January 25, 2021

Project Name: REHABILITATION OF LOCAL ROAD, KAGITINGAN ST., (PHASE II)


Location: BRGY MUZON, MALABON CITY

METHODOLOGY OF WORKS

1. Secure all necessary permits for the rehabilitation of roads and drainage.
2. Coordinate with barangay for the start up of project and other concern
3. Preparation for temporary barracks.
4. Mobilization of Equipment and Materials Needed in the Project
5. Coordinate with barangay if needed to close the road.
6. Established all perimeters, stationing and elevation of the project
7. Start to setup driving of sheet pile for the drainage were located near at the fish
pan
8. Start clearing existing drainage and replace new dimension of drainage bout side
9. First setup is concreting of footing, siding and covered.
10. Fabricate cover of the drainage separately according in the plan dimension.
11. After all the drainage bout side is completed start to prepare for the road pavement
12. Start breaking existing pavement if needed, and put embankment to reach exact
elevation for the new pavement.
13. Prepared for base coarse
14. Start concreting one side of pavement until to complete bout side.
15. Concrete cutting
16. Applying Asphalt sealant for the pavement
17. Waiting for curing time of the concrete pavement before allow it to used.
18. Site clearing and preparation for demobilization of equipment and materials.

Prepared by:

Rolando A. Maiquez

RAM Builders Inc.