E01-P-MOP-EE-001_ MOP Remove Batteries of UPS 2 x 600kva_CGK-2 BSD_Rev.01_signed (12 July 2024)
E01-P-MOP-EE-001_ MOP Remove Batteries of UPS 2 x 600kva_CGK-2 BSD_Rev.01_signed (12 July 2024)
Prepare By:
PT. Eaton Industries
Mariston Frans P
Acknowledge by
BDx FMT/OPS CGK 2
Approved by
BDx Project
Reynaldi Aditya 12 July 2024
Approved by
HSE BDx
Project
Existing Power room has 2 units of UPS 600KVA working in parallel system’s, remove the batteries
existing to temporary Batteries room is required.
To provide temporary room in the area loading room with make a gypsum partition room
To provide temporary cooling with install 2 units standing Air cool include installation piping
until outdoor unit
To provide temporary tray cable ladders between UPS room to Battery temporary room
To explain the procedure for removing the 2x600KVA UPS battery while online then moving the
battery to the temporary battery room in the Loading dock area.
To clarify the risk of work and classify the mitigation plan required.
To ensure that during replacement’s work is run smoothly and eliminated the risk (no downtime
occur)
1. Multimeter
2. Clamp meter
3. Rotary Phase Tester
4. Insulation Resistant Tester
5. Torque Wrench
6. Vaccum Cleaner
7. Cable Cutting
8. Hand Press Hyodrolic Scun
9. Hand Drill
10. Weld Trafo
11. Hand Cutting wheel
1. Insulation gloves
2. Safety Shoes
3. Helmet
4. Dust Cloth
5. Goggle weld
6. Hand gloves
7. long sleeved shirt
8. Safety Glasses
9. First Aid Equipment
10. Baricade Line
1. Existing Configuration
Layout UPS Room, Battery Room (EXISTING)
Batt. Lith-Ion
UPS L1.A4
Batt. Lith-Ion
UPS L1.A5
UPS
1
UPS
2
Panel BCB
Batt UPS L1.A5
Panel BCB
Batt UPS L1.A4
Equipment’s data :
Battery Dimension : 600 x 1000 x 2000 (mm) : 8 Rack
BCB Panel Dimension : 600 x 800 x 500 (mm) : 2 Unit
Scope of Works :
1. Rack Batteries UPS L1.A4 and Panel BCB Battery UPS L1.A4 dismantle and move to
temporary battery room
2. Rack Batteries UPS L1.A5 and Panel BCB Battery UPS L1.A5 dismantle and move to
temporary battery room
3. Make the room place a temporary battery by installing partitions and door
Cable DC Power
UPS to Batter
NYAF 4Cx240mm
10 Installation new cable DC power from UPS to BCB Panel and BCB Panel to Battery Bank
Temporary Room
11 Genset Running during the gradual replacement of ups units exiting
12 Mobilization of battery and rack Battery exisiting to storage BDX
13 Positioning Rack Battery with placement Modules Battery in the Rack
14 Termination, startup Battery and Power On
Impact on
Engineering System
Section 7 – Engineering Assessment of Risk Control
Standard
Moderate
Major
Minor
2
1 2 3
High 3 3 6 9
Likelihood of Incident
Medium 2 2 4 6
Potential incidents with a risk score greater than 2 must have mitigation measure and / or controls
identified that reduce the revised risk score to no more than 2 so far is as this is practicable.
Once the final Risk Rating has been established the rules set out below MUST be applied.
1.
Potential Incidents related to work effort:
Electric shocks, short circuits, stops phase lines, falls and squish
Impact Score: 3 Likelihood Score: 3 Risk Score: 9
Mitigation Measure:
use personal protection, including the following :
1. busbars are covered with insulation
2. wearing electric gloves
3. used wear long sleeves
4. Take measurements before starting work
Cable DC Power
UPS to Batter
NYAF 4Cx240mm
Date:
Laying new cables and pull the Arrange a pile of cables on the
3 4 hours N/A N/A Eaton
cables are form UPS to BCB than to tray or ladder line that has been
Handling
Moving all Rack Battery and panel fell and
moving
6 BCB UPS L1.A5 to Temporary 2 hours battery circuit is ready to use was Eaton
moduls
Room Battery crushed
battery
ensure the connection is good and Check connection and tighten DC High Short
9 1 hour Eaton
correct the bolt with torque tools Voltage Circuit
11 Finish
Cable DC Power
UPS to Batter
NYAF 4Cx240mm
Date:
Laying new cables and pull the Arrange a pile of cables on the
3 cables are form UPS to BCB than to 4 hours tray or ladder line that has been N/A N/A Eaton
the rack battery bank provided
5 UPS L1.A4 set to mode bypass 3 hours Place and arrange the new DC High Short Eaton
static, than panel go to External
E01‐P‐MOP‐EE‐001_ MOP Remove Batt of UPS 600KVA – CGK-2
Page 12 of 18
Unless indicated, printed copies are regarded as un-controlled documents.
Version 0
Restricted
Bypass with Breaker Bypass Close. battery in the rack that is Voltage Circuit
Breaker panel BCB should be already available
switch Open
Take Out interconnection in the
rack battery and panel BCB
Handling
Moving all Rack Battery and panel fell and
moving
6 BCB UPS L1.A4 to Temporary 2 hours battery circuit is ready to use was Eaton
moduls
Room Battery crushed
battery
ensure the connection is good and Check connection and tighten DC High Short
9 1 hour Eaton
correct the bolt with torque tools Voltage Circuit
11 Finish
Date:
Preparation :
will damage scratched
‐ make protection on the floor using
makes it easy to mobilize the the floor on damaged
1 a plywood plinth 1 Hours Eaton
device to be taken out the way broken
‐ In the raised floor area, use a base
through vanished
in the form of an iron plate
Outdoor Unit AC
Piping AC
Standing
Indoor Unit AC
Date:
Preparation :
‐ Preparation of a standing indoor AC
will damage
stand 25cm high
Marking and pipe lines are floors and floors
‐ Prepare an outdoor AC Support
1 1 Hours available for installation from walls during and walls Eaton
wall mount
indoor to outdoor installation damage
‐ Prepare a 3 Phase 32 Amp Power
work
cable,
‐ Siapkan pemutus fasa 32 Amp 3
‐ install the outdoor AC mount and AC indoor and Outdoor can be be cannot
3 5 Hours Eaton
install the outdoor unit taken easily squeezed be issued
Section 11‐ Test Scrip Check List, Sequence and Time line
Section 11 – Escalation
Primary Support:
Secondary Support:
EATON Contact