratory Space Month 24.000 10,000.00 240,000.00
2. Providing, installing and maintaining Quality control laboratory with equipment as specified in the Technical
Specifications.
Unit: LS Specification Clause No: 504 Norms Reference No: 5.2
Rate Amount
S.N. Description Unit Quantity Remarks
NRs. NRs.
A Equipment and Furniture Cost
Laboratory Equipment Set 1.00 317,794.20 317,794.20
Laboratory Furniture Set 1.00 150,000.00 150,000.00
5% of
Accessories and Consumables LS Equipmen 15,889.71
t cost
Sub Total 3 483,683.91
Contractor's Overhead and Profit Cost (15%) 72,552.59
Total 556,236.50
Rate Amount
S.N. Description Unit Quantity Remarks
NRs. NRs.
A Laboratory staff
Lab Technician Month 24.00 28,950.00 694,800.00
Insurance Calculations
Material Rate
Adopted Rate is taken from (district rate+transportation rate+Loading Unloading) and (collection rate+royalty+transportation rate+Loading Unloading)
which ever is less.
1 Gravel
1.1 ( 5 - 70 mm size) m3 1553.85 266.11 231.18 266.11 2051.14
1.2 ( 5 - 40 mm size) m3 1553.85 0 266.11 231.18 266.11 2051.14
1.3 ( 5 - 20 mm size) m3 1553.85 0 266.11 231.18 266.11 2051.14
1.4 ( 5 - 08 mm size) m3 1553.85 0 266.11 231.18 266.11 2051.14
1.5 ( 40 - 70 mm size) m3 1553.85 0 266.11 231.18 266.11 2051.14
1.6 ( 70 - 100 mm size) m3 1553.85 0 266.11 231.18 266.11 2051.14
1.7 Rubble of required size m3 1553.85 0 0.00 231.18 0.00 1785.03
2 Broken Aggregates
2.1 ( 70 - 100 mm) m3 2048.25 0 266.11 231.18 266.11 2545.55
2.2 ( 40 - 70 mm) m3 2048.25 0 266.11 231.18 266.11 2545.55
2.3 ( 20 - 40 mm) m3 2048.25 0 266.11 231.18 266.11 2545.55
2.4 ( 10 - 20 mm) m3 2048.25 0 266.11 231.18 266.11 2545.55
2.5 ( 5 - 10 mm) m3 2048.25 0 266.11 231.18 266.11 2545.55
2.6 4.75mm and below m4 2048.25 266.11 231.18 2545.55
3 Sand m3 2118.88 1007.34 0 177.41 231.18 1184.75 1415.93
Round Aggregates
31
(Used in Analysis) .
70 to 100 mm cum 1500.00 0.00 231.18 0.00 1731.18
40 to 70mm cum 1500.00 0.00 231.18 0.00 1731.18
20 to 40 mm cum 1500.00 0.00 231.18 0.00 1731.18
10 to 20 mm cum 1500.00 0.00 231.18 0.00 1731.18
10 mm and down cum 1500.00 0.00 231.18 0.00 1731.18
32 Crusher Run Material 0.00
a 19 mm Nominal Size cum 2240.00 0 266.11 231.18 266.11 2737.29
13mm Nominal Size cum 2240.00 266.11 231.18 266.11 2737.29
b 10 mm Nominal Size cum 2240.00 0 266.11 231.18 266.11 2737.29
Base cum 1450.00 266.11 231.18 266.11 1947.29
Subbase cum 1250.00 1250.64 199.58 231.18 1450.23 1680.76
Well Graded Filter Material
1180.03 199.58 231.18 1610.79
cum
Capping Layer cum 1182.38 199.58 231.18 1613.14
Soil cum 80.00 44.35 231.18 355.53
Cement Concrete tile nos
102.00 102.00
(300*300*25)
50 mm thick Stone slab sqm 0.00 0.00
4 Brick nos. 13.35 0.47 0.65 0.47 14.47
5 Wood kg 14.00 14.00
5.a wood ( uttis) m3 45767.88 438.91 0.00 46206.80
5.b Sal wood m3 186885.52 438.91 0.00 187324.44
Timber Planks cum 45767.88 438.91 0.00 46206.80
6 Stone dust m3 953.50 0.00 0.00 953.50
7 Rubble m3 1500.00 940.18 0.00 0.00 940.18 940.18
8 Cement mt. 15479.27 7.92 412.00 7.92 15899.19
9 Water KL 188.80 0.31 188.80 189.10
10 Bitumen 80/100 Grade kg 113.00 0.40 0.31 0.40 113.71
Emulsion (MC) kg 96.00 0.40 0.31 0.40 96.71
Reinforcement steel mt. 93750.00 396.00 396.00 94146.00
11 Reinforcement (Tor Steel) 0.00
11.a 8 mm dia mt. 94000.00 158.40 412.00 158.40 94570.40
11.b 10 - 22 mm dia mt. 93000.00 158.40 412.00 158.40 93570.40
11.c 25 - 32 mm dia mt. 94000.00 158.40 412.00 158.40 94570.40
11.d 4.75 - 7 mm dia mt. 94000.00 158.40 412.00 158.40 94570.40
12 Binding Wire kg 106.00 158.40 158.40 264.40
13 G.I Wire heavy coated 0.00 0.00
13.a 8 gauge kg 120.00 0.16 0.16 120.16
13.b 10 gauge kg 120.00 0.16 0.16 120.16
13.c 12 gauge kg 120.00 0.16 0.16 120.16
13.d Machine made gabion box sqm 273.00 0.16 0.16 273.16
14 RCC Hume Pipes (NP3) 0.00 0.00
14.a 300mm diameter m 3953 20.21 395.12 20.21 4368.33
14.b 450mm diameter m 5798.00 39.00 395.12 39.00 6232.12
14.c 600 mm diameter m 7770.00 59.45 565.83 59.45 8395.28
14.d 750 mm diameter m 9000.00 59.45 565.83 59.45 9625.28
14.e 900 mm diameter m 14338.00 118.13 898.29 118.13 15354.41
14.f 1000 mm diameter m 15408.00 151.22 898.29 16457.50
14.g 1200 mm diameter m 18572.00 196.23 898.29 196.23 19666.52
PVC Pipes 100 mm dia 473.00 473.00
HDPE Pipe of 10 kg/cm2
27 0.00
pressure
Adopted
District Collection Royalty Transportation Loading Total Rate
S.N. Description Unit Rate Remarks
Rate (D) Rate (C) (R) Rate ( Tp ) /Unloading ( C + R + Tp)
HDPE pipe 90 mm m 525.00 0.00 525.00
HDPE pipe 200mm m 1575.00 1575.00 1575.00
HDPE pipes 250mm m 1995.00 1995.00
HDPE pipes 160mm m 1050.00 1050.00
15 Jute kg 90.00 0.00 90.00
16 Nails kg 120.00 0.00 120.00
17 Ply wood 0.00
17.a plywood 3 mm m2 387.50 0.00 387.50
17.b plywood 4 mm m2 301.39 0.00 301.39
17.c plywood 6 mm m2 570.49 0.00 570.49
17.d plywood 8 mm m2 613.54 0.00 613.54
17.e plywood 10 mm m2 480.00 0.00 480.00
17.f plywood 12 mm m2 861.11 0.00 861.11
17.g plywood 18 mm m2 1237.85 0.00 1237.85
Road marking thermoplastic lit. 258.00 0.31
18 0.00 258.31
paint
Reflectorizing glass beads Kg. 169.00 0.31 169.31
Road marking paint lit. 579.00 0.31 579.31
19 Enamel Paint lit. 545.00 0.31 0.00 545.31
20 Lime kg 31.00 0.31 0.00 31.31
21 Gum/Fevicol kg 151.00 0.31 0.00 151.31
22 Snow cem kg 60.00 0.31 0.00 60.31
23 Primer Lit. 319.00 0.31 0.00 319.31
24 Steel Plate(3 mm ) Sq. m 1287.40 281.60 0.00 1569.00
25 Steel tube(50 mm dia) Rm 232.87 412.00 0.00 644.87
Angle iron (mild steel) Kg 104.00 0.41 104.41
Anti-striping agent Kg 415.00 0.41 0.41 415.41
Road Stud (Cat eye) nos. 618.00 618.00
Asphalt filler Board sqm 500.00 500.00
26 GI Pipe Medium Class 0.00
26.a 40mm m 514.00 0.00 514.00
26.b 50 mm m 706.00 0.00 706.00
26.c 75 mm m 1122.00 0.00 1122.00
26.d 100 mm m 1680.00 0.00 1680.00
0.00
28 Bearing pad nos. 0.00 0.00
29 Geotextile m2 117.00 0.00 117.00
30 Expansion joint 0.00 0.00
Hot dip galvanized 0.41
Corrugated W beam sheet 3 200.41
mm thick Kg 200
Hot dip galvanized Channel 0.41
200.41
post 150 x 75 x 5 mm, Kg 200
Hot dip galvanized Spacer 0.41
200.41
Channel 150 x 75 x 5 mm Kg 200
Mild steel angle iron 75 x 40 x 0.41
6 mm, 3. m long @ 6.8 kg/m 1611.60 0.41 1612.01
Kg
District
4 Bio-Engineering Item
Rate
4.1 Hesian Jute sq.m 60.00
4.2 Tree/shurb Nos 12.00
4.3 Container seedlings Nos 12.00
4.4 Grass Slips Nos 3.30