Date : June 13, 2024

Project : LRI CHROMA ASIA


Location : Cavite, Cavite City
Contractor : RUEL PULHIN
Subject : LABOR - FIRE PROTECTION WORKS
LABOR COST PROPOSAL FOR FIRE PROTECTION WORKS

Item no. Description Qty Unit Unit Cost Total Cost


I. FIRE PROTECTION WORKS

A General Requirements
A.1 House Rental & Supervision 1 lot 100,000.00 100,000.00
B Piping Works
B.1 Feedmain, Crossmain, Loop Pipe Supply, Underground 1 lot 295,800.00 295,800.00
Pipe Work, Test Header and Fire Department
Connection Inlet
B.2 Branchline/Droppings 1 lot 550,080.00 550,080.00
B.3 Main Riser, Wet 1 lot 10,000.00 10,000.00
B.4 Pre-Action 1 lot 12,000.00 12,000.00
B.5 Valves & Accessories 1 lot 15,000.00 15,000.00
B.6 Fire Hose Cabinet 1 lot 20,000.00 20,000.00
B.7 Sprinkler Heads 1 lot 19,700.00 19,700.00
B.8 Foam System & Supply 1 lot 60,000.00 60,000.00

C Hanger and Support 1 lot 45,000.00 45,000.00


D Painting Works 1 lot 70,000.00 70,000.00
E Hauling of Materials 1 lot 45,000.00 45,000.00
F Excavation Works 1 lot 35,000.00 35,000.00
G Testing and Commissioning 1 lot 35,000.00 35,000.00

TOTAL AMOUNT 1,312,580.00

Prepared by: Approved by:

RUEL PULHIN BEN BAGSIT


Sub-contractor General Manager
Labor-Fire Protection Works Interpipe Plumbing Services

LRI Chroma Asia Project Page 1 of 1