Week10

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 34

KIX2006

ENGINEERING ECONOMICS AND PROJECT MANAGEMENT

Week 10: Managing Risks


Chapter Objectives
• To describe the risk management process
• To identify different kinds of risks
• To illustrate approaches for risk identification,
analysis, and assessment
• To suggest approaches for responding to project
risks and opportunities
• To propose the use of contingency reserves to
cover risk events
• To recognize the need for a change control
process/system for any size project.
Risk Management Process
• Risk
– Uncertain or chance events that planning can not
overcome or control.
It can effect at least one or all : scope, schedule, cost
and quality.
• Risk Management
– A proactive attempt to recognize and manage internal
events and external threats that affect the likelihood of a
project’s success.
• What can go wrong (risk event).

• How to minimize the risk event’s impact (consequences).

• What can be done before an event occurs (anticipation).

• What to do when an event occurs (contingency plans).


The Risk Event Graph
• The early stages of the project represent the period when the
opportunity for minimizing the impact or working around a
potential risk exists.
• Conversely, as the project passes the halfway implementation
mark, the cost of a risk event occurring increases rapidly.

FIGURE 7.1
Risk Management’s Benefits
• A proactive rather than reactive approach (better
planning).
• Reduces surprises and negative consequences
(avoid surprises).
• Prepares the project manager to take advantage
of appropriate risks (improved project delivery).
• Provides better control over the future (Increased
customer satisfaction).
• Improves chances of reaching project performance
objectives within budget and on time (reach schedule
& budget goals).
Example Risk Categories
• Inflation
• Market acceptance (Market risk)
• Exchange rates
• Government regulations
• Financial risk
• Technical risk
• People risk
“threats” and its unlimited
The Risk
Management
Process

FIGURE 7.2
Managing Risk
• Step 1: Risk Identification
– Generate a list of possible risks through brainstorming,
problem identification and risk profiling.
• Macro risks first, then specific events
– Organizations use risk breakdown structures (RBSs) in
conjunction with work breakdown structures (WBSs) to
help management teams identify and eventually analyze
risks. Figure 7.3 provides a generic example of an RBS.
The focus at the beginning should be on risks that can
affect the whole project as opposed to a specific section of
the project or network.
– A risk profile is another useful tool. A risk profile is a list of
questions that address traditional areas of uncertainty on a
project.
The Risk Breakdown Structure (RBS)

FIGURE 7.3
Partial Risk Profile for Product Development Project

FIGURE 7.4
Managing Risk
• Step 2: Risk Assessment
– Scenario analysis for event probability and impact.
The quality and credibility of the risk analysis process
requires that different levels of risk probabilities and
impacts be defined. Because impact ultimately needs
to be assessed in terms of project priorities, different
kinds of impact scales are used (Figure 7.5-impact
scales could be defined given the project objectives
of cost, time, scope, and quality.)
– Figure 7.6: Documentation of scenario analyses can
be seen in various risk assessment forms used by
companies.
Defined Conditions for Impact Scales of a Risk on Major
Project Objectives (Examples for negative impacts only)

FIGURE 7.5
Risk Assessment Form

IS project involving the upgrade from Windows Vista to Windows 7


Notice that in addition to evaluating the severity and probability of risk
events the team also assesses when the event might occur and its
detection difficulty. FIGURE 7.6
Managing Risk
• Step 2: Risk Assessment
– Risk assessment matrix. The matrix is typically structured
around the impact and likelihood of the risk event. The risk
severity matrix provides a basis for prioritizing which risks to
address. Red zone risks receive first priority followed by
yellow zone risks. Green zone risks are typically considered
inconsequential and ignored unless their status changes.
– Failure Mode and Effects Analysis (FMEA). the risk severity
matrix by including ease of detection in the equation:
Impact X Probability X Detection = Risk Value
– Probability analysis
• Decision trees, Net Present Value (NPV), and Program Evaluation and
Review Technique (PERT)
Risk Severity Matrix
Failure Mode and Effects Analysis (FMEA)
Impact × Probability × Detection = Risk Value

User Interface
4 Backlash problems
Likelihood

Red zone (major risk)


3 Yellow zone (moderate risk)
Green zone (minor risk)

System
2
freezing

Hardware
1 malfunc-
tioning

1 2 3 4 5 FIGURE 7.7
Impact
Managing Risk (cont’d)
• Step 3: Risk Response Development
– Mitigating Risk
• Reducing the likelihood an adverse event will occur.
• Reducing impact of adverse event.
– Avoiding Risk
• Changing the project plan to eliminate the risk or condition.
– Transferring Risk
• Paying a premium to pass the risk to another party.
• Requiring Build-Own-Operate-Transfer (BOOT) provisions.
– Retaining Risk
• Making a conscious decision to accept the risk.
Contingency Planning
• Contingency Plan
– An alternative plan that will be used if a possible
foreseen risk event actually occurs.
– A plan of actions that will reduce or mitigate the
negative impact (consequences) of a risk event.

• Risks of Not Having a Contingency Plan


– Having no plan may slow managerial response.
– Decisions made under pressure can be potentially
dangerous and costly.
Risk Response Matrix

Windows 7 project is used to illustrate this kind of matrix

FIGURE 7.8
Risk and Contingency Planning
• Technical Risks
– Backup strategies if chosen technology fails.
Assessing whether technical uncertainties
can be resolved.
• Schedule Risks
– Use of slack increases the risk of a late project finish.
– Imposed duration dates (absolute project finish date)
– Compression of project schedules due to a shortened
project duration date.
Risk and Contingency Planning (cont’d)
• Costs Risks
– Time/cost dependency links: costs increase when
problems take longer to solve than expected.
Price protection risks (a rise in input costs) increase if
the duration of a project is increased.
• Funding Risks
– Changes in the supply of funds for the project can
dramatically affect the likelihood of implementation or
successful completion of a project.
Opportunity Management Tactics
• Exploit
– Seeking to eliminate the uncertainty associated with an
opportunity to ensure that it definitely happens.
• Share
– Allocating some or all of the ownership of an opportunity to
another party who is best able to capture the opportunity for the
benefit of the project.
• Enhance
– Taking action to increase the probability and/or the positive
impact of an opportunity.
• Accept
– Being willing to take advantage of an opportunity if it occurs, but
not taking action to pursue it.
Contingency Funding and Time Buffers
• Contingency Funds
– Funds to cover project risks—identified and unknown.
• Size of funds reflects overall risk of a project
– Budget reserves
• Are linked to the identified risks of specific work packages.
– Management reserves
• Are large funds to be used to cover major unforeseen risks
(e.g., change in project scope) of the total project.
• Time Buffers
– Amounts of time used to compensate for unplanned
delays in the project schedule.
• Severe risk, merge, noncritical, and scarce resource activities
Contingency Fund Estimate ($000s)

Table 7.1 shows the development of a contingency fund estimate for a


hypothetical project. Note how budget and management reserves are
kept separate; control is easily tracked using this format
TABLE 7.1
Managing Risk (cont’d)
• Step 4: Risk Response Control
– Risk control
• Execution of the risk response strategy
• Monitoring of triggering events
• Initiating contingency plans
• Watching for new risks

– Establishing a Change Management System


• Monitoring, tracking, and reporting risk
• Fostering an open organization environment
• Repeating risk identification/assessment exercises
• Assigning and documenting responsibility for managing risk
Change Management Control
• Sources of Change
– Project scope changes
– Implementation of contingency plans
– Improvement changes
Change Control System Process

1. Identify proposed changes.


2. List expected effects of proposed changes
on schedule and budget.
3. Review, evaluate, and approve or disapprove
of changes formally.
4. Negotiate and resolve conflicts of change,
condition, and cost.
5. Communicate changes to parties affected.
6. Assign responsibility for implementing change.
7. Adjust master schedule and budget.
8. Track all changes that are to be implemented
The Change
Control
ntrol Process

FIGURE 7.9
Benefits of a Change Control System
1. Inconsequential changes are discouraged
by the formal process.
2. Costs of changes are maintained in a log.
3. Integrity of the WBS and performance measures
is maintained.
4. Allocation and use of budget and management
reserve funds are tracked.
5. Responsibility for implementation is clarified.
6. Effect of changes is visible to all parties involved.
7. Implementation of change is monitored.
8. Scope changes will be quickly reflected in baseline
and performance measures.
Sample Change
Request

FIGURE 7.10
Change
Request Log

FIGURE 7.11
Key Terms

Avoiding risk Risk


Budget reserve Risk breakdown structure (RBS)
Change management system Risk profile
Contingency plan Risk register
Management reserve Risk severity matrix
Mitigating risk Scenario analysis
Opportunity Time buffer
Retaining risk Transferring risk
Review Questions
Project risks can/cannot be eliminated if the project is carefully
planned. Explain.

Project risks cannot be eliminated. It is impossible to be aware of


all things that might happen when a project is being implemented.
Undesirable events identified before the project begins can be
transferred, retained/reduced, or shared. Contingency plans with
trigger points and responsibility should be established before the
project begins.
Review Questions
The chances of risk events occurring and their respective costs
increasing change over the project life cycle. What is the
significance of this phenomenon to a project manager?

The chances of risk events and estimated costs changing over the
project life cycle are high. These events will impact project
change control mechanisms. Moreover, such changes could be
significant enough to require changes in scope. The project
manager must ensure that these changes are recorded and kept
updated. Otherwise the integrity of the project control system will
quickly deteriorate and become useless as a management tool.
Review Questions
What are the major differences between managing negative risks
versus positive risks (opportunities)?

Essentially the same process that is used to manage negative


risks is applied to positive risks. The major differences occur in
the responses. Instead of avoiding negative risks, project
managers often try to exploit positive risks by taking action to
ensure that the opportunity occurs. Instead of transferring risks to
another party, project managers often share positive risks to
increase the likelihood the opportunity can be exploited. Instead
of mitigating negative risks, project managers will take action to
enhance the likelihood the opportunity will occur and/or increase
the positive impact of the opportunity. Finally, project managers
will often choose to accept both negative and positive risks, but be
prepared to respond if either occurs.

You might also like