PROJECT

PROPOSAL
SUPPLY AND LAY OF NEW OD 400 mm HDPE SUBMARINE
PIPELINE FROM PERNU TO PULAU BESAR, MELAKA
Prepared by MS CONSULTANT & RESOURCES
1 9 th M a r c h 2 0 2 4

1
1.0 Introduction by Consultant
1.1 Background 3

1.2 Introduction 4–5

1.3 3 Long Term Measures Proposed 6

2.0 Project Presentation by Consultant


Table of 2.1 Proposed Project Objective 7

contents 2.2 Proposed Project Scope of Work

2.3 Proposed Pipeline Route


8

9 – 11

2.4 Method of Installation 12 – 31

2.5 Authorities Involved 32

2.6 Proposed Consulting Engineer Scope of Works 34 – 36

2.7 Proposed Project Timeline 37

3.0 Q&A Session


Background
Introduction
PULAU BESAR, MELAKA is located about 15km south east
of Melaka city and can be reached by ferry or speed boat. As the
name suggests, it is a large island (168 hectares). However, there
are approximately only 300 populations with most of them studied
in Tahfiz Centre in Pulau Besar.

Pulau Besar daily consumption is 30,000 GPD. However, the largest


land owner of Pulau Besar, Perbadanan Kemajuan Negeri Melaka
(PKNM) mooted the idea to develop the area as tourism attraction
by constructing hotels in line with State Government of Melaka to
flourish further their tourism sector which had contributed largest
income to the state’s coffer.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
3 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Introduction

The treated water source from Duyung Lama Reservoir ● A study was made to study the feasibility to extract
(Cap: 2 MG, TWL: 41.46 m, BWL: 36.46 m) deliver the water groundwater in Pulau Besar. The study comprises
via DN600mm mild steel pipes laid from Duyung, Pekan investigation and hydrogeological survey and construction of
Ayer Molek, Kampung Bukit Lintang, Taman Telok Mas production well and constructing compact packaged plant
and Jalan Pernu before cross from the mainland in Pernu or desalination plant.
to Pulau Besar via DN400 HDPE submarine pipes. The
water will then store into Pulau Besar Reservoir (Cap: 0.22 ● The study had cost SAMB RM 0.453 million. Over the long
MG, TWL: 24.30 m, BWL: 20.30 m). The existing submarine run, treatment and production cost by desalination process
pipes was laid back in 1994. is high at RM 2.40/cu.m in comparison to only RM 1.14/cu.m
by normal conventional treatment process. With logistic and
SAMB had carried out short term measures to preserve access will remain become problems for operation and
the conveyance of treated water to Pulau Besar. maintenance, groundwater extraction and conventional
treatment plant in Pulau Besar was found not a sustainable
It was reported four (4) major leaks occurred in the option.
existing submarine pipeline, on 25 April 2017, 4 August
2017, 13 March 2018, 26 November 2018. With a whooping
cost of nearly RM 2.5 million spent, it becomes unbearable
to address the issue without implementing long term
measure to resolve the leaks problem once and for all.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
4 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Introduction

● Subsequently in year 2020, a Seawater Reverse Osmosis


(SWRO) plant cost SAMB RM 3.1 million was completed in
Pulau Besar with design production capacity of 20,000
litre/hr (0.48 MLD @ 0.1 MGD).

● Yet, over the years, the production is decreasing due to parts


need to be replaced.

● Even after replacement of parts, yet the results are not


encouraging and satisfying. SAMB still received the
complaint of brackish water produced. Worsen with
barnacles growth has clogged the pipes interior affecting the
flow of pipe.

● This leave the option to lay new submarine pipeline as a long


term measure to resolve the problem.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
5 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
3 Measures Proposed

11 22 3
3 4
construction of construction of laying new submarine
production well compact WTP pipeline
(extraction of ground (packaged plant)
water)

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
6 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Project Objective
The Project is in tandem with SAMB’s continuous efforts in
restructuring, improving and enhancing the water supply
distributions in Melaka State particularly Pulau Besar.

❖ Proposed pipe of OD400 mm HDPE pipe (PE100, PN12.5) will


increase the delivery and distribution of treated water to
Pulau Besar.

❖ The pipes shall conforms to MS 1058 equivalent to ISO 4427


from SPAN approved supplier.

❖ With bigger pipes, amount of at least 1 – 1.3 MGD will be


distributed, cater the rise up in water demand especially
during festive and holiday season and also anticipated future
development in Pulau Besar.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
7 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Project Scope of Work
The extent of the works under this Project shall include but not limited to the followings:

Supply and delivery of pipes, fittings, specials and valves to site. Excavation, laying, testing and

1 commissioning of pipelines; OD400 mm HDPE pipes (approximately 4.5 km). Excavation, supply and
install all pipe fittings, specials and valves;

2 Pipe connection works;

3 Obtaining approval from relevant Authority for carrying out work

4 Maintain all temporary and permanent accesses affected by construction in a satisfactory condition at
all times; and

5 All works incidental to the foregoing including any necessary modifications carried out in accordance
with the terms of the contract.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
8 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Pipeline Route
Pipeline route: from Pernu (mainland) to Pulau Besar (island).

Pernu

4.8km

Pulau Besar

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
9 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Pipeline Route

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
10 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Pipeline Route

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
11 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Method of
Installation

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
12 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Installation of Submarine Pipelines

8 major processes

• Mobilization of Pipe Laying Spread etc.


• Preparation & Pre-installation Works
• Double Joint of HDPE Pipes
• Shallow Water (Initial) Pipe Laying
• Deep Water Pipe Laying
• Additional Protection System (Optional)
• Hydro-testing of Pipeline

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
13 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Three Types of Pipelaying in Trench

Without Concrete Without Concrete Without Concrete


Ballast Ballast Ballast
(On River Bed) (On River Bank)

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
14 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
15 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
16 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
17 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
18 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
19 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying

Concrete Ballast @ 3000 c/c


(maximum spacing)

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
20 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Pulau
Pernu Melaka

Anchor Mat @ 100m Spacing

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
21 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Mobilization of Pipe Laying Barge Spread and Supporting Equipment and etc.
The main spread and machineries shall be mobilized and properly set up at site prior to
HDPE pipe laying works:-
❖ 120ft x 46ft flat top spud barge equipped with 28m long pipe launching ladder, 100 ton
crane, 100 h/p suction cutter, 50ft long arm hydraulic excavator.
❖ 700 h/p anchor handling tow tug.
❖ Material supply (HDPE pipes and concrete ballast) feeder barge complete with crawler
crane on deck.
❖ 25 ton supporting excavator on land.
❖ HDPE pipes butt welding machine.
❖ Hydrographic survey equipment completed with DGPS system on board.
❖ 2 nos. of Speedboats.
❖ Diving team.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
22 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Preparation and Pre-installation Works
Prior to the starting of the pipeline laying works, the following activities shall be carried out:-

❖ Pre-Installation hydrographic survey.


❖ Site clearing and working platform establishment at anchor block area by excavator at
both Pernu and Pulau Melaka.
❖ Delivery of HDPE pipes & reinforced concrete ballast blocks etc.
❖ Availability of fresh water for sinking of HDPE pipes etc.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
23 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Double Joints of HDPE Pipes

❖ In order to facilitate for faster pipe laying process, all the 12m long 400mm HDPE pipe
shall preferably be double jointed and stored at pipe lay barge in stages during pipeline
laying.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
24 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Shallow Water (Initial) Pipe Laying

❖ Pipeline laying shall be commenced first at string, starting from one end at mainland / island
❖ Long arm excavator shall be used to carry out shallow water trenching works (water depth ≤
5m) to form a trench (depend of hydro graphic survey) at approx. 30m to 50m long.
❖ HDPE pipes installed complete with concrete ballast block and others accessories at required
interval shall than be launched from pipe lay barge ladder towards the anchor block.
❖ The weighted pipes shall be slid to the bottom of the trench at the riverbed of an articulated
sled, which shall be designed such that the allowable bending radius of the pipe shall not be
exceeded.
❖ The launched HDPE pipes will be secured at the existing anchor block.
❖ The 25 ton excavator shall carry out backfilling works to the launched pipe near shore
manually. The backfilling of overburden shall form a secure cover to the launched pipes at
the river bank.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
25 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying

Spud Barge

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
26 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying

Anchor Tug Boat

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
27 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Deep Water Pipe Laying

❖ The pipe lay spread equipped with the DGPS control system and water depth detector
will than continue to dredge the trench with its hydraulic suction cutter and with air
lifting facility for self-backfilling.
❖ At the same time; the HDPE pipe will be butt welded, ballast installed on the lay barge
deck and laid down into the trench from the pipe launching ladder.
❖ The gradient of pipe laying ladder shall be control by a tillable hydraulic cylinder to suit
the laying of HDPE pipes.
❖ Divers will be engaged periodically to ensure that the pipeline was laid in the dredged
trench.
❖ Fresh water shall continue to be filled into the laid pipes at mainland to sink down the
laid pipes and increase the pipe stability against sea/river current.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
28 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Shore Approach Works

❖ The long arm excavator on the flat top barge will be used to dredge the balance length
of the pipe trench.
❖ Pipe lay barge shall than be turn long sided with river bank/mainland, the balance length
of the HDPE pipe shall be continued to be jointed on the barge deck.
❖ The HDPE pipes with the assistance of 100 ton crane on barge and excavator at the river
bank/mainland shall then lay the balance length of the HDPE pipes rope to the shore.
❖ The HDPE pipes shall then be tied with concrete ballast block with ropes (act as an
anchor) at approx. 2m intervals at lower down to the river bed (if necessary).

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
29 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Additional Protection System (Anchor Mat)

❖ Divers with the assist of working speed boat and DGPS system shall lower the anchor
mat as required.

Hydro Testing of Pipelines

❖ On completion of pipe lay, the pipe will be hydro tested to 1.5 times its working pressure.
Upon successful completion of hydro test, tie in spools with flanges will be connected
between existing pipe and the newly laid river crossing pipe on both ends of the river
bank.
❖ Pump with minimum capacity of 100 l/s for the flushing pipeline after sinking operation
shall be provided.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
30 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Demarcation of Submarine Pipeline

❖ Appropriate numbers of signboard shall be installed at location approved by the


authority.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
31 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Project Cost Estimation
Estimated Cost
Description
(RM)
ENGINEERING CONSULTANCY
Professional Fees (Pmin = 4.5% x Construction Cost) [A] 675,000.00
Supervision Fees [B] 400,000.00
Reimbursable Fees [C] 25,000.00
PRELIMINARY ENGINEERING WORKS
Bathymetric / Hydrographic Survey Works and Data Collection [D] 100,000.00
WORKS
Preliminaries and General Items
Site Clearing, Excavation and Backfilling
Supply and Delivery of Pipes, Fittings, Valves and Specials
[E] 15,000,000.00
Laying and Installation of Pipes, Fittings, Valves and Specials
Anchor Block, Chambers, No-Anchorage Signboard and Miscellaneous
Piling Works

TOTAL OF WORKS [F] = [A] + [B] + [C] + [D] + [E] 16,200,000.00

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
32 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Authorities Involved
Following are the relevant authorities to liaise with for implementation of the Project:-

.
List of Related Authorities
1. Ibu Pejabat Maritim Negeri Melaka & Negeri Sembilan
Agensi Penguatkuasaan Maritim Malaysia,
Kementerian Dalam Negeri,
Lot 1113 Mukim Kuala Linggi,
78200 Alor Gajah, Melaka.
Tel : 06-3876730, Faks : 06-3876827

2. Tenaga Nasional Berhad 4. Syarikat Air Melaka Berhad


Jalan TTC 9, Lot 897, Wisma Air,
Taman Teknologi Cheng, Jalan Hang Tuah,
75260 Melaka 75300, Melaka

3. Jabatan Laut Malaysia 5. Majlis Bandaraya Melaka Bersejarah (MBMB)


Pejabat Laut Negeri Melaka Graha Makmur, No.1,
Pejabat Laut Melaka, Jalan Tun Abdul Razak - Ayer Keroh,
Jalan Pantai Puteri, Hang Tuah Jaya,
76400 Melaka 75450 Melaka

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
33 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Consulting Engineer Scope of Work
The extent of the consulting engineer services for this Project shall include but not limited to the followings:

1. Feasibility Stage 2. Design Stage


a) To study on existing and future water distribution a) Coordinating and supervising a hydrographic survey
system;
b) To study the pipeline routes, interconnection point b) Preparing design proposal complete with project
to the existing network, and prepare preliminary implementation schedule for pipelaying works from
layout plan of proposal; Pernu to Pulau Besar area which shall include:-
c) To coordinate engineering survey works, interpret
and use the information from survey works for
design of pipeline route. i. Laying of submarine pipeline from Pernu to
Pulau Besar [approximately 4.8 km];
ii. Connection to existing pipeline.
iii. Other related works

b)

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
34 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Consulting Engineer Scope of Work
The extent of the consulting engineer services for this Project shall include but not limited to the followings:

3. Tender Stage 4. Construction Stage


a) Carry out pre-qualification to pre-qualified / selective a) Contract administration, check and review
qualified tenders. submissions by the contractor;
b) To prepare tender document which shall include b) Make recommendation for issuance of certificates;
preparing instruction to tenderer, form of tender, c) Verify claims by the contractor and preparation for
conditions of contract, tender drawing, bill of recommendation of payment certificate;
quantities and material taking off sheet;
d) Liaison with all relevant authorities and to obtain
c) To prepare cost estimate; necessary approval;
d) To analyze and evaluate tender submission and e) Supervision of project to meet requirement;
assist in tender clarification;
f) Commissioning of project
e) The analysis of tender submission shall be through
in order to give a clear picture to the Tender
Committee / Board as for the relative merits of the
tenders for their decision on accepting the tender

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
35 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Consulting Engineer Scope of Work
The extent of the consulting engineer services for this Project shall include but not limited to the followings:

5. Post Contract Stage


a) Carry out defect inspection every quarter of year
until complete defect liability period
b) Recommendation for issuance of Certificate Making
Good Defect and finalization of contract.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
36 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Project Timeline
Proposed project implementation schedule is as follows:

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
37 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Q&A
SESSION
MS CONSULTANT & RESOURCES
Consulting Engineers
SSM No. 201603103223 (002528409-H)

[SELANGOR]:
41B, Jalan Sentosa 2, Taman Sentosa, Sungai Jelok, 43000 Kajang, Selangor Darul Ehsan

[PERAK]:
No. 292, Jalan Gopeng, Taman Cemerlang Rapat, 31350 Ipoh, Perak Darul Ridzuan

Tel: 019 – 313 2102 | E: msconsultantr@gmail.com

You might also like