DWP- 05-07-23 (1)
DWP- 05-07-23 (1)
Balance - Weekly
Weekly Planned
Today Executed
Remark
UOM
Plan
Qty.
Name of Structure Manpower Distribution Description of Weekly Work Plan
Qty
Qty
M H CP BB SC W Str. O PIT
Sub-Station
Vikas/ Pandey Wall Casting 1st lift Cum 165 0 165 165 0 Completed
Areation tank RCC Wall 2nd lift scaffolding Sqm 110 0 0 110
2 6 8 6 14
RCC Wall 2nd lift reinforcement MT 6 0 0 6
Under reamed pile Nos 17 0 0 17
STP
Yellow soil filling Cum 40 0 0 40 30
24 TPD building
Plinth beam PCC Rmt 50 10 10 40
Plinth beam reinforcement Rmt 50 10 10 20 30
Tie Beam
plinth beam shuttering Rmt 50 10 10 20 30
Plinth beam Casting Rmt 50 10 10 40 10
Pedestal Shuttering Nos 15 1 1 14
Pedestal Works 1 6 6 8
Bolt Fixing Nos 15 1 1 14
Pedestal Works 1 6 6 8
Pedestal Casting Nos 15 0 3.5 4 12
Pile Cap Back Filling Cum 150 0 0 150
Column starter Nos 8 9 9 -1 5
Column reinforcement- 1st Lift Nos 8 6 3 9 -1 4
Column works
Column Shuttering- 1st lift Nos 8 0 7 7 1 2
Column Casing- 1st lift Nos 8 0 0 8
Flaker & Warehouse
Column starter Nos 23 12 12 11
Column reinforcement- 3rd Lift Nos 10 6 6 12 -2
Column works
Column Shuttering- 3rd lift Nos 15 2 2 4 11
Column Casing- 3rd lift Nos 15 0 4 4 11
Yellow soil filling Cum 100 0 0 100
Warehouse filling
AAC Block Cum 40 18 18 22
Admin & Canteen Building
Pile Cap Excavation Nos 10 0 0 10 5
Pile Cap PCC Nos 10 0 0 10
Pile Chipping Nos 10 0 0 10
Pile Cap Works
Reinforcement Nos 12 0 0 12
Shuttering Nos 12 0 0 12
Ranit koley Casting Nos 12 0 0 12
2 6 12 4 10 1
Distillation Unit
Pedestal Shuttering Nos 8 3 2 5 3 2
Bolt Fixing Nos 8 3 3 5 2
Distillation Building
Pedestal Casting Nos 8 3 3 5 2
Back Filling Cum 100 0 0 100
Pipe rack -PR-18
Pile cap Excavation Cum 150 0 0 150 20
RTO package
Reinforcement MT 2.5 0 0 3
Stack Other Foundations Shuttering Sqm 30 0 0 30
Casting Cum 22 0 0 22
Road works
Excavation Rmt 50 0 20 20 30
Yellow soil Filling- Layer 1 Rmt 80 0 20 20 60 20
Yellow soil Filling- Layer 2 Rmt 80 0 20 20 60
Road works Yellow soil Filling- Layer 3 Rmt 80 0 20 20 60
Yellow soil Filling- Layer 4 Rmt 80 0 20 20 60
GSB Filling Rmt 120 0 0 120
WBM Rmt 100 0 0 100
Hume pipe excavation Rmt 75 0 0 75
Kishore/ Dhamu Kumar Hume pipe PCC Rmt 75 0 0 75
1 5 7 1 JCB,2 Tractor, 1 farana
Crossing Works Hume Pipe Fixing Rmt 74 0 0 74
Hume Pipe Shuttering Rmt 50 0 0 50
Hume pipe Encasing Rmt 50 7 7 43
Drain Excavation Rmt 125 0 0 125
Drain PCC Rmt 125 0 0 125
Drain Works Drain laying Rmt 125 0 0 125
Filling Cum 350 45 45 305
Chamber Works Nos 8 0 0 8
Structural Works
Blasting and Primer MT 100 43 10 53 47
Fabrication MT 15 3 3 12
Fumeric Acid Plant Final Painting Mt 50 0 4 4 46 5
Erection MT 50 0 19 19 31 5
0 0 5
Fabrication MT 50 0 2 2 48
Mr. Chinmey
Pipe rack- 3 JLG, 1 Tailor, 1 Crane
Final Painting MT 35 5 5 30
120 0 0
Fabrication MT 0 0 0 0
PAC Crystallizer Final Painting MT 4 0 4 4 0
Erection MT 14 0 0 14 3
Fabrication MT 30 3 4 7 23
TG/TB Building
Final Painting MT 30 2 3.5 6 25 3
Fabrication MT 50 4 4 8 42
Distillation Building
Final Painting MT 40 0 1.5 2 39 2
Pradip Electrician 2 Light Fixing Work
Ajay Store 1 Material supply
Imran Surveying work 1 2 Oxidation building, Sub-station,
Chandra Safety 4 Safety work, Material shifting
Ali QC lab/Curing 1 Hand overing
Ramesh Batching Plant 2 Mechanical work
Total 12 44 54 33 37 3 120 7 5
Mason 12 600 20 20 580 188
Unskilled/ Helper 44 Total Concrete Qty Executed Cum
Carpenter 54 Total Concrete Qty Planned for Tomo 188 Cum
Fitter 33 Remarks - Material Requirement Remarks:-
1. Foundation bolt Today all concreteing and structural works has
Scafolder 37 2. Pine wood been hampered due to non-availblity of vechicle
3. movement and the preparation is In progress
Welder 3
Supervisor 8
Strl. Steel Workers 120
Others 7
Piling Work 5
Total 323
Total Planned Amount
ROHAN BUILDERS (I) PVT LTD
TCLIPL D2 PROJECT, DAHEJ.
PILE WORK DETAILS
Till Previous
Today
Sr.No Building Units Total Qty day
Completed
completed
1 RW & FW Tank
Tank B Nos 67 67
Tank A Nos 67 67
2 Oxidation Unit
Reactor Nos 30 30
Scrubber Nos 16 16
Tank A Nos 62 62
Tank B Nos 62 62
4 Turbine unit
Chimney Nos 4 4
6 Distillation unit
Staircase Nos 8
9 DM Plant Nos 15 15
16 Admin Nos 42 42
17 Store Nos 68 68
21 RO Plant Nos 34 34
25 STP Nos 17 0
67 Completed
67 Completed
30 Completed
188 Completed
5 Completed
25 0 Completed
8 Completed
16 Completed
8 Completed
14 Completed
4 Completed
16 Completed
4 Completed
5 Completed
62 Completed
62 Completed
40 Completed
30 Completed
30 Completed
40 Completed
4 - Completed
4 Completed
4 Completed
6 Completed
16 Completed
16 Completed
16 Completed
59 Completed
343 Completed
32 Completed
15 Completed
17 Completed
12 Completed
10 Completed
169 Completed
23 Completed
9 Completed
8 Completed
168 Completed
233 Completed
12 Completed
16 Completed
42 Completed
68 Completed
97 Completed
36 0 Completed
21 0 Completed
29 0 Completed
12 0 Completed
34 0 Completed
27 0 Completed
9 0 Completed
Till Previous
Sr.No Building Units Total Qty
day completed
A Road Works
1 Reactor Foundation Road
Road Excavation Rmt 350 350
Yellow soil filling Rmt 350 350
GSB Filling Rmt 350 350
WMM Rmt 350 350
2 Other Structure roads
Road Excavation Rmt 1250 402
Yellow soil filling Rmt 1250 751.5
GSB Filling Rmt 1250 260
WMM Rmt 1250 120
B Crossing Works
1 Hume pipe
Hume Pipe Excavation Rmt 1731 1024
Hume Pipe PCC Rmt 1731 1011
Hume Pipe Pipe fixing Rmt 1731 999
Hume Pipe Pipe Encasing Rmt 1100 637
C Pre-Cast Drain Works
1 Pre-Cast Drain Works
Pre-cast Excavation Rmt 2258 1560
Pre-cast PCC Rmt 2258 1560
Pre-cast laying Rmt 2258 1540
Today Cumulative Tomorrow
Balance Remarks
Completed Completed Plan
350 0 Completed
350 0 Completed
350 0 Completed
350 0 Completed
0 1024 707 20
Work front is not availble
0 1011 720 30
0 999 732 25
0 637 463 36
0 1560 698 40
0 1560 698 40
0 1540 718 60
Sr.No Site Engg Name Building Name
1 2
2 2 1
1
2 3 1 1
1
1
1 2
6 6 3 0 3 1 1 1
Acitivity