Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 13

Project - TCLIPL D2Project, Dahej

Work Planning for 06/07/23

This week Executed


Engineer/ In charge

Balance - Weekly
Weekly Planned

Today Executed

Next Day Plan


Previous Day
Executed Qty

Remark
UOM

Plan
Qty.
Name of Structure Manpower Distribution Description of Weekly Work Plan

Qty

Qty
M H CP BB SC W Str. O PIT
Sub-Station

Slab Scaffolding Sqm 77 77 77 0 Completed


Slab Works Slab Shuttering Sqm 300 100 70 170 130 60
Slab reinforcement Mt 15 2 2 4 11 3
RO Plant
Pile cap excavation Nos 3 0 0 3
Pile Chipping Nos 12 0 0 12
Pile Cap Reinforcement Nos 3 0 0 3
Shuttering Nos 3 0 0 3
Casting Nos 3 0 0 3
Thermic Fluid heater
Dyphil tank Pedestal casting Cum 2.5 0 0 3
DG unit
Md. Saif
DG Foundation 1 8 27 13 9 5 Back Filling Cum 30 0 0 30
Pipe Rack -12
Pile Cap reinforcement Nos 3 0 0 3 3
Pile Cap Pile Cap Shuttering Nos 3 0 0 3
pile Cap Casting Nos 3 0 0 3
Pedestal reinforcement Nos 4 4 4 0
Pedestal Works Pedestal shutering Nos 4 0 0 4
Pedestal Casting Nos 4 0 0 4
Raw water collection sump
Pile cap excavation Nos 2 0 0 2 2 1 JCB, 2 tractor
Pile Cap PCC Nos 2 0 0 2
Pump foundation pile cap Pile Cap reinforcement Nos 2 0 0 2
Pile Cap Shuttering Nos 2 0 0 2
Piel Cap RCC Nos 2 0 0 2
Oxidation Unit
Salt Day Tank Back Filling Sqm 130 50 30 80 50 20
Excavation Cum 15 0 0 15
PCC Cum 1 0 0 1
BFW preheater Reinforcement MT 1.5 0 0 2
Shuttering Sqm 8 0 0 8
Casting Cum 4 0 0 4
Rampratap/ shiv
Pedestal Reinforcement Mt 0.1 0.0 0.0 0.1
HP Flash Draum Pedestal Shuttering Sqm 12 0 0 12
Pedestal casting Cum 3 0 0 3
Pedestal Reinforcement Cum 0.3 0 0.0 0.3
Drain weighing System tank Pedestal Shuttering Cum 12 0 0 12
Pedestal casting Cum 2 0 0 2
Oxidation Building Grouting Nos 15 0 0 15
Turbine unit
Plinth beam Casting Rmt 7 7 7 0
4.1 MW ACC unit Pedestal shuttering- 2nd lift Nos 2 0 0 2
Pedestal Casting-2nd lift Nos 2 0 0 2
Column Shuttering Nos 3 1 1 2
5 MW Turbine unit
Column Casting Nos 3 0 1 1 2
Pedestal shuttering- 2nd lift Nos 2 0 1 1 1 1
5.1 ACC unit
Pedestal Casting-2nd lift Nos 2 0 0 2 1
Collection pit Back Filling Cum 150 0 0 150
Pile Cap excvation Nos 5 0 0 5
Pile chipping Nos 15 0 0 15
Shiv Pile Cap PCC Nos 5 1 1 4
2 10 7 6 6 2
Pile Cap reinforcement Nos 5 0 0 5
Pile Cap Shuttering Nos 5 0 0 5
TG/TB Building
Pile Cap RCC Nos 5 0 0 5
Back Filling Cum 200 0 0 200
Pedestal shutering Nos 8 1 1 2 6 1
Bolt Fixing Nos 8 2 2 6 1
Pedestal casting Nos 8 1 1 2 6 1
Slab Shuttering Sqm 39 0 0 39
4 MW turbine Slab reinforcement MT 7.68 1 1 2 6 2
Slab Casting Cum 64 0 0 64
ETP & STP
Column reinforcemnt Mt 3 3 3 0 Completed
UASB reactor
Wall Shuttering- 2nd lift Sqm 250 110 40 150 100 30

Vikas/ Pandey Wall Casting 1st lift Cum 165 0 165 165 0 Completed
Areation tank RCC Wall 2nd lift scaffolding Sqm 110 0 0 110
2 6 8 6 14
RCC Wall 2nd lift reinforcement MT 6 0 0 6
Under reamed pile Nos 17 0 0 17
STP
Yellow soil filling Cum 40 0 0 40 30
24 TPD building
Plinth beam PCC Rmt 50 10 10 40
Plinth beam reinforcement Rmt 50 10 10 20 30
Tie Beam
plinth beam shuttering Rmt 50 10 10 20 30
Plinth beam Casting Rmt 50 10 10 40 10
Pedestal Shuttering Nos 15 1 1 14

Pedestal Works 1 6 6 8
Bolt Fixing Nos 15 1 1 14
Pedestal Works 1 6 6 8
Pedestal Casting Nos 15 0 3.5 4 12
Pile Cap Back Filling Cum 150 0 0 150
Column starter Nos 8 9 9 -1 5
Column reinforcement- 1st Lift Nos 8 6 3 9 -1 4
Column works
Column Shuttering- 1st lift Nos 8 0 7 7 1 2
Column Casing- 1st lift Nos 8 0 0 8
Flaker & Warehouse
Column starter Nos 23 12 12 11
Column reinforcement- 3rd Lift Nos 10 6 6 12 -2
Column works
Column Shuttering- 3rd lift Nos 15 2 2 4 11
Column Casing- 3rd lift Nos 15 0 4 4 11
Yellow soil filling Cum 100 0 0 100
Warehouse filling
AAC Block Cum 40 18 18 22
Admin & Canteen Building
Pile Cap Excavation Nos 10 0 0 10 5
Pile Cap PCC Nos 10 0 0 10
Pile Chipping Nos 10 0 0 10
Pile Cap Works
Reinforcement Nos 12 0 0 12
Shuttering Nos 12 0 0 12
Ranit koley Casting Nos 12 0 0 12
2 6 12 4 10 1
Distillation Unit
Pedestal Shuttering Nos 8 3 2 5 3 2
Bolt Fixing Nos 8 3 3 5 2
Distillation Building
Pedestal Casting Nos 8 3 3 5 2
Back Filling Cum 100 0 0 100
Pipe rack -PR-18
Pile cap Excavation Cum 150 0 0 150 20
RTO package
Reinforcement MT 2.5 0 0 3
Stack Other Foundations Shuttering Sqm 30 0 0 30
Casting Cum 22 0 0 22
Road works
Excavation Rmt 50 0 20 20 30
Yellow soil Filling- Layer 1 Rmt 80 0 20 20 60 20
Yellow soil Filling- Layer 2 Rmt 80 0 20 20 60
Road works Yellow soil Filling- Layer 3 Rmt 80 0 20 20 60
Yellow soil Filling- Layer 4 Rmt 80 0 20 20 60
GSB Filling Rmt 120 0 0 120
WBM Rmt 100 0 0 100
Hume pipe excavation Rmt 75 0 0 75
Kishore/ Dhamu Kumar Hume pipe PCC Rmt 75 0 0 75
1 5 7 1 JCB,2 Tractor, 1 farana
Crossing Works Hume Pipe Fixing Rmt 74 0 0 74
Hume Pipe Shuttering Rmt 50 0 0 50
Hume pipe Encasing Rmt 50 7 7 43
Drain Excavation Rmt 125 0 0 125
Drain PCC Rmt 125 0 0 125
Drain Works Drain laying Rmt 125 0 0 125
Filling Cum 350 45 45 305
Chamber Works Nos 8 0 0 8
Structural Works
Blasting and Primer MT 100 43 10 53 47
Fabrication MT 15 3 3 12
Fumeric Acid Plant Final Painting Mt 50 0 4 4 46 5
Erection MT 50 0 19 19 31 5
0 0 5
Fabrication MT 50 0 2 2 48
Mr. Chinmey
Pipe rack- 3 JLG, 1 Tailor, 1 Crane
Final Painting MT 35 5 5 30
120 0 0
Fabrication MT 0 0 0 0
PAC Crystallizer Final Painting MT 4 0 4 4 0
Erection MT 14 0 0 14 3
Fabrication MT 30 3 4 7 23
TG/TB Building
Final Painting MT 30 2 3.5 6 25 3
Fabrication MT 50 4 4 8 42
Distillation Building
Final Painting MT 40 0 1.5 2 39 2
Pradip Electrician 2 Light Fixing Work
Ajay Store 1 Material supply
Imran Surveying work 1 2 Oxidation building, Sub-station,
Chandra Safety 4 Safety work, Material shifting
Ali QC lab/Curing 1 Hand overing
Ramesh Batching Plant 2 Mechanical work
Total 12 44 54 33 37 3 120 7 5
Mason 12 600 20 20 580 188
Unskilled/ Helper 44 Total Concrete Qty Executed Cum
Carpenter 54 Total Concrete Qty Planned for Tomo 188 Cum
Fitter 33 Remarks - Material Requirement Remarks:-
1. Foundation bolt Today all concreteing and structural works has
Scafolder 37 2. Pine wood been hampered due to non-availblity of vechicle
3. movement and the preparation is In progress
Welder 3
Supervisor 8
Strl. Steel Workers 120
Others 7
Piling Work 5
Total 323
Total Planned Amount
ROHAN BUILDERS (I) PVT LTD
TCLIPL D2 PROJECT, DAHEJ.
PILE WORK DETAILS
Till Previous
Today
Sr.No Building Units Total Qty day
Completed
completed

1 RW & FW Tank

Tank B Nos 67 67

Tank A Nos 67 67

2 Oxidation Unit

Reactor Nos 30 30

Oxidation Building Nos 188 188

Stack RTO Package Nos 5 5

RTO Package Nos 25 25

Crude PA DAY Tank Nos 8 8

Hot & Cold Oil tank Nos 16 16

Gas cooler Nos 8 8

Salt DAY tank Nos 14 14

AIR pre heater Nos 4 4

Scrubber Nos 16 16

HP Flash Drum Nos 4 4


TFH Drain weighing system
Nos 5 5
tank
3 O-xylene Tank Farm

Tank A Nos 62 62

Tank B Nos 62 62

4 Turbine unit

5.1 MW Turbine Nos 40 40

4.1 MW ACC Unit Nos 30 30


5 MW ACC Unit Nos 30 30

4.1 MW Turbine Nos 40 40

Ejector skid Nos 10

Stem duct of hexacool Nos 10

TG/Tb Building staircase Nos 12

5 Thermic Fluid heater Nos 4 4

Chimney Nos 4 4

TFH Air preheater Nos 4 4

Dyphil DAY tank Nos 6 6

6 Distillation unit

Pre treatment vessels Nos 16 16

Crude PA tank Nos 16 16

Pure PA tank Nos 16 16

Distillation unit Nos 59 59

Staircase Nos 8

7 ETP Nos 343 343

8 Main cooling tower Nos 32 32

9 DM Plant Nos 15 15

DM Water tank Nos 17 17

RO Premeate Tank Nos 12 12

Neutralization tank Nos 10 10

10 24 TPD Building Nos 169 169

Main MAC Receiver Nos 23 23

Caustic, Condensate &


Nos 9 9
Distillate Tanks

11 DG Unit (30m high stack) Nos 8 8

12 Substation and Centralized Nos 168 168

13 Flaker and Warehouse Nos 233 233


14 Transformer yard Nos 12 12

15 PAC Crystallizer Nos 16 16

16 Admin Nos 42 42

17 Store Nos 68 68

18 Turbine surrounding Area Nos 97 97

19 Pipe rack-10 (Under remead) Nos 36 36

Pipe rack-11 (Under remead) Nos 40 36

Pipe rack-12 (Under remead) Nos 21 21

Pipe rack (Hydrulic) - PR-18 Nos 29 29

Pipe rack (Hydrulic) - PR-15 Nos 12 12

Pipe rack-1 (Under remead) Nos 13

Pipe rack-2 (Under remead) Nos 7

Pipe rack-14 (Under remead) Nos 11

Pipe rack-16 (Under remead) Nos 23

21 RO Plant Nos 34 34

RO plant RCC Tank Nos 27 27

NaOH and HCL Tank Nos 9 9

23 Raw water intake sump Nos 4 4

24 MCC Lab room Nos 15

25 STP Nos 17 0

26 Security cabin Nos 4

Total Nos 2462 2328 0


Cumulative Tomorrow
Balance Remarks
Completed Plan

67 Completed

67 Completed

30 Completed

188 Completed

5 Completed

25 0 Completed

8 Completed

16 Completed

8 Completed

14 Completed

4 Completed

16 Completed

4 Completed

5 Completed

62 Completed

62 Completed

40 Completed

30 Completed
30 Completed

40 Completed

0 10 Undre reamed pile, drawingreceived on 24th june

0 10 Undre reamed pile, drawingreceived on 24th june

0 12 Drawing received on 29th june

4 - Completed

4 Completed

4 Completed

6 Completed

16 Completed

16 Completed

16 Completed

59 Completed

0 8 Drawing received on 29 June, hydraulic pile

343 Completed

32 Completed

15 Completed

17 Completed

12 Completed

10 Completed

169 Completed

23 Completed

9 Completed

8 Completed

168 Completed

233 Completed
12 Completed

16 Completed

42 Completed

68 Completed

97 Completed

36 0 Completed

36 4 4 Nos pile hold due to fouling with crossing

21 0 Completed

29 0 Completed

12 0 Completed

0 13 Drawing received on 14 June area soil filling required

0 7 Drawing received on 27 June

0 11 Drawing received on 29 June

0 23 Drawing received on 29 June

34 0 Completed

27 0 Completed

9 0 Completed

4 0 Drawing received on 24th June, soil filling required

0 15 Drawing received on 29 June

0 17 Drawing received on 24th June, soil filling required

0 4 Waiting for area clearence

Pilling workers are stopped due to bad weather


2328 134
condition
ROHAN BUILDERS (I) PVT LTD
TCLIPL D2 PROJECT, DAHEJ.
ROAD WORK DETAILS

Till Previous
Sr.No Building Units Total Qty
day completed

A Road Works
1 Reactor Foundation Road
Road Excavation Rmt 350 350
Yellow soil filling Rmt 350 350
GSB Filling Rmt 350 350
WMM Rmt 350 350
2 Other Structure roads
Road Excavation Rmt 1250 402
Yellow soil filling Rmt 1250 751.5
GSB Filling Rmt 1250 260
WMM Rmt 1250 120
B Crossing Works
1 Hume pipe
Hume Pipe Excavation Rmt 1731 1024
Hume Pipe PCC Rmt 1731 1011
Hume Pipe Pipe fixing Rmt 1731 999
Hume Pipe Pipe Encasing Rmt 1100 637
C Pre-Cast Drain Works
1 Pre-Cast Drain Works
Pre-cast Excavation Rmt 2258 1560
Pre-cast PCC Rmt 2258 1560
Pre-cast laying Rmt 2258 1540
Today Cumulative Tomorrow
Balance Remarks
Completed Completed Plan

350 0 Completed
350 0 Completed
350 0 Completed
350 0 Completed

402 848 After completion of road


751.5 498.5 35 crossing works, road filling will
260 990 30 be started
120 1130 35

0 1024 707 20
Work front is not availble
0 1011 720 30
0 999 732 25
0 637 463 36

0 1560 698 40
0 1560 698 40
0 1540 718 60
Sr.No Site Engg Name Building Name

1 Md.Saif Pipe rack-12/ cable trench


2 Kishore/Dhamu Kumar Road Work/ Crossing Work
3 Shiv singh TG/TB Building/ Oxidation building
4 Chinmey Structural
5 Mukhiya Batching plant
6 Chandra Water sprinkling
7 Pintu kumar Reactor area soil filling/material shifting
Total
Machinery

JCB Tractor Farana Roller JLG Crane Trailer Tanker

1 2
2 2 1
1
2 3 1 1
1
1
1 2
6 6 3 0 3 1 1 1
Acitivity

Pile cap excavation and sand laying


Road Crossing and drain Laying
Pile cap excavation and concreting work
Structural steel erection
Bulk Material Shifting
Water sprinkling
Rebar shifting, and concrete working

You might also like