Doc.

No FORM-04-QA-G002
Quality Form Revision 00
Date 23/02/2023
Daily Report Page -

PROJECT NAME : Retaining Wall dan Rantai Loading Ramp EMPLOYER : PT. SAWITAKARYA MANUNGGUL
PROJECT ID : 22SRF1780 CONTRACTOR : PT. PUTRA MAS AGRO SEJAHTERA
LOCATION : PT. SAWITAKATYA MANUNGGUL - SWTM DAY/DATE : 20 Juni 2023
A. Working B. Arrival / Mutation: Equipment and basic materials

No Type Of Work Location No Material Total Total Rejected Total Accepted

1 On - Site and Preparation SWTM PROJECT - - - -

C. Tools Usage

No Tool Type TOTAL Damage Hours


D. Project Personel / Contractor

No Task / Position Quantity 1 - - - -

1 Site Manager - Orang 2

2 Supervisor - Orang 3

3 OHSE 1 Orang 4

4 Head Worker - Orang 5

5 Man Power 6 Orang 6

E. Weather / Natural Disasters

No TYPE CLOCK REMARKS

1 Berawan - 07:00 - 17.00 WITA

08.30am Durasi 3 Jam

Total 7 Orang
Proposed Submissions / Suggestions / Instructions Of Deal / Reporting:

Work Start At : 13.20 WITA Until Hour : 17.00 WITA


Work Stalled Because :

Prepared By, Acknowledge By,


PT. PUTRA MAS AGRO SEJAHTERA PT. SAWITAKARYA MANUNGGUL

ARSUDIN SIRAIT RIO DERMAWAN


Safety Officer Resident Engineer

PMAS
Doc. No FORM-04-QA-G002
Quality Form Revision 00
Date 23/02/2023
Daily Report Page -

PROJECT NAME : Retaining Wall dan Rantai Loading Ramp EMPLOYER : PT. SAWITAKARYA MANUNGGUL
PROJECT ID : 22SRF1780 CONTRACTOR : PT. PUTRA MAS AGRO SEJAHTERA
LOCATION : PT. SAWITAKATYA MANUNGGUL - SWTM DAY/DATE : 21 Juni 2023
A. Working B. Arrival / Mutation: Equipment and basic materials

No Type Of Work Location No Material Total Total Rejected Total Accepted

1 Pelaksanaan Briefing / Safety Talk SWTM PROJECT Multiplek (2,4m x 1,2m); Keping 40 0 40

2 Persiapan Area Kerja (Penempatan Material & Alat) SWTM PROJECT Besi D13 @12 m; Batang 442 0 442

3 Survey ulang rencana volume pekerjaan SWTM PROJECT

C. Tools Usage

No Tool Type TOTAL Damage Hours


D. Project Personel / Contractor

No Task / Position Quantity 1 Gerobak Sorong 4 0 2

1 Site Manager - Orang 2 Cutting Whell 14" 1 0 8

2 Supervisor - Orang 3 Pembengkok Besi 2 0 8

3 OHSE 1 Orang 4

4 Head Worker - Orang 5

Man Power 6 Orang 6

E. Weather / Natural Disasters

No TYPE CLOCK REMARKS

1 Sunny - 07:00 - 17.00 WITA

Total 7 Orang
Proposed Submissions / Suggestions / Instructions Of Deal / Reporting:
Deviasi progress per hari ini (- 0,691%) kejar target sesuai schedule, segera mendatangkan material sebagaimana target pekerjaan di schedule

Work Start At : 07.00 WIB Until Hour : 17.00 WIB


Work Stalled Because : -

Prepared By, Acknowledge By,


PT. PUTRA MAS AGRO SEJAHTERA PT. SAWITAKARYA MANUNGGUL

ARSUDIN SIRAIT RIO DERMAWAN


Safety Officer Resident Engineer

PMAS
DOKUMENTASI HARIAN PMAS
Proyek / PT :
Lokasi : PT. SAWITAKARYA MANUNGGUL
No. Kontrak : 22SRF1780
Kontraktor : PT. PUTRA MAS AGRO SEJAHTERA
Hari/Tanggal : 21 Juni 2023

Survey Lokasi (Lanjutan) Pra - Pelaksanaan Konstruksi Existing salah satu sisi Heeling Concrete Cover

Existing salah satu sisi Heeling Concrete Cover Existing salah satu sisi Apron di Loading Ramp
Doc. No FORM-04-QA-G002
Quality Form Revision 00
Date 23/02/2023
Daily Report Page -

PROJECT NAME : Retaining Wall dan Rantai Loading Ramp EMPLOYER : PT. SAWITAKARYA MANUNGGUL
PROJECT ID : 22SRF1780 CONTRACTOR : PT. PUTRA MAS AGRO SEJAHTERA
LOCATION : PT. SAWITAKATYA MANUNGGUL - SWTM DAY/DATE : 22 Juni 2023
A. Working B. Arrival / Mutation: Equipment and basic materials

No Type Of Work Location No Material Total Total Rejected Total Accepted

1 Pelaksanaan Briefing / Safety Talk SWTM PROJECT 1 Multiplek (2,4m x 1,2m); Keping 40 0 40

2 Penerimaan Material Onsite SWTM PROJECT 2 Besi D13 @12 m; Batang 442 0 442

3 Pabrikasi (Pembersian D13 @12m) SWTM PROJECT

C. Tools Usage

No Tool Type TOTAL Damage Hours


D. Project Personel / Contractor

No Task / Position Quantity 1 Gerobak Sorong 4 0 2

1 Site Manager - Orang 2 Cutting Whell 14" 1 0 8

2 Supervisor - Orang 3 Pembengkok Besi 2 0 8

3 OHSE 1 Orang 4

4 Head Worker - Orang 5

5 Man Power 6 Orang 6

E. Weather / Natural Disasters

No TYPE CLOCK REMARKS

1 Sunny - 07:30 - 18.00 WITA

Total 7 Orang
Proposed Submissions / Suggestions / Instructions Of Deal / Reporting:
-

Work Start At : 07.30 WIB Until Hour : 18.00 WIB


Work Stalled Because : -

Prepared By, Acknowledge By,


PT. PUTRA MAS AGRO SEJAHTERA PT. SAWITAKARYA MANUNGGUL

ARSUDIN SIRAIT RIO DERMAWAN


Safety Officer Resident Engineer

PMAS
DOKUMENTASI HARIAN PMAS
Proyek / PT :
Lokasi : PT. SAWITAKARYA MANUNGGUL
No. Kontrak : 22SRF1780
Kontraktor : PT. PUTRA MAS AGRO SEJAHTERA
Hari/Tanggal : 22 Juni 2023

Penerimaan Material On-Site Penerimaan Material On-Site

Pemindahan Tiang Listrik di Area Apron oleh Pekerja Owner Pekerjaan Pabrikasi Pembesian D13 @ 12m
Doc. No FORM-04-QA-G002
Quality Form Revision 00
Date 23/02/2023
Daily Report Page -

PROJECT NAME : Retaining Wall dan Rantai Loading Ramp EMPLOYER : PT. SAWITAKARYA MANUNGGUL
PROJECT ID : 22SRF1780 CONTRACTOR : PT. PUTRA MAS AGRO SEJAHTERA
LOCATION : PT. SAWITAKATYA MANUNGGUL - SWTM DAY/DATE : 23 Juni 2023
A. Working B. Arrival / Mutation: Equipment and basic materials

No Type Of Work Location No Material Total Total Rejected Total Accepted

1 Pelaksanaan Briefing / Safety Talk SWTM PROJECT 1 Multiplek (2,4m x 1,2m); Keping 60 0 60

2 Penerimaan Material dan Alat Onsite SWTM PROJECT 2 Papan Kls III 2/20 @4m, Keping 62 0 62

3 Pabrikasi (Pembersian D13 @12m) SWTM PROJECT 3 Balok 5/7 @4m; Batang 72 0 72

4 Pabrikasi Bekisting Beton Plat Dasar Retaining Wall SWTM PROJECT 4 Balok 5/5 @4m; Batang 100 0 100

5 Cerucuk 6-8@4m; Batang 300 0 300

6 Besi D13 @ 12m; Batang 113 0 113

7 Besi d8 @ 12m; Batang 190 0 190

8 Besi d10 @ 12m; Batang 30 0 30

9 Plastik Cor 1m x 25m; Gulung 4 0 4

C. Tools Usage

No Tool Type TOTAL Damage Hours


D. Project Personel / Contractor

No Task / Position Quantity 1 Gerobak Sorong 2 0 2

1 Site Manager - Orang 2 Cutting Whell 14" 1 0 8

2 Supervisor - Orang 3 Pembengkok Besi 2 0 8

3 OHSE 1 Orang 4

4 Head Worker - Orang 5

5 Man Power 6 Orang 6

E. Weather / Natural Disasters

No TYPE CLOCK REMARKS

1 Sunny - 07:00 - 17.00 WITA

Total 7 Orang
Proposed Submissions / Suggestions / Instructions Of Deal / Reporting:
-

Work Start At : 07.00 WIB Until Hour : 17.00 WIB


Work Stalled Because : -

Prepared By, Acknowledge By,


PT. PUTRA MAS AGRO SEJAHTERA PT. SAWITAKARYA MANUNGGUL

ARSUDIN SIRAIT RIO DERMAWAN


Safety Officer Resident Engineer

PMAS
DOKUMENTASI HARIAN PMAS
Proyek / PT :
Lokasi : PT. SAWITAKARYA MANUNGGUL
No. Kontrak : 22SRF1780
Kontraktor : PT. PUTRA MAS AGRO SEJAHTERA
Hari/Tanggal : 23 Juni 2023

Penerimaan Material Penerimaan Material Perancah Kayu bulat d 6 -8 @4m

Pabrikasi Pembesian D13 @4m Pabrikasi Pembesian D13 @4m


Doc. No FORM-04-QA-G002
Quality Form Revision 00
Date 23/02/2023
Daily Report Page -

PROJECT NAME : Retaining Wall dan Rantai Loading Ramp EMPLOYER : PT. SAWITAKARYA MANUNGGUL
PROJECT ID : 22SRF1780 CONTRACTOR : PT. PUTRA MAS AGRO SEJAHTERA
LOCATION : PT. SAWITAKATYA MANUNGGUL - SWTM DAY/DATE : 24 Juni 2023
A. Working B. Arrival / Mutation: Equipment and basic materials

No Type Of Work Location No Material Total Total Rejected Total Accepted

1 Pelaksanaan Briefing / Safety Talk SWTM PROJECT - - - -

2 Pabrikasi (Pembersian D13 @12m) SWTM PROJECT

3 Pabrikasi Bekisting Beton Plat Dasar Retaining Wall SWTM PROJECT

4 Pabrikasi Bekisting Beton Dinding Retaining Wall SWTM PROJECT

C. Tools Usage

No Tool Type TOTAL Damage Hours


D. Project Personel / Contractor

No Task / Position Quantity 1 Gerobak Sorong 2 0 2

1 Site Manager - Orang 2 Cutting Whell 14" 1 0 8

2 Supervisor - Orang 3 Pembengkok Besi 2 0 8

3 OHSE 1 Orang 4

4 Head Worker 0 Orang 5

5 Man Power 6 Orang 6

E. Weather / Natural Disasters

No TYPE CLOCK REMARKS

1 Sunny - 07:00 - 17.00 WITA

Total 7 Orang
Proposed Submissions / Suggestions / Instructions Of Deal / Reporting:
-

Work Start At : 07.00 WIB Until Hour : 17.00 WIB


Work Stalled Because : -

Prepared By, Acknowledge By,


PT. PUTRA MAS AGRO SEJAHTERA PT. SAWITAKARYA MANUNGGUL

ARSUDIN SIRAIT RIO DERMAWAN


Safety Officer Resident Engineer

PMAS
DOKUMENTASI HARIAN PMAS
Proyek / PT :
Lokasi : PT. SAWITAKARYA MANUNGGUL
No. Kontrak : 22SRF1780
Kontraktor : PT. PUTRA MAS AGRO SEJAHTERA
Hari/Tanggal : 24 Juni 2023

Pelaksanaan Briefing / Safety Talk View 0%

Pabrikasi Pembesian Plat Beton Tapak Retaining Wall View 0%


Doc. No FORM-04-QA-G002
Quality Form Revision 00
Date 23/02/2023
Daily Report Page -

PROJECT NAME : Retaining Wall dan Rantai Loading Ramp EMPLOYER : PT. SAWITAKARYA MANUNGGUL
PROJECT ID : 22SRF1780 CONTRACTOR : PT. PUTRA MAS AGRO SEJAHTERA
LOCATION : PT. SAWITAKATYA MANUNGGUL - SWTM DAY/DATE : 25 Juni 2023
A. Working B. Arrival / Mutation: Equipment and basic materials

No Type Of Work Location No Material Total Total Rejected Total Accepted

1 Pelaksanaan Briefing / Safety Talk SWTM PROJECT - - - -

2 Pabrikasi (Pembersian D13 @12m) SWTM PROJECT

3 Pabrikasi Bekisting Beton Plat Dasar Retaining Wall SWTM PROJECT

4 Pabrikasi Bekisting Beton Dinding Retaining Wall SWTM PROJECT

C. Tools Usage

No Tool Type TOTAL Damage Hours


D. Project Personel / Contractor

No Task / Position Quantity 1 Gerobak Sorong 2 0 2

1 Site Manager - Orang 2 Cutting Whell 14" 1 0 8

2 Supervisor - Orang 3 Pembengkok Besi 2 0 8

3 OHSE 1 Orang 4

4 Head Worker 0 Orang 5

5 Man Power 6 Orang 6

E. Weather / Natural Disasters

No TYPE CLOCK REMARKS

1 Sunny - 07:00 - 17.00 WITA

Total 7 Orang
Proposed Submissions / Suggestions / Instructions Of Deal / Reporting:
-

Work Start At : 07.00 WIB Until Hour : 17.00 WIB


Work Stalled Because : -

Prepared By, Acknowledge By,


PT. PUTRA MAS AGRO SEJAHTERA PT. SAWITAKARYA MANUNGGUL

ARSUDIN SIRAIT RIO DERMAWAN


Safety Officer Resident Engineer

PMAS
DOKUMENTASI HARIAN PMAS
Proyek / PT :
Lokasi : PT. SAWITAKARYA MANUNGGUL
No. Kontrak : 22SRF1780
Kontraktor : PT. PUTRA MAS AGRO SEJAHTERA
Hari/Tanggal : 25 Juni 2023

Pekerjaan Pabrikasi Bekisting Plat Beton Lantai Retaining Wall Pekerjaan Pabrikasi Bekisting Dinding Retaining Wall

Parikasi Pembesian D13 @12m Gudang Peralatan