Project Network
Project Network
Given the following network, with activity times in months, determine the earliest and latest
activity times and slack for each activity. Indicate the critical path and the project duration.
b. The following table provides the crash data for the network project described in Problem 1a
Crash the network to 32 months. Indicate the critical path activities and the cost of the
network.