Professional Documents
Culture Documents
Earned Value Management
Earned Value Management
MANAGEMENT
By: TANVEER
Date: Jan 2021
L i n ke d In
Earned Value Management
• Introduction
• Solved Example
2
Best practice focusing on
Integrates
What is Technical Performance (status of work)
Cost Performance
Measuring performance
Analysing Variance
Developing Forecast
3
Data only for the current
4
Easy to understand Low overhead
Well Proven
5
The alleged complexity of surrounding
1 methodology and Processes
6
Major Steps in Using EVM
ANALYZE AND
DEVELOP ACTIVITY RECORD ACTIVITY MEASURE PHYSICAL FORECAST REPORT
LEVEL BUDGET LEVEL USAGE PROGRESS PERFORMANCE PERFORMANCE
7
EVM Terminology & Definition
ACRONYM NAME DEFINITION
8
Schedule Variance (SV) = EV-PV
VAC = BAC-EAC
FORMULAS
EAC = BAC/CPI
ETC = EAC-AC
TCPI = (BAC-EV)/(BAC-AC)
9
Interpretation of Basic EVM-Performance
SCHEDULE
SV > 0 SV = 0 SV < 0
SPI >1.0 SPI =1.0 SPI <1.0
10
EVM-Scenarios
with Graphical
Representation Scenario # Case Remarks
1 Behind Schedule, Worst Case
Over Budget
Example#1
Day-3
C a l c u l a t e P V, E V, A C , B A C , C V, C P I , S V, S P I , E A C , E TC , VA C
12
General Overview
Schedule
Schedule Variance Cost Variance
Performance Index
SV = EV-PV CV = EV-AC
SPI = EV/PV
Cost Performance
Index VAC = BAC-EAC EAC = BAC/CPI
CPI = EV/AC
TCPI = (BAC-
ETC = EAC-AC
EV)/(BAC-AC)
13
Example#1 with Solution Solution:
NEW OLD
ACRONYM NAME ACRONYM NAME
PV Planned Value BCWS Budgeted Cost of Work Schedule
15
Thank you
ANY
QUESTION?
16
Scan and Ask