Professional Documents
Culture Documents
IR Valve, Tube & Fittings KKC HPCL 06.05.2024
IR Valve, Tube & Fittings KKC HPCL 06.05.2024
DNV/HPCL/KKC/
5300009417/2024/SK/
IR/01
SOURCE - INSPECTION REPORT Revision No:
01
Particulars of project
DNV project name: CNG STATION CONSTRUCTION WORKS SS TUBING & MECH-
UP CLUS For HPCL.
DNV customer name: M/s. KULDEEP KUMAR CONTRACTOR.
Supplier: M/s. KULDEEP KUMAR CONTRACTOR.
Manufacturer: PARKER, DK-LOK & TUBACEX
DNV acts on behalf of: M/s. KULDEEP KUMAR CONTRACTOR.
Inspection details
Customer's PO number to Supplier: Contract No.: 5300009417Date: 18.07.2023
Supplier's reference: ITP. No. for SS Ball Valve: TEW/22-23/103 Date: 21.02.2023
ITP. No. for SS Tube: TEW/TUBACEX/SS TUBES 026/22-
23Date:25.01.2023
ITP.No. for SS Fittings: KKC/HPCL/SS Fittings & Valves/22-
23/01 Rev.01 Date: 17.01.2023
Additional references: NIL
Inspection location: G.T. Road, Ansal Town, Karnal. 132001
Details of visit
Reference documentation1
Number/Reference Rev/Date Title/Approval status
5300009417 --/ 18.07.2023 Contract /HPCL
TEW/22-23/103 00/ 21.02.2023 ITP for SS Ball Valve / Tractebel
TEW/TUBACEX/SS TUBES 026/22-23 00/ 25.01.2023 ITP for SS Tube / Tractebel
KKC/HPCL/SS Fittings & Valves/22-23/01 01/17.01.2023 ITP for SS fittings/ Tractebel
1. As per Qap. Sr. No. 1: Review the Raw Material Test certificate (Mechanical & Chemical Analysis) and
PMI test report of offered material & found satisfactory.
2. As per Qap. Sr. No. 2: Review the test report of Typical Hydrostatic test report for valve and seat closure
test and Gas pressure test report for valve body and seat of the offered material and found accepted.
3. As per Qap. Sr. No. 3: Witness the dimension and visually check the offered material & found
satisfactory.
4. As per Qap. Sr. No. 4: Visually check the identification and verified with the catalogs and found satisfactory.
5. As per Qap. Sr. No. 5: Witness the preparation of shipment and packing inspection of the offered
material and found accepted.
6. As per Qap. Sr. No. 6: Review of all inspection documents as per requirement & issue inspection
certificate.
1
Quality plans, drawing numbers, test procedures. Include revision.
1. As per QAP Clause no.1. Reviewed the Raw material test certificate of offered material and found
satisfactory.
2. As per QAP Clause no.2 & 3. Reviewed the chemical composition and corrosion test as per given
in inspection certificate and found satisfactory.
3. As per QAP Clause no 4A, 4B & 4C. Reviewed the tensile test, hardness test & flaring test as per
given in inspection certificate and found satisfactory.
4. As per QAP Clause no.5. Reviewed the eddy current test as per given in inspection certificate and
found satisfactory.
5. As per QAP Clause no.6. Reviewed the hydrostatic pressure tested at 350kg/cm2 for 5 sec as per
given in inspection report and found satisfactory.
6. As per QAP Clause no.7. Witnessed the PMI test of offered material and result found satisfactory.
7. As per QAP Clause no.8. Witnessed the marking of grade, standard, heat no etc over offered
material and found satisfactory.
8. As per QAP Clause no.9. Witnessed the visual & dimension of the offered material as per MTC
and found satisfactory.
9. As per QAP Clause no.10. Reviewed the packing list and certificate of the offered material and
found satisfactory.
1. As per QAP Clause no.1. Reviewed the material test certificate of offered material and found
satisfactory.
2. As per QAP Clause no.2. Visually check & verified the marking with test certificate of the offered
material and found satisfactory.
3. As per QAP Clause no 3. Reviewed the positive material identification inspection certificate and
found satisfactory.
4. As per QAP Clause no.4. Visually check and witnessed the dimension of the offered material and
found satisfactory.
5. As per QAP Clause no.5. Reviewed the hydraulic burst pressure test, impulse & vibration and found
satisfactory.
6. As per QAP Clause no.6 & 7. Reviewed test Helium test & Re-assembly test report of offered
material and result found satisfactory.
7. As per QAP Clause no.8. Visually check and witnessed the dimension of the offered material and
found satisfactory..
8. As per QAP Clause no.9. Reviewed the packing list and certificate of the offered material and found
satisfactory.
Action items3
Action no. Description Responsible party
NIL
Punch list
Punch list issued: ☐ Yes ☐ No ☒ N/A
Punch list number/title: N/A
Punch list attached to this report: ☐
Comments: N/A
List of attachments
Attachment(s) and ID No(s) Description
RMTC, Internal Report, Packing List & Calibration Certificate
The goods/items specified have been inspected in accordance with the scope of inspection provided. The result is as
stated on the inspection report front page.
(Sumit Kumar)
Inspector
Stamp:-
2
Any NCR shall be issued on the same day after inspection and shall be attached to the report.
3
Actions/information needed to complete or clarify the process of Inspection, by Customer, DNV, or the Equipment/Service provider.