Professional Documents
Culture Documents
Shore Pile Arrangement Drawing
Shore Pile Arrangement Drawing
Shore Pile Arrangement Drawing
2500
consumption shall be maintained for each pile.
C-C LINER UP TO 5.5. Deflection shall be checked after suitable interval of time, by using Inclinometer or
WEATHERED other suitable instruments.
ROCK 5.6. The pile concreting shall be done on same day of pile drilling by tremmie concreting
method. The gap between tremmie pipe (or concrete) and pile bottom shall not exceed
150- 200mm.
8T HELICAL REINFORCEMENT 5.7. Clear Cover of 30 mm shall be provided to piles. At least four concrete cover blocks shall
@200 mm C-C WITH 10T MASTER be placed at each elevation at not more than 1.50m C-C spacing.
PRESTRESSED ROCK RING @1 m C-C 5.8. Clear Cover of 40 mm shall be provided to capping beam.
5.9. Lap Length - 50D shall be provided.
6000
6.1. Slump of concrete should be between 160 mm to 180mm. Concrete cubes shall be
SPACING AND WAILER prepared for each concrete batch (or RMC) for strength confirmation.
BEAM 2 ISMC 400 PILE@ 400mm C-C SPACING 6.2. Pile integrity test should be conducted on all piles.
6.3. The third party testing shall be carried out on 2% anchors.
X X
EXCAVATION
LEVEL-6.00m 400
16 T 8 NOS
NO. REVISION DATE DESCRIPTION
8T HELICAL R0 08.05.2024 Drawing Issued.
REINFORCEMENT PILE REINFORCEMENT
400
@200 mm C-C
4 L 8 T LATERAL
1200
250
The anchor lengths (fixed and free both) shall be grouted using Non-Shrinkable GP2 or
120mm∅ HOLE
4. ANCHOR BEARING PLATE equivalent grout mix.
(32mm THICK AND 150mm∅) 25mm THICK BOTTOM 5.1. Ref. Code : IS10270:1982, IS14268:1995.
INCLINED PLATE 5.2. The free and fixed length of anchor is 6.00 m to 7.00m for 2.50m level; however the
4. ANCHOR STRESS BOX
PLAN VIEW free anchor length shall be considered up to weathered rock encountering depth.
400
250
300
5.3. The anchors shall be pre-stressed after 7 days of grouting.
25mm THICK SIDE
PLATE (TRIANGULAR) 5.4. The adjacent building basement, foundations or any other structure shall be verified
4. ANCHOR STRESS BOX before commencement of shoring work.
5. ANCHOR STRESS BOX
ISOMETRIC VIEW 5.5. Anchor Stressing should be done using multipull jack.
(REFER DETAIL DRAWING)
6. Testing
300 mm∅ PILE 25
6. FRONT PLATE 250
6.1. Slump of concrete should be between 160 mm to 180mm. Concrete cubes shall be
(20mm THICK STEEL PLATE) 25mm THICK 25mm THICK SIDE prepared for each concrete batch (or RMC) for strength confirmation.
28
SIDE PLATE PLATE (TRIANGULAR)
7
Note : - 25mm THICK UPPER 6.2. Pile integrity test should be conducted on all piles.
7. SIDE STIFFENER PLATE
335
The steel plate and INCLINED PLATE 6.3. The third party testing shall be carried out on 2% anchors.
bolts may not be (16mm THICK STEEL PLATE) 25mm THICK UPPER
required where liner INCLINED PLATE 25mm THICK BOTTOM
INCLINED PLATE
2
is available
25
26
25mm THICK BOTTOM
PLAN VIEW OF ANCHOR BLOCK INCLINED PLATE
4. ANCHOR STRESS BOX
3. ISMC 400 4. ANCHOR STRESS BOX FRONT VIEW
SIDE VIEW
300 mm∅
PILE 4. ANCHOR BEARING PLATE
(32mm THICK AND 150mm∅) 1. BOLTS 5.00 T
28 50
PROVIDE 6 NOS
16
16
236
2. CURVED 5. ANCHOR STRESS BOX 348
BASE PLATE (REFER DETAIL DRAWING) 261
2 8. BOTTOM BRACKET
26
2. CURVED BASE PLATE
(16mm THICK PLATE PLAN VIEW
880
700
PLAN VIEW
STEEL PLATE) 16 261 16
1320
348
7. SIDE STIFFENER PLATE
45° (16mm THICK STEEL PLATE)
Note : -
The steel plate and 6. FRONT PLATE
367
bolts may not be (20mm THICK STEEL PLATE)
367
required where liner
9
51
is available
1320
1320
PROVIDE 6 NOS PLATE FRONT VIEW PLATE SIDE VIEW
880
700
700
WELLER BEAM
SECTION 2 SECTIONS OF 12.7 mm ∅