MINKONSTRAK ENGINEERING & GEN.

SERVICES
Luga-it, Misamis Oriental
snippingTel. No. (063) 225-1906, Fax No. (063) 222-2513
E-mail Address: minkonstrak@yahoo.com

SAFETY, ENVIRONMENT RISK AND QUALITY RISK ASSESSMENT

Site : Restoration of Cladding Team Members: FVS. BALDOMERO, M.ALCOS, J.ATILLO Revision No.:

Location / Department : Approved by : Date Updated:

FM1 - Holcim Lugait Plant

Note 1: If the relevant control is not in place, the local supervisor must install additional controls (Extra supervision, Tool Box talks, warning signs, PPE, etc) until the appropriate control is in place.

Note 2: This RA should consider human behavior and capabilities of all personnel (employees, contractors, visitors) who have been given an appropriate induction that covers site hazards, use of standard PPE and the site rules and are trained in their resp

Note 3: This RA shall include Routine and non-routine activities: Routine- Company's routine or intended processes/ activities- usually are scheduled and planned(daily activities of equipment, operations and process) ; Non-routine - an extension of company's non routine activities.

Risk
CONTROLS Risk New New
Safety Envi. Quality Rating Respo Due Rating
Hazard Aspect Risk Consequence/Impact Rating
(L, M, contr nsible Date (L, M,
(L, M, H) Elimination Substitution Engineering Administration PPE ols
H) H)

Process/Activity : General Activities

Influence : Direct Indirect

Condition : Normal Abnormal Emergency

Activity : Routine Non-routine

1. Processing of permits x L - - - L

keep away from line of


Fall from height fire

close the area using


2. Instalaltion of c-purlins Dust ensure manlift is Wear Proper working
using manlift
x L hard barricades and - goggles and dust mask L
caution tapes checked and tagged
manlift failure before using

falling flux

keep away from line of


Fall from height fire

close the area using


3. Form Issue: 04/27/2011
Installation of angle bars Page 1 of 11 Wear Proper working
using manlift for canopy
x L hard barricades and - goggles and dust mask L
caution tapes
keep away from line of
Fall from height fire

Dust close the area using


3. Installation of angle bars ensure manlift is Wear Proper working
using manlift for canopy
x L hard barricades and - goggles and dust mask L
checked and tagged
caution tapes before using
manlift failure

falling flux

ensure electric drill is in


Fall from height good condition before
using
close the area using
4. Installation of cladding Wear Proper working
using manlift
x Dust L hard barricades and - ensure manlift is goggles and dust mask L
caution tapes checked and tagged
electrocution before using

ensure electric drill is in


Fall from height good condition before
using

Dust close the area using


5. repeat the process for both ensure manlift is Wear Proper working
sides of fm1
x L hard barricades and - checked and tagged goggles and dust mask L
caution tapes before using
electrocution

ensure electric drill is in


Fall from height good condition before
using

Dust close the area using


6. Do this for all the ensure manlift is Wear Proper working
Foundation to be demolished
x L hard barricades and - checked and tagged goggles and dust mask L
caution tapes before using
electrocution

ensure equipments used


flyig chunks of concrete are tagged and checked
before using

Dust wear proper Working


7.Housekeeping x L - - - Gloves, dust mask and L
working goggles

Form Issue: 04/27/2011 Page 2 of 11


Quality Risk Management
LIKELIHOOD/ PROBABILITY

ALMOST CERTAIN LIKELY POSSIBLE


IMPACT RATING
Occurs once a
Occurs monthly Occurs quarterly
year

Level A B C
C
Catastrophic H H H
o
5
n
s Major H H H
e 4
q
u Moderate H H M
e 3
n Minor
c M M L
2
e
Insignificant L L L
1

CATEGORY OPERATION

Catastrophic Plant operation disrupted for more than 15 days

Major Plant operation disrupted for 11 - 15 days

Moderate Operation may be disrupted for 5 to 10 days

Minor Operation disrupted for 2 - 4 days

Insignificant Operation disrupted for 1 day


ment
PROBABILITY

UNLIKELY RARE

Occurs between
Occurs once
3 years to 5
every two years
years

D E

H H

M M

M L

L L

L L

ATION

ys
H Safety Risk Assessment Matrix
More than Once or Once in Unlikely to
Once in 5
twice per twice per approx 15 happen in the
Risk Rating year year
years
years operation
A B C D E

Fatality 1 H H H M M

Permanent Disability 2 H H M M L

Lost Time Injury 3 H M M L L

Medical Treatment 4 M M L L L

First Aid Treatment


5 L L L L L
(Minor Impact)

Acceptable level of risk. Monitoring and measurements of associated


GREEN
important Environmental parameters. Effective control measures have
Low Risk (L)
already been established.

Risk level relatively considered acceptable. Action Plans should be


made to reduce the Risk - Develop or review existing document
YELLOW
procedures with defined operating criteria, including training of relevant
Medium Risk (M)
personnel where applicable, monitor and measure associated important
Environmental parameters.

Unacceptable level of risk. Work should not be started or shutdown


operation until the risk has been eliminated or reduced. Action Plans
RED should be made to reduce the Risk - Develop or review existing
High Risk (H) document procedures with defined operating criteria, including training of
relevant personnel where applicable, monitor and measure associated
important Environmental parameters.
85
Environment Aspect and Impact Assessment Matrix
LIKELIHOOD/ PROBABILITY
NORMAL LEGACY ABNORMAL/ EMERGENCY SI

Impact Rating Occurred in the


Occurs normally Occurred in the
Occurs due to plant between a
upon operation/ plant for the
past activities year ago to 3
activity past 12 months
years ago

Environment Reputation Level F E D C


Catas-trophic
Massive Impact International Effect H H H H
C 5
o
Major
n Major Impact National Effect H H H H
4
s
e Mode-rate
q Local Impact Local Effect M M H M
3
u
e Minor
Minor Impact Limited Effect L L M L
n 2
c Insignificant
e Slight Impact Slight Effect L L L L
1
No Effect
Zero Impact No Effect L L L L
0

RISK-BASED CONTROL PLAN


GREEN
Acceptable level of risk. Monitoring and measurements of associated important Environmental parameters. Effective control measures h
Low Risk
established.
(L)

YELLOW Risk level relatively considered acceptable. Action Plans should be made to reduce the Risk - Develop or review existing document proce
Medium Risk (M) operating criteria, including training of relevant personnel where applicable, monitor and measure associated important Environmental pa

RED Unacceptable level of risk. Work should not be started or shutdown operation until the risk has been eliminated or reduced. Action Plans
High Risk the Risk - Develop or review existing document procedures with defined operating criteria, including training of relevant personnel where
(H) measure associated important Environmental parameters.
x
BABILITY
RMAL/ EMERGENCY SITUATION

Never occurred 5
Occurred in the
years ago and
plant between 3
beyond or never
years to 5 years
occurred in the
ago
plant

B A

H M

M M

M M

L L

L L

L L
fective control measures have already been

w existing document procedures with defined


mportant Environmental parameters.

d or reduced. Action Plans should be made to reduce


relevant personnel where applicable, monitor and
OCCUPATIONAL HEALTH, SAFETY AND ENVIRONMENT RISK ASSESSMENT

REVISION HISTORY

Reasons for Change Details Date Approved by