Professional Documents
Culture Documents
Lecture 11 - Certificates CCC (2)
Lecture 11 - Certificates CCC (2)
Lecture 11 - Certificates CCC (2)
15.2(a) If in the opinion of the Architect the works is not Practically Completed, he
shall issue reply to the contractor giving his opinion
The certificate shall be issued to contractor copies to Employer and all sub contractors and
contractor shall return the site to Employer
Implication upon issuance the Certificate of Practical
Completion
1. End of Contraction contractual obligation
2. Employer to insure the building
3. Return of half of the Retention Fund
4. End of warranty. Performance Bond return
5. Beginning of Defect Liability Period
6. End of Liquidated Ascertain Damages (LAD)
7. Beginning of Final Account
22.1 the Contractor is to complete the works by the Completion Date
failing which the Architect in the opinion that the works are incomplete
The Architect shall issue Certificate of Non Completion (CNC)
22.2 LAD is a fine imposed to the contractor for failing the complete on time.
It is calculated to cover the loss to the employer due to the delay in completion
15.3 Contractor’s failure to comply with the undertaking
Contractor has to comply to make good all minor defect as per defect list within
specified time. In the event if they fail. Employer may take the following actions:
15.3(a) Grant contractor extra time-specified by Architect, or
15,3(b) Employ and pay other person and set off the payment or
15.3(c) accept the defect and appropriate set off the cost of the defects.
15.4 Schedule of Defects
Any defects appear during Defect Liability Period (DLP) shall be prepared
by Architect in a Schedule of Defect and shall be delivered to the
contractor within 14 days after DLP and the contractor shall make good
within 28 days. If they fail to comply, the following actions shall be taken
-Employ and pay other person and set off the payment or
-accept the defect and appropriate set off the cost of the defect
15.5 Instruction to make good Defects
Architect may issue A.I at any time during DLP on any critical
defects which need urgent rectification within reasonable time
and if the contractor fail, the Employer may employ other person
to do the defects and cost incurred shall be set off by the Employer
5.0 CERTIFICATE OF MAKING GOOD DEFECTS
Issued by Architect upon completion and acceptance of
rectification of defects works by the Contractor. It mark the end
of Contractor liability to the contract.
The implication that
1. The balance of half of the Retention Fund to be release
2. Final account to be finalised and release for payment.
15.6 Certificate of Making Good Defects
Contractor to give written notice Architect upon completion of
making good defects. The Architect within 14 days shall do the
following
15.6(a) In the opinion of the architect, there is no defects or has
been made good he shall issues Certificate of Make Good
Defects (CMGD) and shall be the date of receipt of contractor’s
notice. Copies to Employer and all sub contractors.
15.6(b) If in the opinion of the Architect that Defects has not been
made good, he shall write to contractor and give reasons.
6.0 PENULTIMATE CERTIFICATE OF PAYMENT
Certificateof payment issued to Contractor after the
issuance of Certificate of Making Good Defects
(CMGD) issued prior to the issue of Final Certificate.
7.0 FINAL CERTIFICATE
See detail
CONTRACT MANAGEMENT
CPC ISSUED
(Certificate of Practical Completion )
Release of half moiety of Retention Fund
CMGD ISSUED
(Certificate of Making Of Good Defect)
12 MONTHS
28 days
Final Certificate issued
POST CONSTRUCTION STAGE within 28 days in the ev ent
NO Penultimate Cert Has
CERTIFICATE OF PRACTICAL COMPLETION (CPC), been issued
DEFECT LIABILITY PERIOD (DLP) &FINAL ACCOUNT
CERTIFICATE OF COMPLIANCE AND
COMPLETION (CCC)
WHY WE NEED CCC?
WHAT IS CCC?
CCC is a certificate that verifies a building is safe and fit for occupation and
this certificate will only be issued after construction complied with the
provisions of the law, approved building plan and also the conditions set by
local authorities in the approval of the building plan.
ROLES AND RESPONSIBILITIES OF THE LOCAL AUTHORITY (LA)
4. Issue notice to PSP to take action on any 8. Charge the parties who have provided false
matter not in compliance with the provisions of certification in the forms as specified in the
the law and the technical conditions imposed in UBBL 2007 and report them to the respective
the Planning Permissions and Building Plan regulatory bodies
5. Issue notice to the PSP to withhold the 9. Ensure that the safety of buildings exceeding
issuance of the CCC 5 floors and aging 10 years from the date CCC
5.1 Until the non-compliances have been is issued are inspected every 10 years.
rectified
5.2 If a fraud occurs in the construction,
documentation or project management,
and if inaccurate information is discovered
in the documentation
ROLES AND RESPONSIBILITIES OF PRINCIPAL SUBMITTING PERSON (PSP)
1. Submit the Building Plan to the LA for approval 7. Ensure that G Forms are duly
using Form A completed and deposit copies of all said
Forms (including those not related) to the
2. Coordinate the preparation commence and LA and Professional Board
submission of other plans besides building plans
3. Inform the LA through Form B to construction 8. Submit the CCC to the owner or
operation at the site developer and a copy of the said
certificate to the LA and the relevant
4. Supervise construction works at the site and ensure Professional Board, and
that the provisions of the law and technical
conditions imposed are complied with 9. Ensure that the rectification of non-
compliances during construction as
5. Report and explain the reasons for non- stipulated in the LA notice to the PSP are
compliance and state the rectification measures complied with before issuing the CCC
taken in the event of non-compliance occurring
during construction
The implementation of
CCC system involves the
use of both new and
existing forms.
FORM G
SYUKRAN
DATE: 13/07/2021
INTERIM CERTIFICATE
11. Contractor give notice to Architect when the works is Practically Completed and
Architect to reply within 14 days.
12. Upon issuance the Certificate of Practical Completion (CPC) it mark the end of
consultant responsibilities
13. LAD is a fine imposed to the contractor for failing the complete on time. It is
calculated to cover the profit to the employer due to the delay in completion
14. Any defects appear during Defect Liability Period (DLP) shall be prepared by Architect in a Schedule
of Defect and shall be delivered to the contractor within 28 days after DLP and the contractor shall
make good within 14 days.
15. If the contractor fail to repair any defect within the given time, Employer can engage
another contractor and the cost shall be deducted form the first contractor
16. Architect may issue A.I at any time during DLP on any critical defects which need urgent rectification.
17. In the opinion of the architect, there is no defects or has been made good he shall issues Certificate of
Compliance and Completion and shall be the date of receipt of contractor’s notice.
18
19
20
21
22
23
25
24
26
CERTIFICATE OF MAKING GOOD DEFECTS
FINAL CERTIFICATE
35. The following are the responsibility of Local Authority in dealing with CCC EXCEPT
A. Certificate of EOT
B. Certificate of Practical Completion
C. Certificate of Non Completion
D. Penultimate Certificate
E. Certificate of Making Good Defect
37. Which is the forms listed below presently not issued by Architect
A. Form F: CCC
B. Form C Notice of setting out
C. Form E: Application for CFO
D. Form A: Submission of building approval/ Bldg. Certificate
E. Form B: Notice of Commencement.
TRUE OR FALSE
38. In the event that the site was stop by the LA due to some non compliance with
the approved plan and in order to resume work Architect to submit notice for the
resumption of work through Form B to the LA
39. Inform the LA through Form D to commence construction operation at the site
40. Upon completion, ensure that G Forms are duly completed and deposit copies of
all said Forms (including those not related) to the LA and Professional Board