Download as pdf or txt
Download as pdf or txt
You are on page 1of 23

Pr

ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
P)
M
TE
,D
Answer C

r
re
tu
ec
(L
Total float affects all activities in the network while free

re
ho
float affects only preceding activities.
at
R
ep
e
ad
Pr
Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Answer C

P)
1. Optimistic time estimates(tO):- Shortest possible time in which

M
an activity can be completed, under ideal conditions.

TE
,D
2. Most Likely / Most probable time (tL):- Most often (Normal

r
re
conditions).

tu
ec
3. Pessimistic time (tP):- Maximum time (abnormal situations).

(L
re
ho
at
Expected Time (tE) :- The average time taken for the completion
R
ep
of the activity or job.
e
ad

tE = (tO+4tL+tP) / 6
Pr

= (6 + 4 × 15 + 60) / 6
= 21 minutes
Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Answer A

P)
M
1. Standard deviation

TE
,Dr
re
tu
ec
= (60-6) / 6 = 9

(L
re
ho
at
R
eep
ad
Pr

2. = 9² = 81
Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Answer C

P)
M
Rules to draw project network→

TE
,D
1. There should be single arrow for every activity.

r
re
2. Every activity should have start and end node.

tu
ec
3 Project should flow only in one direction.

(L
re
4. Project should have only one start & only one finish

ho
at
node.
R
ep
5. Two activities should not have common start & end
e
ad
Pr

node.
6. There should be no looping allowed in network.
Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Pr
Answer D
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Answer B

P)
M
1. Normal Time:- is the time that an estimator would usually

TE
allow for an activity.

,Dr
2. Crash time:- is the minimum possible time in which an activity

re
tu
ec
can be completed, by employing extra resources.

(L
Crash time is the time, beyond which the activity cannot be

re
ho
shortened by any amount of increase in resources.
at
R
3. Normal Cost:- This is direct cost required to complete the
eep
activity in normal time duration.
ad
Pr

4. Crash Cost:- This is the direct cost corresponding to the


completion of the activity within crash time.
c)
a)

d)
b)
Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Answer D

P)
M
Total Project Cost = Direct Cost + Indirect Cost

TE
,Dr
re
1. Indirect Cost:- Those expenditures which cannot be clearly

tu
ec
allocated to the individual activities of a project, but are assessed

(L
re
as a whole. Eg. Overhead, supervision, penalty etc.

ho
at
R
ep
2. Direct Cost:- Those expenditures which are directly chargeable
e
ad

to and can be identified specially with the activities of the


Pr

project. Eg. Labour cost, material cost, equipment cost etc.


Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Answer D

Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Answer A

P)
1. Normal Time:- is the time that an estimator would usually

M
TE
allow for an activity.

,D
2. Crash time:- is the minimum possible time in which an activity

r
re
can be completed, by employing extra resources.

tu
ec
Crash time is th

(L
re
at time, beyond which the activity cannot be shortened by any

ho
at
amount of increase in resources.
R
ep
3. Normal Cost:- This is direct cost required to complete the
e
ad

activity in normal time duration.


Pr

4. Crash Cost:- This is the direct cost corresponding to the


completion of the activity within crash time.
Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
Answer B

Pr
ad
eep
R
at
ho
re
(L
ec
tu
re
r,D
TE
M
P)
P)
M
TE
,D
Thank You For Watching

r
re
tu
ec
🙏☺

(L
re
Like, Comment, Share and Subscribe
ho
at
R
eep
ad
Pr

Civil Engineering Pathshala

You might also like