Professional Documents
Culture Documents
Unit 6 Testing & Commissioning and O&M
Unit 6 Testing & Commissioning and O&M
Unit 6 Testing & Commissioning and O&M
Testing ,
Commissioning,
Operation and
Maintenance
Testing and Commissioning of MHP 1
Testing , Commissioning, Operation
and Maintenance (5 hours)
Head works, Electro‐mechanical equipment, Alternator,
Loading machine on main load, Taking readings, Setting
up trips.
Types of manuals‐operation manual, component
manual, installer manual, preventive maintenance
schedule, log sheet, repair manual, training manual,
responsibility of designers, installer and users as regards
to O and M.
Head Works
Channel:
It should be cleaned and flushed of all loose soil,
stones, dirt, etc.
cracks and damages should be checked and repaired if
any.
Desilting:
The flushing valve functions properly.
Desilting basin is clear of all debris.
Gates/Stop-logs:
They operate properly.
Penstock:
All bolts are tightened properly.
It has not sagged at any point.
Water is passed to remove any objects if present.
It should be pressure checked.
Testing and Commissioning of MHP 33
Turbine:
The turbine is well mounted and in good
operation.
Corrosion protection and paint are ok.
The ball bearings are well
lubricated.
The shaft is running smoothly,
there is no noise or vibration.
The turbine alternator alignment is ok.
All the nuts and bolts are properly tightened.