Site Report : 5 Date : 01.07.

24
Project : Pecatu Sahadewa Cluster Client : Orbita
Time : 17:55

Work/Progress :

1st Floor & 2nd Floor General Note


- ceiling work is still not been finished
- electrical wiring is still not been finished/cleared yet
- front roster wall façade is done plastered but not painted

Site project pictures:

- ceiling work is still not been finished

- electrical wiring is still not been finished/cleared yet

- front roster wall façade is done plastered but not painted


Rooftop Floor Note

- Planter box and structure post work is in progress

- Roster wall and Kitchen wall work is in progress, concrete canopy roof is being cast

- Custom stepping concrete is in process on site (Contractor to have protection)