Professional Documents
Culture Documents
Submarine Pipe from Pernu to Pulau Besar
Submarine Pipe from Pernu to Pulau Besar
PROPOSAL
SUPPLY AND LAY OF NEW OD 400 mm HDPE SUBMARINE
PIPELINE FROM PERNU TO PULAU BESAR, MELAKA
Prepared by MS CONSULTANT & RESOURCES
1 9 th M a r c h 2 0 2 4
1
1.0 Introduction by Consultant
1.1 Background 3
9 – 11
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
3 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Introduction
The treated water source from Duyung Lama Reservoir ● A study was made to study the feasibility to extract
(Cap: 2 MG, TWL: 41.46 m, BWL: 36.46 m) deliver the water groundwater in Pulau Besar. The study comprises
via DN600mm mild steel pipes laid from Duyung, Pekan investigation and hydrogeological survey and construction of
Ayer Molek, Kampung Bukit Lintang, Taman Telok Mas production well and constructing compact packaged plant
and Jalan Pernu before cross from the mainland in Pernu or desalination plant.
to Pulau Besar via DN400 HDPE submarine pipes. The
water will then store into Pulau Besar Reservoir (Cap: 0.22 ● The study had cost SAMB RM 0.453 million. Over the long
MG, TWL: 24.30 m, BWL: 20.30 m). The existing submarine run, treatment and production cost by desalination process
pipes was laid back in 1994. is high at RM 2.40/cu.m in comparison to only RM 1.14/cu.m
by normal conventional treatment process. With logistic and
SAMB had carried out short term measures to preserve access will remain become problems for operation and
the conveyance of treated water to Pulau Besar. maintenance, groundwater extraction and conventional
treatment plant in Pulau Besar was found not a sustainable
It was reported four (4) major leaks occurred in the option.
existing submarine pipeline, on 25 April 2017, 4 August
2017, 13 March 2018, 26 November 2018. With a whooping
cost of nearly RM 2.5 million spent, it becomes unbearable
to address the issue without implementing long term
measure to resolve the leaks problem once and for all.
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
4 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Introduction
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
5 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
3 Measures Proposed
11 22 3
3 4
construction of construction of laying new submarine
production well compact WTP pipeline
(extraction of ground (packaged plant)
water)
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
6 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Project Objective
The Project is in tandem with SAMB’s continuous efforts in
restructuring, improving and enhancing the water supply
distributions in Melaka State particularly Pulau Besar.
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
7 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Project Scope of Work
The extent of the works under this Project shall include but not limited to the followings:
Supply and delivery of pipes, fittings, specials and valves to site. Excavation, laying, testing and
1 commissioning of pipelines; OD400 mm HDPE pipes (approximately 4.5 km). Excavation, supply and
install all pipe fittings, specials and valves;
4 Maintain all temporary and permanent accesses affected by construction in a satisfactory condition at
all times; and
5 All works incidental to the foregoing including any necessary modifications carried out in accordance
with the terms of the contract.
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
8 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Pipeline Route
Pipeline route: from Pernu (mainland) to Pulau Besar (island).
Pernu
4.8km
Pulau Besar
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
9 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Pipeline Route
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
10 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Pipeline Route
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
11 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Method of
Installation
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
12 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Installation of Submarine Pipelines
8 major processes
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
13 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Three Types of Pipelaying in Trench
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
14 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
15 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
16 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
17 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
18 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
19 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
20 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Pulau
Pernu Melaka
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
21 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Mobilization of Pipe Laying Barge Spread and Supporting Equipment and etc.
The main spread and machineries shall be mobilized and properly set up at site prior to
HDPE pipe laying works:-
❖ 120ft x 46ft flat top spud barge equipped with 28m long pipe launching ladder, 100 ton
crane, 100 h/p suction cutter, 50ft long arm hydraulic excavator.
❖ 700 h/p anchor handling tow tug.
❖ Material supply (HDPE pipes and concrete ballast) feeder barge complete with crawler
crane on deck.
❖ 25 ton supporting excavator on land.
❖ HDPE pipes butt welding machine.
❖ Hydrographic survey equipment completed with DGPS system on board.
❖ 2 nos. of Speedboats.
❖ Diving team.
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
22 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Preparation and Pre-installation Works
Prior to the starting of the pipeline laying works, the following activities shall be carried out:-
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
23 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Double Joints of HDPE Pipes
❖ In order to facilitate for faster pipe laying process, all the 12m long 400mm HDPE pipe
shall preferably be double jointed and stored at pipe lay barge in stages during pipeline
laying.
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
24 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Shallow Water (Initial) Pipe Laying
❖ Pipeline laying shall be commenced first at string, starting from one end at mainland / island
❖ Long arm excavator shall be used to carry out shallow water trenching works (water depth ≤
5m) to form a trench (depend of hydro graphic survey) at approx. 30m to 50m long.
❖ HDPE pipes installed complete with concrete ballast block and others accessories at required
interval shall than be launched from pipe lay barge ladder towards the anchor block.
❖ The weighted pipes shall be slid to the bottom of the trench at the riverbed of an articulated
sled, which shall be designed such that the allowable bending radius of the pipe shall not be
exceeded.
❖ The launched HDPE pipes will be secured at the existing anchor block.
❖ The 25 ton excavator shall carry out backfilling works to the launched pipe near shore
manually. The backfilling of overburden shall form a secure cover to the launched pipes at
the river bank.
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
25 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Spud Barge
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
26 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
27 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Deep Water Pipe Laying
❖ The pipe lay spread equipped with the DGPS control system and water depth detector
will than continue to dredge the trench with its hydraulic suction cutter and with air
lifting facility for self-backfilling.
❖ At the same time; the HDPE pipe will be butt welded, ballast installed on the lay barge
deck and laid down into the trench from the pipe launching ladder.
❖ The gradient of pipe laying ladder shall be control by a tillable hydraulic cylinder to suit
the laying of HDPE pipes.
❖ Divers will be engaged periodically to ensure that the pipeline was laid in the dredged
trench.
❖ Fresh water shall continue to be filled into the laid pipes at mainland to sink down the
laid pipes and increase the pipe stability against sea/river current.
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
28 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Shore Approach Works
❖ The long arm excavator on the flat top barge will be used to dredge the balance length
of the pipe trench.
❖ Pipe lay barge shall than be turn long sided with river bank/mainland, the balance length
of the HDPE pipe shall be continued to be jointed on the barge deck.
❖ The HDPE pipes with the assistance of 100 ton crane on barge and excavator at the river
bank/mainland shall then lay the balance length of the HDPE pipes rope to the shore.
❖ The HDPE pipes shall then be tied with concrete ballast block with ropes (act as an
anchor) at approx. 2m intervals at lower down to the river bed (if necessary).
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
29 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Additional Protection System (Anchor Mat)
❖ Divers with the assist of working speed boat and DGPS system shall lower the anchor
mat as required.
❖ On completion of pipe lay, the pipe will be hydro tested to 1.5 times its working pressure.
Upon successful completion of hydro test, tie in spools with flanges will be connected
between existing pipe and the newly laid river crossing pipe on both ends of the river
bank.
❖ Pump with minimum capacity of 100 l/s for the flushing pipeline after sinking operation
shall be provided.
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
30 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pipelaying
Demarcation of Submarine Pipeline
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
31 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Project Cost Estimation
Estimated Cost
Description
(RM)
ENGINEERING CONSULTANCY
Professional Fees (Pmin = 4.5% x Construction Cost) [A] 675,000.00
Supervision Fees [B] 400,000.00
Reimbursable Fees [C] 25,000.00
PRELIMINARY ENGINEERING WORKS
Bathymetric / Hydrographic Survey Works and Data Collection [D] 100,000.00
WORKS
Preliminaries and General Items
Site Clearing, Excavation and Backfilling
Supply and Delivery of Pipes, Fittings, Valves and Specials
[E] 15,000,000.00
Laying and Installation of Pipes, Fittings, Valves and Specials
Anchor Block, Chambers, No-Anchorage Signboard and Miscellaneous
Piling Works
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
32 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Authorities Involved
Following are the relevant authorities to liaise with for implementation of the Project:-
.
List of Related Authorities
1. Ibu Pejabat Maritim Negeri Melaka & Negeri Sembilan
Agensi Penguatkuasaan Maritim Malaysia,
Kementerian Dalam Negeri,
Lot 1113 Mukim Kuala Linggi,
78200 Alor Gajah, Melaka.
Tel : 06-3876730, Faks : 06-3876827
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
33 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Consulting Engineer Scope of Work
The extent of the consulting engineer services for this Project shall include but not limited to the followings:
b)
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
34 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Consulting Engineer Scope of Work
The extent of the consulting engineer services for this Project shall include but not limited to the followings:
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
35 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Consulting Engineer Scope of Work
The extent of the consulting engineer services for this Project shall include but not limited to the followings:
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
36 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Project Timeline
Proposed project implementation schedule is as follows:
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG OD 400 mm HDPE SUBMARINE PIPELINE
/ KOLAM
37 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Q&A
SESSION
MS CONSULTANT & RESOURCES
Consulting Engineers
SSM No. 201603103223 (002528409-H)
[SELANGOR]:
41B, Jalan Sentosa 2, Taman Sentosa, Sungai Jelok, 43000 Kajang, Selangor Darul Ehsan
[PERAK]:
No. 292, Jalan Gopeng, Taman Cemerlang Rapat, 31350 Ipoh, Perak Darul Ridzuan