Professional Documents
Culture Documents
roof coverings
roof coverings
COVERING 345
ROOFS
AND
upto16
m span.
nly
only trusses are fire-proof.
5. Steel
Steel trusses are termite proof.
trusses are most resistant to other environmental have
7. Steel agencies, and
longer life.
mac
be
site for erection.
uIwwuw
Reversed
(a) Pan tiles
FNibs-U
Section X - X
Insulation
Gutter
Section
(c) Eaves details Elevation
Fascla
WITH PAN-TILES.
FIG. 15.26. ROOFING
348 BUILDING CONSTRUCTION
of the wave, nail hole is formed below the nib and two of the
a opposite diagonals
corners are splayed or rounded. Pan-tiles are laid with overlapping side joints with
two thicknesses only at the head joints and a single thickness at the unlapped portions,
Pan-tiles are unbonded,
having continuous side joints from eaves to the ridge. Thus,
pan-tiles are single lapped in contrast to the plain tiles which are double lapped. Side
lap in pan-tiles varies from 38 to 50 mm. The head or longitudinal lap varies rom
7.5 to 10 cm,
according to the pitch of the roof. Plain tiles are also nailed. As stated
above, two diagonally opposite corners or shoulders are splayed
off to the depthof
the lap, to permit a reasonably close fit between the tiles. If this is not done, four
thicknesses would occur at the corners, resulting in
open joints due to tilting or
over-riding
of tiles. Fig. 15.26 shows the details of
roofing with pan-tiles.
3. Halfround
country tiles : Head
Spanish tiles (Fig. 15.27)
Half-round country tiles are Head
commonly used in villages. These Tail
tiles are laid in pairs of under-tiles
and over-tiles. The under-tiles are
Tail
laid with concave surface (a) Over tile (b) Under tile
upwards,
while the over-tiles are laid with Unders
convex surface
Overs
upwards. These -AAAA
1.05m
Side lap
44.45 mm
Steel
purlin 1.02 m-
1.09 m
Nut
(a) Everest big six G . I. washer
Purlin
Wood purlin
Hook bolt
(b) Everest standard (c)Everesttrafford
FIG. 15.30. A.C. SHEETS3
Cranked Asbestos
Bitumen h o o k bolt washer
washer
The laying is always commenced from eaves. The eaves course is, therefore, laid
nrst. When laying is done from left to right (Fig. 15.33), the first sheet is laid uncut
352 BUILDING CONSTRUCTION
Ridge capping
Bigsix
m.s corrugated
sheet
burlin
M . S .a n g l e
Wood
purlin
Bigsix
Corrugated
(c) Ridge details
Hook
bolt sheets M.S.angle
rafter
m . s .a n g l e
Eaves gutter
1. The A.C. sheets should be laid with smooth side upward, and the end marked
toward the ridge.
Top' pointing
2. End lap and side lap should be properly maintained. General end lap is 15
but this can be vaned to suit
purlin spacing.
3. Purlin spacing and length of sheets should properly checked, before
4. The holes for fixing accessories should be drilled (and not punched) in the
laying
crown of the corrugations. The diameter of the holes should be 3 mm greater than
the diameter of the fixing bolt or screw. Thus 8 mm dia. drilled holes, and screwed
lightly
5. Bitumen washers should be provided under G.I. flat washer. The nuts of the
screws or bolts are moderately tightened when 10 to 12 sheets have been laid. They
should not be screwed very tight.
6. Ridge cappings
should be secured to the ridge purlin.
7. The sheets should be 'mitred' properly as
required.
8. The unsupported overhang of A.C. sheets should not exceed 30 cm.
(e) Galvanised Iron corrugated sheets (G.I. sheets)
G.I.
are also
sheets used. They are stronger than A.C. sheets.
widely
because of their higher cost, they are now gradually replaced by A.C. sheets. They
However
are not used for slopes flatter than 1 in 4. G.I. sheets are manufactured with corrugations
running from one end to the other. The corrugations impart additional strength to
the sheets. G.I. sheets are made of iron sheets which are galvanised with zinc to
protect them from rusting action of water and wet weather. These sheets are fixed
in a manner similar to the A.C. sheets. End lap should not be less than 15 cm and
the side lap varies from 1 to 2 corrugations. The holes are either drilled or punched
in the sheet crowns. The sheets are secured to purlins by means of G.I. hook bolts,
screws and nails etc., with curved washers. The sheets should be fixed to eaves by
means of flat iron wind ties.
Slate
Slate roofing
Slate is a hard, fine-grained sedimentary argillaceous(clayey) stone. Slate is obtained
trom either open qquarries or mines, in the form of blocks. A diamond or circular saw
Ised to divide each block into sections which are 450 to B00 mm wide and upto
360 mm thick. The saw blocks are then reduced to slabs which are about 15 to 30
mm thick. Each slab is then divided into thin laminae or slates, by hand labour, using
à splitter. The thickness of slate, used for roofing may vary from 4 to 8 mm. The
e s of slates vary from 600 mm x 300 mm to 400 mm x z00 mm. A good slate should
be hard, tough and durable, of rough texture, ring bell-like when struck, not split
Wnen holed or dressed, practically non-absorbant and of a satisfactory colour. Slates
re not commonly used in our country. However, in hilly areas, where slate roofing
as been used, the roofing consists of bituminous slates known as Eternit. They are
Eenerally available in three colours-grey, black and red.
Slates are laid so that each slate overlaps a slate in the next course but below
t h e amount is known as lap. The amount of lap depends upon the pitch and the
354
BUILDING CONSTRUCTION
355
O.9
(b) Pitch troughed sheet
Sheet width 928
0.9
P 127
e/T (c) Industrial corrugated sheet H
45
150 Side lap
0.6 mm
600 to 1000
(d) Aluminium alloy and steel decking
FIG. 15.35. METAL ROOF
SHEETING
aTe generally of 50 to 75 mm thickness. They are nailed to timber joists at 600 to
900 mm centres, with the help of 102 to 125 mm long clout nails. These slabs, when
unreinforced, can take load upto 0.75 kN/m2.
Straw board decking is made of
compressed straw with thick water
eovering. The thickness is 50 mm, width 1.2 m and length from 1.8 to proof paper
3.6 m. For
roof decking, the board is
supported at 600 mm centres, all along all edges.
Aleminium alloy and steel can be pressed to form
troughed roof decking (Fig.
15.35 d) with thicknesses varying from 0.7 mm to 1.2 mm, depth of corrugations varying
rom 25 to 85
mm, widths varying from 450 to 900 mm, and lengths 10 m.
bese are suitable
upto
upto a super-imposed load of 0.75 kN/m. The deck is fixed to the
oot
supports by hook bolts, or bolts and cleats, or by hammer drive screws. A felt
Roof lRidge cap
finish
Grit-finish 5-ply felt
Hot Bitumen
Fibre
board S t e e ld e c k *
Steel dech
Internal ridge
E n dl a p
A A Z
Purtin Purlin
Purlin
7The speed of tlat root construction is much slower than the pitched roof.
aThe initial cost of flat roof is more than pitched roof.
8.
aThe flat roof exposes the entire building to the weather agencies, while the
ing elements (such as eaves ete.) of pitched roof provide some protection to the
projecting e l e m e n t s
building.
also b e
sed over RC.C. slab. The procedure of lime terracing varies from place to
he one adopted for Jodhpur stone slab roofing is described below, in steps
place. T h e
T1.h e longitudina Joints between the stone slabs are first pointed in cement
The joints should be V-shaped, not exceeding 25 mm at the top and 10 mm
morta
ttom. This
the bottom. This joint is filled with cement mortar (mix 1:2 to 1:4) and pickedd
astone
stor
chips of wedge shape and top finish rounded with cement mortar so as
with
tle above
ct little above the slabs. Before filling mortar in the joints, flat strips of timber
toainch dia. bamboos) should be kept along the joint on the other face of the stone
(Or
slabs that
so that mortar does not fall down. Similarly, the space left over the walls at
ends of
he slabs, and
the also the space on walls between the slabs where ro001
is
the
ntipuous should be filled with 1:2:4 cement concrete. These joints should properly
continu
cured, at
least days.
for 7
2. In order to provide proper slope to the roof, ralthal is laid. This is done
hylaving stone spawls in l : 2 lime mortar over the surface of the slabs in the required
thickness. Hydraulic lime (kankar lime) should be used. Ralthal so laid should be cured
for 7 days.
3. Laying of the lime chhat is done in four consecutive days. On the first day,
unslaked kankar lime (hydraulic lime) 10 cm in thickness is spread over the roof slabs.
The lime is then slaked in situ, by adding water. It is then beaten with conical stones
by hand, so that no particles of lime remain unslaked to cause blisters.
4. On the second day, the lime is watered, raked up and again the process of
first day is repeated.
5. On the third day, 250 gm of hemp (finely choped) and methi 750 gm finely
powdered per 10 sq. metre is evenly and thoroughly mixed with the lime. Then coarse
stone aggregate duly washed should be spread over this lime in a thickness not less
than 10 cm.
The coarse aggregate is thoroughly beaten with conical stones by hand so that
this stone aggregate gets well-embedded in lime mass.
6. On the fourth day, stone grit or screening is spread in a layer of 40 mn
and beaten with stone beaters till they are well set. This process of beating should
continue with wooden thapies and by sprinkling water till the whole mass becomes
T and offers resistance to penetration. Thickness of lime chhat should not be less
than 15 cm at
any place.
7. The above work should be cured at least for 7 days.
After seven days, sandala coat consisting of cream of lime is laid over the
lime
hat in thin layers and rubbed for full four kours or more, using rounded pebbles
for
rubbing and polishing.
During the process rubbing, solution of 65 gm of Gur
of
g m of Gugal per 10 square metres is sprinkled every now and then.
.The surface thus prepared is cured with water at least for 15
days using
d or moist gunny bags so as to keep the surface constantly wet.
.
Lime
terracing with tiles
ncrete
h s type of terracing is commonly adopted over R.C.C. roofing. Fig. 15.39 shows
PCal
section of roofing, which is laid in the following steps
360
BUILDING CONSTRUCTION
PROBLEMS