IR BOXN Rake Unloading Report 11-Jun-24

No of No of No of Avg. Avg.
Free Total
Station Rakes Rakes Rakes in Cycle Unloading Remarks
Time Dem Hrs
Received Delayed Free Time Time Time

Dadri 6 6 0 07:00 10:36 04:24 21:40 System Design Issue.


MUNL, Meja 5 4 1 05:00 09:14 08:02 21:20 No Reason Provided By Station
BRBCL, Nabinagar 1 1 0 07:00 09:00 06:40 02:00 No Reason Provided By Station
Incomplete Facility. Chp System Handling Constraints, Metallic Nature Coal , Sampling
KBUNL, Kanti 1 1 0 07:00 08:40 07:05 01:40 Delay.
Barh 5 2 3 07:00 07:34 06:15 02:55 BULGED WAGON. knucke fallen & SAC-4 rack segment bolt loose.
Solapur 2 2 0 05:00 06:57 04:12 03:55 No Reason Provided By Station
APCPL, Jhajjar 6 4 2 07:00 06:29 04:00 09:00
NPGCL, Nabinagar 6 0 6 07:00 06:20 03:33 00:00
Unchahar 4 0 4 07:00 06:05 04:13 00:00

Gadarwara 5 1 4 05:00 05:45 04:33 04:00 TONE BOULDERS-BIG SIZE COAL 1 HRS 20 MIN, WAGON TIPPLER PROBLEM 4 HRS 20 MIN.
Kudgi 2 1 1 05:00 05:15 04:19 00:30 No Reason Provided By Station
Tanda 4 0 4 07:00 05:12 03:37 00:00
Mouda 4 2 2 05:00 04:57 03:47 01:25
Simhadri 6 0 6 05:00 04:42 04:42 00:00
Ramagundam 2 0 2 07:00 06:42 05:05 00:00
Total 59 24 35 68:25

BOXN Unloading Report


10:36

09:14

09:00

08:40

12:00
08:02

07:34
07:05

06:57

06:42
06:40

06:29

06:20
06:15

06:05
09:36

05:45

05:15

05:12

05:05
04:57

04:42
04:42
04:33
04:24

04:19
04:13
04:12

04:00

03:47
03:37
03:33

07:12
04:48
02:24
00:00

Avg. Cycle Time Avg. Unloading Time Free Time