REPUBLIC OF THE PHILIPPINES

Province of Nueva Vizcaya


Bagabag

PROJECT TITLE: A Proposed (Two) Storey Residential Building


LOCATION: San Geronimo St., Villa Coloma, Bagabag, Nueva Vizcaya

BILL OF LABORS AND MATERIALS


MATERIALS
I.Site Works 25,000.00
Description of Particulars Qty Unit Unit Cost Amount
Demolision 6.00 day 500.00 3,000.00
Clearing and Grabbing 6.00 day 1,000.00 6,000.00
Layouting 100.00 bdft 60.00 6,000.00
Backfill 20.00 sqm 500.00 10,000.00

II.Side Fence Works 35,604.00


Description of Particulars Qty Unit Unit Cost Amount
10mm RSB 20.00 pcs 175.00 3,500.00
12mm RSB 15.00 pcs 240.00 3,600.00
CHB 300.00 pcs 12.00 3,600.00
Cement 30.00 bag 230.00 6,900.00
Tubular Bar 1" x 1" 15.00 pcs 320.00 4,800.00
Flat Bar 1" x 1" 2.00 pcs 580.00 1,160.00
Welding Rod 3.00 box 240.00 720.00
Flap Disc/ Cutting Disc 15.00 pcs 60.00 900.00
Round Bar 12MM 1.00 pc 420.00 420.00
Rust Converter 2.00 pc 260.00 520.00
Gray Epoxy Primer with Catalist 1.00 gals 970.00 970.00
A & B Epoxy 2.00 can 400.00 800.00
Thinner 2.00 gal 730.00 1,460.00
Baby Roller 2.00 pcs 50.00 100.00
Paint Brush 4" 2.00 pcs 110.00 220.00

III.Equipments 9,600.00
Description of Particulars Qty Unit Unit Cost Amount
Chipping Gun/ Demolision Hammer 6.00 day 400.00 2,400.00
Welding Machine 18.00 day 400.00 7,200.00

TOTAL MATERIAL COST 35,604.00

SUMMARY OF MATERIAL COST


II.Side Fence Works 35,604.00

Total Material Cost (A) 35,604.00


LABOR COST
I.Site Works 25,000.00
II.Side Fence Works 17,089.92
III.Equipments 9,600.00
Total Labor Cost (B) 51,689.92
TOTAL MATERIAL COST (A) 35,604.00
TOTAL LABOR COST (B) 51,689.92
TOTAL PROJECT COST (A+B) 87,293.92

Collection= Professional Fee


6,689.92

Prepared By:

BRYAN PAUL S. TALLOD, CE, SO


Civil Engineer

Approved by:

MRS. GLORIA O. NAPE


Owner