Professional Documents
Culture Documents
20-vcc-how-to-apply-set-up-time-reduction-v2
20-vcc-how-to-apply-set-up-time-reduction-v2
Reduction
Value Chain Competitiveness (VCC)
Version: 2
February 2020
This information is provided by Rolls-Royce in good faith based upon the latest information available to it;
© 2020 Rolls-Royce | Not Subject to no warranty or representation is given; no contractual or other binding commitment is implied.
Export Control
2
2. Apply a
1. Understand the Gate Gate
structured
Start benefits of set-up Check Check
list approach for set- list
time reduction
up time reduction
© 2020 Rolls-Royce
3
© 2020 Rolls-Royce
4
Production Stop Find Tooling Load Tooling Set-Up M/c Verify Production
Production Production
VA NVA VA
The objective is to:
© 2020 Rolls-Royce
5
1. Understand the benefits of set-up time BACK Map NEXT
reduction
Set-up time reduction enables smaller economic batch quantities (EBQ)
EBQ
Cost
Overall cost
Batch size
smaller EBQ
Key advantages of smaller batch sizes after set-
Overall cost up reduction
Inventory cost • reduced stock levels
• shorter lead-times
Set-up cost
• better response to customer demands
Batch size • higher flexibility in planning – easier to
manage production
© 2020 Rolls-Royce • lower overall cost
6
1. Understand the benefits of set-up time BACK Map NEXT
reduction
Following set-up time reduction there is more time available (capacity) for value-added
work (hence more productivity and throughput)
Production Stop Find Tooling Load Tooling Set-Up M/c Verify Production
© 2020 Rolls-Royce
7
Gate checklist 1: Understand the benefits of BACK Map NEXT
set-up time reduction
The benefits of set-up time reduction on batch size and operating cost is understood
© 2020 Rolls-Royce
8
2. Apply a structured approach for set-up BACK Map NEXT
time reduction
The set-up can be categorised into internal and external activities
VALUE-ADDED NON VALUE-ADDED VALUE-ADDED
Set-Up Time
Internal Activity = Activities that can only be done whilst the process is stopped
External Activity = Activities that could be done whilst the process is running
Minimise
Set-Up Time
© 2020 Rolls-Royce
9
2. Apply a structured approach for set-up BACK Map NEXT
time reduction
Five steps to a successful set-up reduction
5 1
4 2 Set-Up Time
3
Production Ext Int Ext Int Ext Int Int Ext Int Int Int Int Production
1. Observe and document the current
process
2. Differentiate between internal
and external activities Production Int Int Int Int Int Production
© 2020 Rolls-Royce
10
2. Apply a structured approach for set-up BACK Map NEXT
time reduction
• Observe and document the process (timings etc.)
5 1 • ensuring that all elements are captured and recorded up until the
4 2 first good ‘new’ component is produced
3
© 2020 Rolls-Royce
11
2. Apply a structured approach for set-up BACK Map NEXT
time reduction
5 1
• Map out the separate activities of the observed set-up
4 2
3
Production Stop Find Tooling Load Tooling Set-Up M/c Verify Production
Go to stores
2’ 35”
Find spacers
4’ 17”
Modify spacers to fit
1’38”
Load tool into fixture
12’ 49”
‘Post-It’ notes
0’ 45”
© 2020 Rolls-Royce
12
2. Apply a structured approach for set-up BACK Map NEXT
time reduction
• Determine activity step type (Internal / External) and identify on the process
5 1
step sequence
4 2
3
Prepare Tools External
Go to stores External
2’ 35”
Find spacers External
4’ 17”
Modify spacers to fit External
1’38”
Load tool into fixture
12’ 49” Internal
0’ 45”
© 2020 Rolls-Royce
13
2. Apply a structured approach for set-up BACK Map NEXT
time reduction
Convert internal activities into external activities wherever
5 1
possible
4 2
3 • All tooling and equipment required to set-up the process must
be prepared and available before the set-up starts – use
shadow boards etc.
• Checklist of all tools and equipment necessary
• Description, specification, method of use, setting methods,
measurement of product, key dimensional characteristics and
processing parameters
• All equipment for use should be in good working order
• Ensure all necessary personnel are available when required
(the ‘F1 Pit Crew’ mentality)
• Visual management of production plan and system for calling
resources to the set-up process defined
• Ensure all information is available when needed
• Drawings, Setting sheets, Check lists, Material Specifications etc.
© 2020 Rolls-Royce
14
2. Apply a structured approach for set-up BACK Map NEXT
time reduction
5 1 Streamline internal operations; challenge everything!
Design standard
4 2 clamps
3
Design out / Eliminate the need for
Use a standard clamps
Pre-assemble tool
Develop
Re-Align
Develop
1’ 34” Get Special Drill
4’ 57” Prepare Clamps Develop quick
release and clamp
3’ 38” Insert & Tighten Screw fixing
2’ 19” Eliminate the need
1’ 25” Re-design the screw
© 2020 Rolls-Royce
15
2. Apply a structured approach for set-up BACK Map NEXT
time reduction
• Standardise functional operations
5 1 • Clamping height
4 2 • Fixing sizes and dimensions
3
• Use common sizes of bolt, screw, nut, etc.
• Use methods or equipment to simplify operations
• Centering jigs
• Intermediary jigs (to bring piece up to standard size or to fit a Toggle clamp
standard fixture)
• Use simple clamping methods - quick release / pneumatic / hydraulic
/ other as appropriate
C - washers
Re-Align Organise
1’ 25”
© 2020 Rolls-Royce
17
2. Apply a structured approach for set-up BACK Map NEXT
time reduction
Machine set-up procedures need to be visually simple and located in the workplace
© 2020 Rolls-Royce
18
Gate checklist 2: Apply a structured BACK Map NEXT
approach for set-up time reduction
The team have converted any identified Internal activity into External activity
wherever possible
© 2020 Rolls-Royce
19
3. Maintain and improve the set-up BACK Map NEXT
standard
Machine set-up metrics must track the performance of the activity to maintain the
standard and identify improvement opportunities
© 2020 Rolls-Royce
20
Gate checklist 3: Maintain and improve the BACK Map
set-up standard
Metrics and visual management are in place to track and manage / drive set-up time
reduction activity
© 2020 Rolls-Royce