PROJECT

PROPOSAL
SUPPLY AND LAY OF NEW DN 400 mm M.S. SUBMARINE
PIPELINE FROM PERNU TO PULAU BESAR, MELAKA
Prepared by MS CONSULTANT & RESOURCES
04 April 2024

1
1.0 Introduction by Consultant
1.1 Background 3

1.2 Introduction 4–5

1.3 3 Long Term Measures Proposed 6

2.0 Project Presentation by Consultant


Table of 2.1 Proposed Project Objective 7

contents 2.2 Proposed Project Scope of Work

2.3 Proposed Pipeline Route


8

9 – 11

2.4 Method of Installation 12 – 31

2.5 Authorities Involved 32

2.6 Proposed Consulting Engineer Scope of Works 34 – 36

2.7 Proposed Project Timeline 37

3.0 Q&A Session


Background Introduction
PULAU BESAR, MELAKA is located about 15km
south east of Melaka city and can be reached by ferry or
speed boat. As the name suggests, it is a large island (168
hectares). However, there are approximately only 300
populations with most of them studied in Tahfiz Centre in
Pulau Besar.

Pulau Besar daily consumption is 30,000 GPD. However,


the largest land owner of Pulau Besar, Perbadanan
Kemajuan Negeri Melaka (PKNM) mooted the idea to
develop the area as tourism attraction by constructing
hotels in line with State Government of Melaka to flourish
further their tourism sector which had contributed
largest income to the state’s coffer.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
3 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Introduction ● It was reported four (4) major leaks occurred in the
existing submarine pipeline, on 25 April 2017, 4 August
2017, 13 March 2018, 26 November 2018. With a
whooping cost of nearly RM 2.5 million spent, it
becomes unbearable to address the issue without
implementing long term measure to resolve the leaks
The treated water source from Bukit Lintang
problem once and for all.
Reservoir (Cap: 18 ML, TWL: 53.00 m, BWL: 47.00
m) delivers the water via DN600mm mild steel
● A study was made to study the feasibility to extract
pipes laid from Duyung, Pekan Ayer Molek,
groundwater in Pulau Besar. The study comprises
Kampung Bukit Lintang, Taman Telok Mas and
investigation and hydrogeological survey and
Jalan Pernu before cross from the mainland in
construction of production well and constructing
Pernu to Pulau Besar via DN400 HDPE
compact packaged plant or desalination plant.
submarine pipes. The water will then store into
Pulau Besar Reservoir (Cap: 0.22 MG, TWL: 24.30
● The study had cost SAMB RM 0.453 million. Over the
m, BWL: 20.30 m). The existing submarine pipes
long run, treatment and production cost by
was laid back in 1994.
desalination process is high at RM 2.40/cu.m in
comparison to only RM 1.14/cu.m by normal
SAMB had carried out short term measures to
conventional treatment process. With logistic and
preserve the conveyance of treated water to
access will remain become problems for operation and
Pulau Besar.
maintenance, groundwater extraction and
conventional treatment plant in Pulau Besar was
found not a sustainable option.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
4 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Introduction ● Subsequently in year 2020, a Seawater Reverse
Osmosis (SWRO) plant cost SAMB RM 3.1 million was
completed in Pulau Besar with design production
capacity of 20,000 litre/hr (0.48 MLD @ 0.1 MGD).

● Yet, over the years, the production is decreasing due to


parts need to be replaced.

● Even after replacement of parts, yet the results are not


encouraging and satisfying. SAMB still received the
complaint of brackish water produced. Worsen with
barnacles growth has clogged the pipes interior
affecting the flow of pipe. Over short period of time, the
treatment capacity and quality of treated water
produced significantly reduced to half, resulting to the
water only being used for washing purposes only.

● As a result SAMB has to deliver bottled potable water


to Pulau Besar using barge and tug boat, and cost
them around RM 180,000 or slightly RM 2 million yearly.

● This leave the option to lay new submarine pipeline as


a long term measure to resolve the problem.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
5 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
3 Measures Proposed

11 22 3
3 4
construction of construction of laying new submarine
production well compact WTP pipeline
(extraction of ground (packaged plant)
water)

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
6 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Project Objective
The Project is in tandem with SAMB’s continuous efforts
in restructuring, improving and enhancing the water
supply distributions in Melaka State particularly Pulau
Besar.

 Proposed pipe of DN400 mm M.S. pipe will increase


the delivery and distribution of treated water to
Pulau Besar.

 With bigger pipes, amount of at least 1 – 1.3 MGD will


be distributed, cater the rise up in water demand
especially during festive and holiday season and also
anticipated future development in Pulau Besar.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
7 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Project Scope of Work
The extent of the works under this Project shall include but not limited to the followings:

1
Supply and delivery of pipes, fittings, specials and valves to site. Excavation, laying,
testing and commissioning of pipelines; DN400 mm M.S. pipes (approximately 4.5 km).
Excavation, supply and install all pipe fittings, specials and valves;

2 Pipe connection works;

3 Cathodic Protection,
Commissioning;
Testing, Sterilizing, Flushing works and Testing and

4 Obtaining approval from relevant Authority for carrying out work

5 Maintain all temporary and permanent accesses affected by construction in a


satisfactory condition at all times; and

6 All works incidental to the foregoing including any necessary modifications carried out
in accordance with the terms of the contract.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
8 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Pipeline Route
Pipeline route: from Pernu (mainland) to Pulau Besar (island).

Pernu

4.8km

Pulau Besar

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
9 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Pipeline Route

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
10 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Proposed Pipeline Route

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
11 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Selection for Type
and Sizing of
Material
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
12 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Type and Material of Pipe
Item Criteria Mild Steel Pipe HDPE Pipe
1 Supply Capacity 1.3 MGD (5.91 MLD) based on maximum allowable head loss gradient of 2 m/km
Many established pipe manufacturers and suppliers in
2 Manufacturer/Supplier local market, Allpipes, Pipefab, Pau Tatt, Pipeworks, PipingTech, BinaPlastic, MRPI, Spirolite,
B&C, Hydropipes, etc
Suitable under rigorous ground and
underwater current.
Body of pipes usually hit by ship/boat anchor, its
Heavier than HDPE pipes. Good in counter buoyancy
flexibility caused the pipe to easily bend and
force and underwater flow current
buckled and eventually cracked.
Flange and welding (spigot socket end welded-joint
Although the weight is added with concrete
3 Durability and collar-joint). Joint can be tested with x-ray. Mild
ballast at interval, the pipes still buoyed / float
steel pipes has gone through various vigorous tests in
and swayed under strong underwater flow
factory and at site.
current.
Mild steel pipes and fittings are compatible to all
The joint is by butt fusion and electrofusion.
accessories such as mechanical couplings, flange
adaptor and valves. Mild steel fittings are easily
available and can be fabrication to size/length
Normal operating life span will be 30 years. Shorter life span. Under normal operating, life
4 Service Life
Proven durability. span will be 10 – 15 years.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
13 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Type and Material of Pipe
Item Criteria Mild Steel Pipe HDPE Pipe
Need cathodic protection for acidic ground condition
Non-corrosive.
5 Corrosiveness or near coastal line. But the power consumption is very
minimal and low.
Feedback from Water
Lasting longer years under scheduled maintenance
6 Operator and Many occurrences of pipe leaks and more
and monitoring.
Contractor repairing works compare to steel submarine
Extensive track records for critical submarine pipeline pipe type. The repairing works require skilled
7 Track Record for over many years in Malaysia. The fact is mild steel diver and very costly.
pipes are very well regulated.
DN200: RM 110.00/m x 4800 m = RM 528,000
DN400: RM 220.00/m x 4800 m = RM 1,056,000

For 4800m, the differences in pipe supply is HDPE PE100, SDR11, PN16
9 Price Rate approximately RM 0.5 mil only. At 4%, cost of pipe is DN200: RM 88.00/m x 4800 m = RM 422,400
small and insignificant, given the cost in supplying DN 400: RM 200.00 /m x 4800 m = RM 960,000
pipes constitutes a small fracture of total cost of Works.
Mostly, cost of Works is on preparatory and engineering
works for launching of submarine pipe.
9 Method of laying Pull bottom method Lay and sink from barge method

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
14 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Type and Material of Pipe
NOTE: Given the cost of Works is mostly spend on site
preparation and laying of submarine pipeline, supply
rate variance is considerably small between mild steel
vs HDPE pipes, in addition to its lifespan and track
record, it is the best to opt for steel pipes and DN400
size.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
15 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Engineering
Design

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
16 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Engineering Design

Those are the design


required
• Survey Works
• Wall Thickness Analysis
• Concrete Coating Analysis
• Sub-Bottom Profile Analysis
• Spanning Analysis
• Minimum Curvature Analysis
• Pull Force Calculation
• Pipe Holdback Analysis
• Pull Head Design
• Launchway Structure Design

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
17 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Method of
Installation

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
18 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Installation of Submarine Pipelines

Major Work Processes


• Site Clearance and Site Establishment Works
• Fabrication of Steel Pipe
• Submarine Pipe Delivery, Pipe Storage and Double Jointing
• Launchway Installation and Winch Hold Back Structure
• Submarine Pipeline Launching
• Trench Backfilling with Sand and Granular Material
• Land Pipe Connection
• Pipe Winching from Pulau Besar
• Pigging and Pressure Testing
• Sterilisation and Flushing
• Cathodic Protection at Pernu

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
19 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Delivery, Storage, Double Jointing

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
20 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Delivery, Storage, Double Jointing

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
21 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Launchway Installation

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
22 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Winch Hold Back Structre

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
23 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Trench Dredging

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
24 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Cable Laying

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
25 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Preparatory for Launching

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
26 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Preparatory for Launching

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
27 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Launching of Pipe

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
28 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Pigging

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
29 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Cathodic Protection

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
30 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Authorities
Involved

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
31 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Authorities Involved
Following are the relevant authorities to liaise with for implementation of the Project:-

.
List of Related Authorities
1. Ibu Pejabat Maritim Negeri Melaka & Negeri Sembilan
Agensi Penguatkuasaan Maritim Malaysia,
Kementerian Dalam Negeri,
Lot 1113 Mukim Kuala Linggi,
78200 Alor Gajah, Melaka.
Tel : 06-3876730, Faks : 06-3876827

2. Tenaga Nasional Berhad 4. Syarikat Air Melaka Berhad


Jalan TTC 9, Lot 897, Wisma Air,
Taman Teknologi Cheng, Jalan Hang Tuah,
75260 Melaka 75300, Melaka

3. Jabatan Laut Malaysia 5. Majlis Bandaraya Melaka Bersejarah (MBMB)


Pejabat Laut Negeri Melaka Graha Makmur, No.1,
Pejabat Laut Melaka, Jalan Tun Abdul Razak - Ayer Keroh,
Jalan Pantai Puteri, Hang Tuah Jaya,
76400 Melaka 75450 Melaka

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
32 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Estimated Project
Cost

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
33 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Description Estimated Cost (RM)
PRELIMINARY
Preliminary & Planning
Bathymetric / Hydrographic Survey Works and Site Investigation & Data Collection
[A] 3,500,000.00
Engineering Design and Report & Engineering Approval
Document Submission & Authorities Approval
SUBMARINE PIPELINE WORKS
Procurement & Pipe Production
Pipe Supply & Delivery Including External Concrete Cladding
Pull Head Fabrication, Delivery & Installation
Launchway Foundation& Installation and all Other Supports [B] 23,500,000.00
Pipe Double Jointing and Storage
Winch Spooler, Wire Rope Laying
Dredging, Trenching Works and Pipeline Launching
POST LAUNCHING WORKS
Post Hydrographic Survey & As-Built Drawing
Pipeline Pigging & Pressure Testing
Marine Backfilling Works
[C] 5,000,000.00
Sterilising and Flushing Works
Final Connection Including Cofferdam
Cathodic Protection
TOTAL OF WORKS [D] = [A] + [B] + [C] 32,000,000.00
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
34 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Consulting Engineer Scope of Work
The extent of the consulting engineer services for this Project shall include but not limited to the followings:

1. Feasibility Stage 2. Design Stage


a) To study on existing and future water distribution a) Coordinating and supervising a hydrographic survey
system;
b) To study the pipeline routes, interconnection point b) Preparing design proposal complete with project
to the existing network, and prepare preliminary implementation schedule for pipelaying works from
layout plan of proposal; Pernu to Pulau Besar area which shall include:-
c) To coordinate engineering survey works, interpret
and use the information from survey works for
design of pipeline route. i. Laying of submarine pipeline from Pernu to
Pulau Besar [approximately 4.8 km];
ii. Connection to existing pipeline.
iii. Other related works

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
35 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Consulting Engineer Scope of Work
The extent of the consulting engineer services for this Project shall include but not limited to the followings:

3. Tender Stage 4. Construction Stage


a) Carry out pre-qualification to pre-qualified / selective a) Contract administration, check and review
qualified tenders. submissions by the contractor;
b) To prepare tender document which shall include b) Make recommendation for issuance of certificates;
preparing instruction to tenderer, form of tender, c) Verify claims by the contractor and preparation for
conditions of contract, tender drawing, bill of recommendation of payment certificate;
quantities and material taking off sheet;
d) Liaison with all relevant authorities and to obtain
c) To prepare cost estimate; necessary approval;
d) To analyze and evaluate tender submission and e) Supervision of project to meet requirement;
assist in tender clarification;
f) Commissioning of project
e) The analysis of tender submission shall be through
in order to give a clear picture to the Tender
Committee / Board as for the relative merits of the
tenders for their decision on accepting the tender

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
36 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Consulting Engineer Scope of Work
The extent of the consulting engineer services for this Project shall include but not limited to the followings:

5. Post Contract Stage


a) Carry out defect inspection every quarter of year
until complete defect liability period
b) Recommendation for issuance of Certificate Making
Good Defect and finalization of contract.

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
37 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
 4 months : Award, Hydro-survey, Design, Approval
 2 months : Procurement and Fabrication of Pipes
 3 months : Site Preparatory
 7 months : Preparatory for launching
 2 months : Launching of Submarine Pipe

Proposed Project  5 months : Post Launching Works


 1 month : Handing Over

Timeline  TOTAL = 24 months

SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
38 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
SUPPLY
PROJEKAND LAY
BINA OF NEW LOJI
– PASANG DN400 mm M.S. SUBMARINE PIPELINE
/ KOLAM
39 FROM PERNU TO PULAU BESAR, MELAKA
DAN PAIP UTAMA DI DAERAH MANJUNG
Q&A
SESSION
MS CONSULTANT & RESOURCES
Consulting Engineers
SSM No. 201603103223 (002528409-H)

[SELANGOR]:
41B, Jalan Sentosa 2, Taman Sentosa, Sungai Jelok, 43000 Kajang, Selangor Darul Ehsan

[PERAK]:
No. 292, Jalan Gopeng, Taman Cemerlang Rapat, 31350 Ipoh, Perak Darul Ridzuan

Tel: 019 – 313 2102 | E: msconsultantr@gmail.com