Professional Documents
Culture Documents
SFM11 AGE150_Specifications_20240209
SFM11 AGE150_Specifications_20240209
Construction Specifications
Submitted to:
Mosaic Fertilizer, LLC
13830 Circa Crossing Drive
Lithia, Florida 33547
Submitted by:
WSP USA Inc.
5411 Skycenter Drive, Suite 650, Tampa, Florida, USA 33607
+1 863 255-0071
21471829-016-SPC-0
February 9, 2024
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
Table of Contents February 9, 2024
Table of Contents
Section Title Revision Date
ii
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 1 Statement of Work February 9, 2024
PART 1 GENERAL
1.1 Scope
A. Primary Project Components
1. SFM-11 Clay Settling Area (CSA): above and below grade earthen impoundment system
for storage of waste clay slurry generated from the ore beneficiation process. The CSA
will be enclosed by approximately 13,200 lineal feet of an above grade perimeter earthen
dam that will impound a total interior area of approximately 350 acres at a maximum
pond elevation of +145 feet (NGVD29).
2. Above Grade Embankment (AGE): earthen embankment constructed above the
preconstruction surrounding grades following the interior embankment foundation
preparation (previously constructed as Base Out Grading). The AGE will include
designated layers or zones with varying material and placement requirements.
3. Spillway Decant Tower and Discharge Pipes (SDT): Steel and concrete structures
allowing control and release of clarified (decanted) process water from the pond interior.
4. Hydraulic Return Water Ditch (HRWD): Earthen embankment transferring clarified
(decanted) process water from the CSA to the existing SFM-9 HRWD.
5. Foundation Drainage Zone (FDZ): The subgrade material beneath the Sand Tailings
Blanket Drain and above the Improved Foundation Zone installed for improved drainage
at the base of the AGE.
6. Sand Tailings Blanket Drain (STBD): pore water drainage collection layer embedded in
the core and along the toe of the AGE to collect and discharge seepage water.
7. Seepage Collection and Surface Water Drains: solid and perforated collection and
conveyances pipe systems installed at regular intervals along the surface water collection
and drainage ditches and along designated sections of STBD for seepage pressure relief.
8. Toe Access Road: earthen embankment forming the perimeter limits of the CSA,
providing access for inspection and maintenance.
9. Surface Water Ditch: perimeter swale along the toe of the embankment for collection,
transfer and discharge of surface water run-off from the CSA exterior slopes and
seepage flow from the STBD.
10. Emergency Diversion and Containment System (ECDS): Earthen embankment providing
containment from a potential dam breach at the spillway towers, directing breach flow
around SFM-9 into SFM-10 mine pit area.
11. SFM-9 East Slope Buttress: Earthen slope buttress placed along the SFM-9 East Slope
to provide an embankment slope drainage system and improved slope stability during the
various stages of filling of SFM-11 CSA.
12. SFM-9 Toe Buffer: 300 feet of buffer zone from the edge of toe road or toe of Buttress
where excavation in prohibited and unsuitable material may be disposed.
13. Ancillary Features: infrastructure exterior to the embankment supporting operations of the
1-1
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 1 Statement of Work February 9, 2024
1.3 Definitions
A. “Contract” is defined as the document executed by the Owner or its authorized
representative(s)/agent(s) with the Contractor to complete specified portions of the Work.
B. “Contractor” is defined as the party(s) that has executed the contract agreement for the Work
with the Owner or its authorized representative(s)/agent(s).
C. “Drawings” are defined as the construction plan set for the SFM-11 Clay Settling Area Above
Grade Embankment furnished by the Owner, Engineer, or others that apply to the Work.
D. “Engineer” or “Engineer of Record (EOR)” is defined as the consultant or engineering company
responsible for the detailed design or any of its authorized representative(s)/agent(s).
E. “Modifications” are defined as changes made to the Specifications or the Drawings that are
approved by Owner and Engineer in writing, after the Specifications and Drawings have been
issued for construction. They also refer to changes to design elements in the field to account
for unforeseen conditions.
F. “Owner” is defined as Mosaic Fertilizer, LLC (Mosaic) or any of its authorized
representative(s)/agent(s).
G. “Site” is defined as the SFM-11 Clay Settling Area Above Grade Embankment (AGE) project
limits where the Work is to be completed as detailed on the Drawings.
H. “Specifications” are defined as the documents, all supplemental addenda, and any
1-2
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 1 Statement of Work February 9, 2024
modifications furnished by the Owner, the Engineer, or others that apply to the Work.
I. “Work” is defined as the entire completed construction of the various separately identifiable
parts thereof required to be furnished as shown on the Drawings and as described in the
Specifications and Contract Documents.
1.4 Submittals
A. The Owner shall provide to the Contractor prior to the start of the Work, the Drawings and
Specifications and associated electronic data files. At a minimum, an onsite superintendent of
the Contractor shall maintain one set of Drawings and Specifications during the construction.
B. The Contractor shall submit a schedule to the Owner and the Engineer with the bid documents.
The work schedule shall include all aspects of the scope of work described in these
Specifications and included in the Drawings. The work schedule shall be updated thereafter,
and through the completion of the scope of work, on a monthly basis.
C. The Contractor shall provide an Environmental Protection Plan (EPP) to the Owner for the work
at least 4 weeks prior to construction for approval. The EPP shall include a description of
measures and equipment required to protect or mitigate impacts to surrounding air, soil, water,
wildlife and general public.
D. The Contractor shall provide a Temporary Works Plan (TWP) to the Owner with the bid
documents. The TWP shall include proposed equipment and material staging areas, site
access and haul roads, unsuitable material handling and disposal, and borrow and excavation
management plans.
E. The Contractor shall provide an Excavation Dewatering Plan (EDP) to the Owner with the bid
documents. The EDP shall include proposed dewatering equipment, projected flow rates,
discharge locations and water quality improvement measures. Additional EDPs shall be
developed by the Contractor for specific areas of the site designated by the Engineer, including
the SFM-11 North and South Embankment Tie-ins to the SFM-9 East Slope. The EDPs will
require approval by the Owner and Engineer.
F. The Engineer shall supply the Owner and Contractor with a Construction Quality Control and
Assurance Plan (CQAP) for the work at least 4 weeks prior to construction for approval. The
QCAP shall detail the minimum responsibilities and roles of the Contractor and the Engineer for
performance of quality control and assurance testing and inspection.
G. The Contractor shall supply a site-specific Health and Safety Plan (HASP) at least 4 weeks
prior to construction for approval. The HASP shall detail the organization and responsibility of
nominated safety personnel, site and job-specific safety hazards and associated mitigation
measures, and procedures for incident and emergency management.
H. Throughout the construction period, the Contractor shall maintain a record of submittals,
request for approvals and request for changes, including submittal dates, responses, action
items, responsible parties and approvals. The Contractor shall provide the record to the Owner
and Engineer during regularly scheduled project meetings.
I. Throughout the construction period, the Contractor shall submit survey data for verification of
progress, pay items and as-built record of constructed grades.
J. Throughout the construction period, the Contractor shall maintain a record of all changes on
1-3
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 1 Statement of Work February 9, 2024
the Drawings during construction. All changes and the Contractor’s field construction notes
shall be neatly and legibly prepared. The Contractor shall submit two copies of the notes and
redline-marked Drawings to the Owner and the Engineer. All pertinent documentation of field
points of the survey shall be recorded in accordance with the site coordinate system and
provided in AUTOCAD release 2022 or DXF file. Such information will be used by the Engineer
to prepare As-Built Drawings for the Owner.
K. Throughout the construction period, the Contractor shall maintain a record of submittals,
request for approvals and request for changes, including submittal dates, responses, action
items, responsible parties and approvals. The Contractor shall provide the record to the Owner
and Engineer during regularly scheduled project meetings.
PART 3 EXECUTION
3.1 Environmental Protection
A. The Contractor shall comply with all applicable rules and regulations set forth by regulatory
agencies including, but not necessarily limited to, the following:
1. Environmental Protection Agency (EPA)
2. Hardee County
3. Florida Department of Environmental Protection (FDEP)
4. Southwest Florida Water Management District (SWFWMD)
5. US Army Corps of Engineers (USACE)
B. The Contractor shall provide and maintain during the life of the contract, environmental
protection as defined herein. The Contractor shall provide environmental protective measures
as required for control of pollution that develops during normal construction practice and
provide environmental protective measures required to correct conditions that develop during
construction associated with the project. The Contract shall comply with all federal, state, and
local regulations pertaining to water, air, and noise pollution and report any environmental
event on-site.
1-4
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 1 Statement of Work February 9, 2024
1-5
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 1 Statement of Work February 9, 2024
requirements.
E. Oily Substances: The Contractor shall take whatever measures necessary to prevent oily or
other potentially hazardous substances from entering the ground, drainage areas, or local
bodies of water. All temporary fuel oil, petroleum, or liquid chemical storage tanks shall be
protected with a temporary earth berm of sufficient size and strength to contain the contents of
the tanks in the event of content leakage or spillage. If any spill occurs, the Contractor will
immediately notify the Owner and will be responsible for all cleanup expenses.
F. Fish and Wildlife Resources: The Contractor shall take necessary steps as required to prevent
the disturbance of fish and wildlife. The Contractor shall not alter water flows or otherwise
significantly disturb native habitats adjacent to the project area which are critical to fish and
wildlife except as approved by the Owner. The Contractor shall be required to complete Mosaic
Fertilizer, LLC’s Endangered Species and Wildlife Training Class.
G. Protection of Erodible Soils: All earthworks brought to a final grade shall be immediately
finished as indicated or specified. The Contractor shall protect slopes upon completion of
grading. Grassing of the earthwork slopes will be completed by the Contractor.
1-6
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 1 Statement of Work February 9, 2024
quality and/or condition of work before subsequent work by the Contractor can take
place. For these cases, the following general procedures will be used:
► The Contractor will notify the CQA Manager in writing of the area or work
requiring approval.
► The CQA Manager will perform all necessary inspections and tests, in such
a manner that will cause the least delay to the work.
► The CQA Manager will inform the Engineer and Owner of the test results, if
required, in writing on the “Work Activity Inspection Form.” The written
approval will contain a clear description and plan of the work approved. If the
work is rejected, the reasons for doing so will be clearly documented and
communicated.
► The Contractor will perform any tasks required to bring the work within the
required testing limits as defined by the Specifications and approved by the
CQA Manager and/or Engineer. The Contractor will notify the CQA Manager
that re-inspection or testing is required. This procedure will continue until the
work meets the required specification.
► The CQA Manager will prepare a weekly & monthly report summarizing work
inspected, tests performed, and other relevant items. The CQA Manager may
supplement this report with other items, drawings, figures, and tables as are
necessary to clearly present the work performed and planned.
C. The Quality Control Assurance Plan should include:
1. Surveying and Grade Control: The Owner’s Surveyor will check lines and grades, at his
discretion, and will verify all quantity measurements and calculations. The Contractor’s
surveying shall comply with the vertical and horizontal tolerances in the Specifications
and shall be conducted under the direct supervision of a Florida Registered Land
Surveyor.
2. Training: Qualified personnel are required to perform the quality assurance/quality control
(QA/QC) testing for soils on the project. The technicians must be trained to perform the
required tests and inspections in accordance with the ASTM procedures or other
applicable standards. The Engineer will approve the qualifications of the technicians prior
to being allowed to perform test and inspection work during the project.
3. Sampling Procedures: Standard procedures for sampling include proper sample
identification, location, collection, custody, handling and documentation.
4. Test Result Records: A record of all tests performed shall be maintained by the CQA
Manager. Individual test data and results will be recorded on a standard form applicable
to the test being performed. The CQA Manager will provide the Owner and Contractor
with copies of all test records performed and submitted by QA/QC personnel, and all
other parties performing tests related to the construction activities.
5. Corrections to Documentation: Entries on all documents are to be in indelible ink. If an
error is made on a document assigned to one individual, that individual may make
corrections by crossing a single line through the error and entering the correct
information.
1-7
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 1 Statement of Work February 9, 2024
1-8
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 2 Mobilization and Demobilization February 9, 2024
PART 1 GENERAL
1.1 Scope
A. Mobilization and Demobilization shall include and cover all work for and in connection with; the
assembly and transportation to the site of all construction equipment, labor, superintendence,
materials and supplies and their removal from the site upon completion of construction;
preparation of equipment storage area; equipment maintenance facilities; office facilities;
sanitation facilities; construction of temporary construction roads; and all clean-up of the area,
construction plant, equipment storage and operation areas – all to finished grades shown on
the Drawings, or as specified by the Owner.
2-1
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 2 Mobilization and Demobilization February 9, 2024
PART 2 PRODUCTS
2.1 Temporary Construction Roads
A. Temporary construction roads for access to borrow areas and other purposes required for the
construction operations shall be constructed in locations approved or specified by the Owner or
any of its authorized representative(s)/agent(s). Construction of roads outside the construction
limits requires approval of the Owner prior to road construction. Indiscriminate construction of
roads and travel by the Contractor’s vehicles will not be permitted in areas outside the limits of
the area.
PART 3 EXECUTION
3.1 Clean-up
A. The Contractor shall maintain the site in an orderly workmanlike manner. Accumulated debris
and trash shall be disposed of off-site periodically or as specified by the Owner. Waste oil,
antifreeze, fuels, grease, or any other hazardous materials shall be disposed of off-site in
accordance with applicable regulations and shall not be dumped on the ground. The Contractor
shall furnish proper records documenting the disposition of any such waste oils, antifreeze,
fuels, grease, or other hazardous materials to the Owner.
B. After completion of construction, excess materials, debris, and other foreign materials shall be
removed from the construction site and temporary construction areas and shall be properly
disposed of off-site by the Contractor in an approved site in compliance with appropriate laws
2-2
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 2 Mobilization and Demobilization February 9, 2024
and regulations.
C. Clean-up of temporary construction roads, regardless of location, shall include smoothing and
grading of the ground surface to eliminate ruts for erosion prevention, and trimming and
smoothing of eroded or caved slopes of cuts or embankment to stable conditions as specified
by the Engineer and/or Owner.
2-3
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 3 Site Preparation February 9, 2024
PART 1 GENERAL
1.1 Scope
A. Summary of Work: The Contractor shall furnish all labor, materials, and equipment necessary
for complete and proper site preparation within the areas shown on the Drawings and specified
herein and observe permit conditions.
B. Clearing shall include removal of surface debris associated with historical land use and removal
of large woody vegetation. The Owner will remove existing disused metal and HDPE
pipes, mechanical equipment and parts, concrete rubble, etc. within the footprint of the work
area prior to commencing construction. The Contractor is responsible for clearing of trees,
branches and stumps, etc. within the limits of the project, and any buried debris encountered
during the work. Clearing of the interior slopes and AGE foundation footprint will be completed
during Base Out construction and prior to AGE construction commencing. Clearing debris
generated during construction of the AGE shall be transported and disposed of within the
project area as designated by the Owner.
C. Stripping, grubbing, and/or raking of vegetated cover, roots, topsoil and other vegetative debris
from areas designated on the Drawings shall be completed prior to borrow or filling operations.
Stripped topsoil shall be transported and disposed within area(s) designated by the Owner or
stockpiled for re-use in erosion control (seeding & mulching surfaces).
D. Removal of unsuitable materials: Saturated soft to very soft clayey and/or organic soils, within
the project limits shall be removed through excavation or methods as agreed with the Owner
and Engineer.
E. Unsuitable materials and stripped topsoil shall be transported and disposed of or stored within
areas designated by the Owner or alternate areas agreed with the Engineer.
3-1
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 3 Site Preparation February 9, 2024
1.6 Responsibilities
A. The Owner will identify known utilities and infrastructure that shall remain in operation during
the Work. The Contractor shall not purposefully disrupt or disconnect any type of utility, electric
or irrigation service without first obtaining the written permission of the Owner. Requests for
disconnection must be in writing and received by the Owner at least seven calendar days prior
to the time of the requested interruption.
B. The Contractor shall take action within two hours and complete within forty-eight hours the
necessary steps to repair, replace, or restore all services to any utilities or other facilities, which
are disrupted due to Contractor operations.
C. Should utilities, structures, etc., be encountered that interfere with the Work; and are not shown
on the Drawings; the Contractor shall notify the Owner immediately.
D. The Contractor shall have all erosion and sediment control measures in place prior to
beginning any construction.
E. The Contractor shall construct and/or manage vegetation debris and unsuitable soil disposal
areas as designated on the Drawings. The Contractor shall operate and maintain the disposal
areas throughout the duration of the project to prevent the release of vegetation debris and
unsuitable soil to adjacent areas not approved by the Owner.
F. The Contractor shall ensure the safe passage of persons around areas of clearing and land
preparation. The Contractor shall conduct its operations to prevent injury to adjacent structures,
vegetation designated to remain, other facilities, and persons.
G. The Contractor will install all traffic control devices required for the project prior to beginning
any construction.
H. Any clearing and stripping beyond the limits shown on the Drawings, or as required by the
Engineer, shall be subject to the approval of the Owner.
I. All usable topsoil, as determined by the Owner, shall be properly stockpiled in locations shown
on the Drawings or approved by the Owner.
3-2
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 3 Site Preparation February 9, 2024
PART 3 EXECUTION
3.1 Clearing and Stripping
A. The Contractor shall strip within the limits of excavation, borrow areas, and ground that will
become the foundation of the dam and other earthwork (borrow areas). Stripping shall include
removal to the depth required of all vegetable matter, roots, debris, and other perishable or
objectionable materials that are unsuitable for the proper bonding of the compacted soils with
their foundations, the proper compacting of the fill materials, or that might be otherwise
objectionable as determined by the CQA Manager or Engineer. This work shall include
stripping and removal of organics, mud, soft sediment, and other material, which may flow or
undergo excessive consolidation under design loads.
B. Prior to any surface treatment on a stripped area, the CQA Manager, Engineer or their
representative shall be notified to inspect the stripped area and designate the method of
treatment required for continuance of the Work. A survey shall be taken of the area if necessary
to determine quantities and/or for verification of lift/layer thickness.
3.4 Disposal
A. All stripped materials shall be hauled to and disposed at the locations specified by the Owner.
The stripped materials shall not be stockpiled within the footprint of the SFM-11
embankment/return hydraulic ditch and/or over any proposed borrow material for use as fill
unless shown otherwise on the Drawings.
3-3
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
SECTION 4 EARTHWORKS
PART 1 GENERAL
1.1 Scope
A. Summary of Work: The Contractor shall furnish all labor, equipment, and materials for all
excavating, filling, embankment construction, backfilling, compacting, grading, and all related
items of earthwork necessary to complete the Work indicated or specified.
4-1
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
16. ASTM D 4318 – Test Method for Liquid Limit, Plastic Limit, and Plasticity Index of Soils.
17. ASTM D 4944 – Standard Test Method for Field Water (Moisture) Content of Soil by the
Calcium Carbide Gas Pressure Tester.
18. ASTM D 6938 – Standard Test Method for In-Place Density and Water Content of Soil
and Soil- Aggregate by Nuclear Methods (Shallow Depth).
B. Miscellaneous Project Data:
1. Subsurface soil boring logs and materials testing data are included with the Information
for Bidders Report.
1.3 Definitions
A. Excavation: The removal of all materials below stripped materials, within the defined limits of
excavation, as shown on the Drawings. Excavation will include non-competent or unsuitable
materials for the proper bonding of the compacted embankment soils for future placement on
top. This work shall include excavation of organics, mud, soft sediment, and other material,
which may flow or undergo excessive consolidation under design loads.
B. Compacted Embankment and Dozer Compacted Fill: The Cast Overburden soil excavated from
within the designated borrow areas as shown in the Drawings or otherwise authorized by the
Owner that will be placed and compacted within the above grade section of the embankment
dam alignment, the HRWD and ECDS embankments and beneath access roads and in other
designated areas as shown on the Drawings in accordance with the material and placement
specifications for each component.
C. Cast Overburden: mixed clay/silt/sand soils that were removed from above the matrix soils
during mining operations and deposited (dragline cast) in spoil piles into the open mine pit. The
Cast Overburden soil shall be utilized as Embankment Fill.
D. Sand Tailings: A relatively clean, fine sand, which has been removed from the matrix soil during
the beneficiation process and hydraulically placed within the mine pit and perimeter areas. In
specific locations (access/utility corridors) the Sand Tailings was subsequently dozer graded. It
will be used as compacted fill for the construction of the Sand Tailings Blanket Drain and other
drainage features.
E. Sand Tailings Blanket Drain: A blanket drain constructed of relative clean Sand Tailings (<5%
fines content). The blanket drain will consist of a drainage collection layer embedded within the
downstream slope of the AGE to collect and discharge seepage water.
F. Foundation Drainage Zone: The subgrade material beneath the Sand Tailings Blanket Drain
and above the Improved Foundation Zone. The Foundation Drainage Zone will be constructed
of a compacted fill that consists of cast overburden with a specified range of fines. The
Foundation Drainage Zone material may be generated through blending of Sand Tailings and
Cast Overburdens to create a suitable material. The blended soils shall meet the required
material specifications for Foundation Drainage Zone.
G. Unmined Matrix: Typically, clayey sand to sandy clay soils containing sand to pebble-sized
phosphate underlying the overburden soils near the base of the mine pit. This material may be
used as Compacted Embankment Fill provided it meets material property specifications.
4-2
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
H. Bedclay Complex: Typically, very stiff to hard sandy clays and silts with limerock lenses
underlying the site. This stratum shall not be excavated for reuse as fill material unless
approved by the Engineer.
I. Drain Rock: Coarse aggregate that may be processed from gravels, granites, limestone,
dolomite, sandstones, or other naturally occurring hard, sound, durable materials meeting the
material requirements of these Specifications. Drain Rock shall be imported from a certified
supplier.
J. Riprap: Rubble consisting of hard, durable broken stone or broken concrete meeting the
material requirements of these Specifications. Riprap shall be imported from a certified
supplier.
1.4 Submittals
A. Samples:
1. Submit samples and sources of off-site aggregate proposed for use in the Work.
B. Miscellaneous Submittals:
1. Test reports for imported materials
2. Delivery tickets
3. Equipment to be used for excavation, transportation, placement, and compaction of fill.
Submittal to include equipment specifications, part of the Work where equipment is to be
used, and operator qualifications.
C. Proposed methods and equipment to be utilized in the Drain Rock layer and Sand Tailings
Blanket Drain construction, particularly detailing any haulage vehicle traffic requirements, shall
be submitted to the CQA Manager or for review prior to commencement of the Work.
D. The Contractor shall submit all required information at least thirty (30) days in advance of
delivery of any materials to the site.
E. Approval by the Engineer of Contractor submittals shall not alleviate the Contractor’s
responsibilities for completing the work as specified.
F. The Engineer shall prepare a detailed CQA Plan to ensure the Contractor’s operations result in
soils for earthwork meeting the specification requirements.
4-3
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
shortfalls due to volume miscalculations or required rework resulting from not meeting material
or placement specifications.
D. The Contractor shall construct fills and backfills to the lines, grades, and cross sections shown
on the Drawings.
E. The Contractor shall place only fill materials obtained from excavations required for the dam
and structure works, and from on-site overburden spoil and borrow area, that meet these
Specifications.
F. The Contractor must use materials free from organics and vegetation including but not limited
to stumps, trees, leaves, roots, rubbish, palmettos, and grass.
G. The Contractor must remove/rework materials not meeting requirements of these
Specifications, as required by the CQA Manager or Engineer, at no additional cost to the
Owner.
H. If the Contractor places fill outside the lines and grades shown on the Drawings or specified by
the Engineer, the Contractor shall remove the excessive fill, as required by the CQA Manager
or Engineer, at no additional cost to the Owner.
I. The Contractor shall excavate test pits with a backhoe (or similar equipment) upon request of
the CQA Manager or Engineer or his/her representative to confirm that unsuitable materials
have been displaced or removed and replaced by the Contractor at no additional cost to the
Owner.
4-4
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
2.2 Materials
A. Compacted Embankment and Dozer Compacted Fill:
1. Compacted Embankment and Dozer Compacted Fill shall be free from trash, clods and
rock pieces greater than 6 inches in maximum dimension.
2. Compacted Embankment and Dozer Compacted Fill shall consist of a blended
combination of Cast Overburden, Sand Tailings, and Unmined Matrix classified as SP-
4-5
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
4-6
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
F. Clay Plug:
1. The Clay Plug Fill shall be clayey sand or sandy clay (SC or CL) material with at least
35% passing the No. 200 sieve as determined in accordance with ASTM D 1140.
2. The Clay Plug Fill shall be and free of clods, gravel and debris and have less than 2%
organic content as determined in accordance with ASTM D 2974.
G. Riprap:
1. Riprap shall be composed of rubble (consisting of broken stone or broken concrete). The
riprap shall be sound, hard, durable, angular, free of friable particles, organic matter, and
other substances, which may possess undesirable characteristics.
2. The rubble material shall consist of a broken stone or concrete with a bulk specific gravity
of at least 1.9.
3. The riprap size shall comply with FDOT Standard Specification Section 530 for the
specified Rubble (Ditch Lining) and shall have an angular shape.
PART 3 EXECUTION
3.1 Protection
A. Protect existing surface and subsurface features on-site and adjacent to site as follows:
1. Provide barricades, coverings, or other types of protection necessary to prevent damage
to existing items indicated to remain in place. This includes, but is not limited to power
transmission poles, guide wires, and power lines; monitoring wells and staff gauges;
irrigation and drainage structures; and associated equipment.
2. Protect and maintain benchmarks, monuments or other established reference points and
property corners. If disturbed or destroyed, the Contractor shall replace them at his/her
own expense to the full satisfaction of the Owner.
3. Verify the location of utilities. The omission or inclusion of utility items does not constitute
non-existence or definite location. Secure and examine local utility records for location
data.
4-7
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
a. Take necessary precautions to protect existing utilities from damage due to any
construction activity.
b. Repair damages to utility items at Contractor’s own expense.
c. In case of damage, notify the Owner at once so that the required protective
measures may be taken.
4. Do not damage structures not indicated to be removed. Any item known, unknown, or not
properly located that is inadvertently damaged shall be repaired to its original condition.
All repairs shall be made and paid for by the Contractor.
5. Provide full access to public and private premises, fire hydrants, street crossings, and
other points as designated by the Owner or Engineer to prevent interruption of travel.
6. Maintain stockpiles and excavations in such a manner as to prevent inconvenience or
damage to structures on-site or on adjoining property.
7. Avoid surcharge or excavation procedures, which can result in heaving, caving, or slides.
B. Salvageable Items: Carefully remove items to be salvaged, and store as directed by the CQA
Manager or Engineer.
C. Legally dispose of all non-combustible waste materials off site. Combustible material stockpiles
may be burned in accordance with applicable regulations.
4-8
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
4-9
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
Supplemental water shall be added to the material by uniform sprinkling on the fill and
shall be mixed by disking and harrowing. Excavated materials which are too wet for
immediate use when excavated shall be moisture conditioned to near optimum for
compaction before use as compacted fill.
7. Pneumatic-tired equipment shall not traffic the top of the Blanket Drain material until 12
inches of Embankment Fill have been placed over the drain material.
B. Placement – Compacted Embankment and Foundation Drainage Zone Fill:
1. The Compacted Embankment and Foundation Drainage Zone Fill used in the compacted
AGE sections shall be mixed such that the soil lift will be free from lenses, pockets, or
layers of material differing in texture, gradation, or moisture from the surrounding
material.
2. The compacted surface of each lift shall be scarified by light disking, sheeps-foot roller or
by any other method approved by the CQA Manager or Engineer before the succeeding
layer is placed.
3. Each lift of fill material shall be spread and leveled by graders or dozers to the maximum
specified loose lift thickness, prior to processing and compaction.
4. The Contractor shall not stockpile fill on the embankment alignment prior to spreading to
the specified loose lift thickness.
5. The Contractor shall place the Embankment and Foundation Drainage Zone Fill in loose
lifts no greater than 12-inches thick for machine-placed fill and loose lifts 6-inches thick
for hand-placed fill. The fill lift thickness shall not be greater than the vertical reach of the
soil mixing equipment.
6. Lift thickness shall be controlled by the Contractor by temporary grade stakes.
7. The entire surface of any section of the embankment under construction shall be
maintained in such condition that construction equipment can travel on any part of any
one section. Ruts in the surface of any layer shall be removed by scarifying before
placing and compacting additional material.
8. Where the ground surface is steeper than 4H:1V, each new lift of soil shall be benched
into the existing surface prior to compaction of the new lift of fill. The bench shall be a
minimum of 4 feet wide and a maximum of 1 foot high. Compact the entire surface of the
fill and bench to achieve a bond between the new fill and the existing surface.
9. When placing Compacted Embankment Fill, the more clayey/silty materials with fines
contents greater than 20% shall be placed upstream of the embankment centerline.
Sandy embankment fill with fines content less than 20% shall be placed downstream of
the centerline. The Compacted Embankment Fill shall generally consist of uniform
materials and shall not include lenses or layers of sands with lower fines content or vary
by more than 10% fines from lift to lift.
10. The outer sections of the Compacted Embankment Fill shall be compacted to the lines
and grade shown in the Drawings and in accordance with these specifications. The fill
lifts must be initially over-built (wide) in order to facilitate safe trafficking by scraper pans,
trucks, rollers and dozers performing compaction near the edge of the fill lifts. The over-
built section shall be cut back to the specified lines and grades, taking care not to leave
4-10
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
4-11
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
by any other method approved by the Engineer before the succeeding layer is placed.
3. Each lift of fill material shall be spread and leveled by graders or dozers to the maximum
specified loose lift thickness, prior to processing and compaction.
4. The Contractor shall place the fill in loose lifts no greater than 12-inches thick (for
machine-placed fill and no greater than 6-inches thick for hand-placed fill. The fill lift
thickness shall not be greater than the vertical reach of the soil mixing equipment. Lift
thickness shall be controlled by the Contractor by temporary grade stakes.
5. The entire surface of any section under construction shall be maintained in such condition
that construction equipment can travel on any part of any one section. Ruts in the surface
of any layer shall be removed by scarifying before placing and compacting additional
material.
E. Placement – Blanket and Diaphragm/Filter Drain Fill:
1. Sand Tailings will be used to construct the Blanket and Diaphragm/Filter Drain Fill along
the base of the downstream sections of the perimeter embankments, along the spillway
discharge pipes (diaphragm and filter drain) through the embankment and at designated
drainage or bedding zones throughout the project area.
2. Blanket Drain Fill used within the base of the downstream portion of the perimeter dam
shall be placed in 24-inch maximum loose lifts and leveled by a dozer to avoid over-
compaction.
3. Diaphragm and Filter Drain Fill will be used within the base of the downstream portion of
the perimeter dam at the spillway embankment at the spillway discharges. The Drain Fill
shall be placed in 24-inch maximum loose lifts and leveled by a dozer to avoid over-
compaction.
4. The Contractor shall not stockpile Drain Fill on the embankment alignment prior to
spreading to the specified loose lift thickness.
5. Scraper pans and dump trucks shall not be allowed to traffic over the exposed Drain Fill
surface. The first lift of the Embankment Fill placed above the Drain Fill shall be dumped
next to the exposed sand and pushed out onto the Drain Fill surface with a dozer.
6. The Contractor shall be responsible to avoid any contamination of the Blanket and
Diaphragm/Filter Drain Fill with fines from wind-blown soils or stormwater runoff. The
Drain Fill shall be covered as soon as practical with the dam embankment fill to protect it
from becoming contaminated, displaced, or damaged in any way that impairs its
effectiveness.
7. One foot of Embankment Fill or other approved fill shall be dozer-spread/placed over the
Blanket and Diaphragm/Filter Drain Fill prior to trafficking by pans and trucks.
8. Lift thickness shall be controlled by the Contractor by temporary grade stakes.
F. Placement – Drain Rock:
1. The Drain Rock used in the Seepage Collection Drains and Surface Water Conveyances
shall be dumped and spread by a small crawler-type tractor or blade.
2. The Contractor shall not stockpile Drain Rock on the drainage component alignment prior
4-12
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
4-13
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
4-14
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
3. The Contractor shall re-grade the inside and outside dam slopes after any damage that
occurs due to surface erosion. Any erosion deeper than 18 inches shall be over-
excavated and backfilled with fill meeting the specified moisture and density criteria.
4-15
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
K. Nuclear methods (ASTM D 6938) or Density of soil in Place by the Drive-Cylinder (ASTM
D2937) may be used for the determination of in-place densities. If the nuclear method is used,
one drive cylinder test shall be performed for every 10 nuclear method tests. The density
correlations between the two test methods shall be submitted with the test results. Pending
satisfactory correlation results, drive cylinder testing may be performed at a lower frequency
with the Engineer’s approval.
L. Any single in-placed density test failing the specified compaction level or moisture content
criteria shall be classified as a failing test and the fill lift section material represented by the
failing test shall be re-processed by the Contractor.
M. The CQA Manager will prepare for the Engineer a report summarizing construction completed.
All test data will be tabulated and plotted, noting any reprocessing of failed material and
retesting.
4-16
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
Drain Rock Gradation C 117 / C 136 1 per type or new source provided
by the supplier
Blanket and Moisture D 2216 Every 10,000 CY, and 1 per type or
Diaphragm/Filter Drain Fines Content D 1140 new source
Fill Organic Content D 2974
B. The CQA Manager or Engineer may adjust the testing frequencies or methods dependent on
the consistency of the fill materials and the performance of the earthworks operations.
C. The CQA Manager will inspect the finished grade for each lift of fill and provide a Subgrade
Acceptance Form for the designated area. The Contractor shall notify the CQA Manager when
the subgrade area is ready for inspection.
D. The CQA Manager will collect and direct testing of fill samples in accordance with the methods
and frequencies noted above. The Contractor shall provide access to sampling locations.
Testing for compliance with specifications. Testing may take multiple days based on the testing
methods. The Contractor should make allowances for the testing durations in their schedule.
4-17
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 4 Earthworks February 9, 2024
4-18
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 5 Dewatering February 9, 2024
SECTION 5 DEWATERING
PART 1 GENERAL
1.1 Scope
A. This section specifies performance of dewatering required to lower and control surface water, pit
water, and groundwater levels from various parts of the work to permit excavation, backfill, and
construction to be performed in the dry. Control of surface water shall be considered as part of
the work under this specification. The work includes:
1. Designing, furnishing, installing, operating, and maintaining temporary impounding,
dewatering, and diversion systems,
2. Furnish, install, operate and maintain all necessary dewatering wells, pumps, piping
and other facilities and equipment,
3. Managing and disposing of water in accordance with project and state
requirements, and
4. Removing all such temporary works and equipment after they have served their
purposes.
1.4 Submittals
A. The Contractor shall identify the proposed locations and discharge quantities of discharge
points to the Owner’s mine water recirculation system.
B. The Contractor shall submit an Excavation Dewatering Plan (EDP) detailing the approach for
capture, control, and discharge of surface waters and groundwater resulting from dewatering.
The Plan shall address the following requirements of the dewatering program:
5-1
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 5 Dewatering February 9, 2024
1. Lower the water table within the base of the excavation to a minimum of 3 feet below
bottom of the excavation to permit work to be completed on a dry and stable subgrade.
2. Lower the water table along excavation slopes as necessary to provide a stable
excavation slope.
3. Relieve hydrostatic pressures in water-bearing strata below excavation to eliminate the
risk of uplift or other instabilities.
4. Prevent the loss of fines, quick condition, heaving, or softening of excavation subgrades.
5. Maintain the stability of sides and bottoms of excavations.
6. Collect and remove surface water.
7. Collect and remove leakage through the upstream cofferdams.
C. Submit EDP and associated Shop Drawings to the Engineer for review and approval. The Plan
and Drawings shall include at least the following items:
1. Dewatering system components and layout including drainage trench geometry, well
depths, well screen lengths, dewatering pump locations, pipe sizes and capacities,
grades, filter sand gradations, surface water control devices, valves, and water disposal
method and location.
2. Methods to seal leaks in temporary and permanent excavation support and protection
systems if used.
3. Methods to seal and/or control leakage through the temporary upstream cofferdams.
4. Primary and standby power system location and capacity.
5. Layout and depth of additional monitoring wells and piezometers (not included as part of
the geotechnical instrumentation plan shown on the Drawings) for system performance
measurement, if required.
6. A Detailed description of dewatering and monitoring system installation procedures, well
development procedures, and maintenance of equipment. The description shall include
how dewatering systems will be installed to ensure that each excavation stage is
performed in the dry.
7. Description of emergency procedures, including provisions for spare pumps and other
required equipment, emergency generators, and provisions for supervision of the
dewatering system.
8. Product Data: Submit data for each of the following:
a. Dewatering Pumps: Indicate sizes, capacities, priming method, and motor
characteristics.
b. Pumping equipment for control of surface water within excavations.
9. Design values, analyses, and calculations to support design.
10. Dewatering system removal and decommissioning procedures.
11. Closeout Submittals:
5-2
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 5 Dewatering February 9, 2024
► Closeout submittals shall follow the requirements in the Section Execution and
Closeout Requirements.
► Provide an Excavation Dewatering Closeout Report summarizing the
decommissioning of the dewatering systems.
► Project Record Documents: Record actual locations and depths of grouted
wells and grouted piping abandoned in place.
1.5 Qualifications
A. The EDP shall be prepared under the direct supervision of an individual experienced in the
design of these systems. All shop drawings and calculations included in the EDP shall be
signed and sealed by a Professional Engineer licensed in the State of Florida.
PART 2 PRODUCTS
2.1 General
A. The Contractor shall be responsible for all costs associated with delays, permitting activities,
fees, penalties, spills, clean-up, malfunctions, or failures of any of the equipment associated
with the dewatering program.
5-3
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 5 Dewatering February 9, 2024
PART 3 EXECUTION
3.1 Preparation
A. Perform additional borings and investigations to supplement existing subsurface investigations
as required to complete the dewatering system design.
B. Existing groundwater levels throughout the SFM-11 project area are presented in the
Geotechnical Data Report. Groundwater levels around the site perimeter shall be maintained
above minimum levels in accordance with Mosaic’s facility operating permits.
C. Mosaic will provide a dewatering transfer system to remove water from the pit to designated
areas for use by the Contractor. The Contractor is responsible for installing and operating pit
dewatering systems to deliver to Mosaic’s transfer point.
3.2 Protection
A. Removal of water from excavations shall be accomplished in such a manner that erosion and
the transmission of sediment and other pollutants are minimized.
B. Maintain accessibility to all components of the dewatering system continuously during
construction operations.
C. Protection of all dewatering equipment and accessories from damage due to construction
activities shall be the sole responsibility of the Contractor.
3.4 Installation
A. Dewatering System
1. The dewatering system shall be installed to prevent potential seepage within the
excavation area from surrounding perimeter grades and from the base of the pit.
2. The dewatering system shall be adequate to pre-drain the water-bearing strata above and
below the bottom of structure foundations, utilities, and excavations to a minimum depth
5-4
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 5 Dewatering February 9, 2024
3.5 Operation
A. Prior to any excavation below the surface water, pit water, and groundwater levels, place the
dewatering system into operation to lower the groundwater table as required. The dewatering
system shall and operate continuously 24 hours a day, 7 days a week, until the work is
complete.
B. Dewatering will be required by the Contractor within the pond interior for management of mine
cuts, ponds and borrow pits, excavations or removal of unsuitable soils, and for placement of fill
within the project limits.
C. Surface water levels in the mine pit area within the project limits will be maintained at or below
Elevation of +80 feet (NGVD29) by the Owner within 30 days of receiving Notice to Proceed
and continuing the duration of the project or subsequent changes agreed with the Contractor.
Dewatering below an Elevation +75 feet will be required to prepare borrow sources and
foundation areas within the mine pit area during construction.
5-5
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 5 Dewatering February 9, 2024
D. Dewatering of mine cuts in the vicinity of available overburden soil spoil piles shall be
completed as required to obtain the necessary quantity of borrow soils.
E. Operate the dewatering system continuously until backfilling is complete.
F. Provide supervision of the dewatering system by personnel skilled in operation, maintenance,
and replacement of system components.
G. Conduct daily observation of the dewatering system and monitoring systems. Make required
repairs and perform scheduled maintenance.
H. Fill fuel tanks before the fuel level in the tank falls below 25 percent capacity.
I. Start emergency generators at least twice each week to check operating conditions.
J. When the dewatering system cannot control water within excavation as required by this
specification, notify CQA Manager or Engineer and stop excavation work.
1. Supplement or modify the dewatering system and provide other remedial measures to
control water within the excavation.
2. Demonstrate dewatering system operation complies with performance requirements
before resuming excavation operations.
K. Modify dewatering and surface water control systems when operation causes or threatens to
cause damage to new construction, existing site improvements, or potentially impact the safety
of workers and equipment.
L. Correct unanticipated pressure conditions affecting dewatering system performance.
M. Do not discontinue dewatering operations without CQA Manager or Engineer’s approval,
except in response to an immediate and dire emergency. In case of such as emergency, the
CQA Manager or Engineer shall be notified as soon as practicable.
5-6
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 5 Dewatering February 9, 2024
5-7
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 6 Seepage Collection Drain February 9, 2024
PART 1 GENERAL
1.1 Scope
A. This section covers the Seepage Collection Drain(s) and Surface Water Conveyance Pipes
installed at the designated locations as shown on the Drawings.
6-1
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 6 Seepage Collection Drain February 9, 2024
6-2
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 6 Seepage Collection Drain February 9, 2024
PART 2 PRODUCTS
2.1 Materials
A. Pipe
1. 6- to 12-inch Seepage Collection Drain and Surface Water Conveyance pipes shall
consist of corrugated single wall HDPE drainage pipe. The pipe shall be Type C or CP
shall meet AASHTO M252 pipe less than 10 inches in diameter and AASHTO M294 for
pipe greater than 10 inches in diameter.
2. Where perforations are required per Plan, perforated pipe shall be perforated at 120o
spacings around the circumference of the pipe cross-section with 0.375-inch diameter
perforations. Perforations shall be spaced along the length of the pipe appropriately to
provide an inflow capacity of 0.04 gpm per linear foot of pipe. All perforations shall be
cleanly cut to the size, orientation, and spacing specified.
3. All pipe connections, including joints and fittings, shall meet or exceed the soil-tight
requirements of AASHTO M252 or M294 and the pipe manufacturer’s recommendations.
The Contractor shall supply the Engineer with all information of joining method for his/her
evaluation. Only jointing methods acceptable to the Engineer will be permitted.
4. The pipe and fittings shall be homogeneous throughout and essentially uniform in color,
opacity, and density. The pipe walls shall be free of cracks, holes, blisters, voids, foreign
inclusions, and any other visible defects that may affect serviceability.
B. Corrugated Metal Pipe (SFM-11 HRWD Culverts)
1. Corrugated Metal Pipe shall be fabricated with helical corrugations that fully develop the
strength of the metal. Fabrication of the pipe shall be in full compliance with AASHTO
M36-03 (R2011). All Fabrication shall occur within the United States.
2. The asphalt coating shall conform to the applicable requirement of coating, paving and
lining for AASHTO M190.
3. The corrugated pipe shall be 8-gauge, made from zinc-coated steel sheets, which shall
conform, to ASTM A 414/A 414M-10. Corrugation shall be 3 inches by 1 inch.
4. The corrugated pipe shall be connected using coupling bands. Coupling bands and
fasteners shall be made of the same base metal and coatings as the corrugated metal
pipe.
5. The pipe shall consist of 40-foot sections and portions thereof of 96-inch galvanized,
corrugated, asphalt-coated, 8-gauge steel culvert pipes.
6. The corrugations shall form smooth continuous curves and tangents. The radius of
curvature of any corrugation profile shall be at least one-half the depth of the
corrugations.
7. The average inside diameter of circular pipe shall not vary more than one (1) percent or
1/2-inch, whichever is greater; from the nominal diameter when measured on the inside
crest of the corrugation.
8. Corrugation depth shall conform to the applicable requirements of paragraph 13.1 of
ASTM A 414 when measured on the outside.
6-3
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 6 Seepage Collection Drain February 9, 2024
9. Pipe section ends shall be rerolled with annular corrugations providing male and female
ends.
10. Any sections or units of the specified metal on which the coating has been damaged or
burned by flame cutting and/or arc welding shall be cleaned with a wire brush, painted
with two (2) coats of zinc oxide paint, and then recoated with bituminous mastic.
C. Pipe Bedding Material
1. Seepage collection Pipe Bedding shall consist of Drain Rock as specified in Section 4.
2. Surface water piping Pipe Bedding shall consist of Embankment Fill as specified in
Section
D. Backfill Material
1. Seepage collection Backfill Material shall consist of Drain Rock as specified in Section 4.
2. Surface water piping Backfill Material shall consist of Embankment Fill as specified in
Section 4
E. Geotextile
1. The Geotextile shall be a non-woven geotextile. The geotextile shall be made from
polyolefin or polyesters with the elongation less than 50 percent. It shall comply with the
following properties determined according to AASHTO M288. The strength values shown
are for the weaker principal direction.
► Mass per Unit Area: 10 oz/sy.
► Equal or exceed the AASHTO M288, Class 1.
► Apparent Opening Size: No. 100 sieve, maximum.
► Permittivity: 0.5 per second, minimum.
► Puncture Strength: 80 pounds, minimum.
► Grab Tensile Strength: 200 pounds, minimum.
► Sewn Seam Strength: 180 pounds, minimum.
2. The thread for the sewn seams shall consist of high-strength polyester, nylon, or other
approved material with comparable chemical compatibility as the geotextile. It shall have
a contrasting color to the geotextile.
F. Concrete Inlet
1. The Concrete Inlet at the seepage collection pipes shall be constructed of cast in place
concrete and placed in accordance with the Drawings and Section 7 of these
Specifications.
6-4
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 6 Seepage Collection Drain February 9, 2024
PART 3 EXECUTION
3.1 Earthwork
A. Excavating, trenching, and backfilling are specified in Section 4.
6-5
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 6 Seepage Collection Drain February 9, 2024
B. Install the corrugated HDPE drainpipe pipe beginning at low points of the system, to the grades
and alignment indicated in the Drawings. The pipe shall be bedded with full bearing on the
Drain Rock. Install gaskets, seals, sleeves, and couplings according to the manufacturer’s
written instructions and other requirements indicated.
C. Install piping pitched down in the direction of flow at a minimum slope of 0.5 percent.
D. Use increasers, reducers, and couplings made for different sizes or materials of pipes and
fittings being connected. Reduction of pipe size in the direction of flow is prohibited.
E. Install corrugated HDPE drainage pipe according to ASTM D 2321 and the manufacturers
installation guidelines.
F. Join corrugated HDPE drainage pipe and fittings according to the manufacturer’s installation
guidelines.
6-6
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 6 Seepage Collection Drain February 9, 2024
6-7
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
SECTION 7 CONCRETE
PART 1 GENERAL
1.1 Scope
A. Concrete spillway riser structures footings, discharge culverts protection slabs, surface water
inlet headwalls, concrete cradle, grout-filled filter point fabric erosion and similar structures shall
be constructed in conformity with the Drawings and Specifications. Concrete and reinforcing
steel for use in work constructed under this specification. Conformance tests shall be
performed with the requirements of this specification.
7-1
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
17. ASTM C 494/C 494 – Standard Specification for Chemical Admixtures for Concrete.
18. ASTM C618 – Standard Specification for Coal Fly Ash and Raw or Calcined Natural
Pozzolan for Use in Concrete.
19. ASTM C685/C685M – Standard Specification for Concrete Made by Volumetric Batching
and Continuous Mixing.
20. ASTM C920 – Standard Specification for Elastomeric Joint Sealants.
21. ASTM C 1017/C 1017M – Standard Specification for Chemical Admixtures for Use- In
Producing Flowing Concrete.
22. ASTM C1218 – Standard Test Method for Water-Soluble Chloride in Mortar and
Concrete.
23. ASTM C1260 – Standard Test Method for Potential Alkali Reactivity of Aggregates
(Mortar-Bar Method).
24. ASTM C1602 – Standard Specification for Mixing Water Used in the Production of
Hydraulic Cement Concrete.
25. ASTM D1751 – Standard Specification for Preformed Expansion Joint Filler for Concrete
Paving and Structural Construction (Non-extruding and Resilient Bituminous Types).
26. ASTM A184/A184M – Standard Specification for Fabricated Deformed Steel Bar Mats for
Concrete Reinforcement.
27. ASTM A615/A615M – Standard Specification for Deformed and Plain Billet- Steel Bars for
Concrete Reinforcement.
28. ASTM A675/A675M (2014) – Standard Specification for Steel Bars, Carbon, Hot-
Wrought, Special Quality, Mechanical Properties.
B. American National Standards Institute/American Welding Society (ANSI/AWS):
1. ANSI/AWS D 1-4 – Structural Welding Code – Reinforcing Steel.
C. American Concrete Institute (ACI):
1. ACI 117 – Standard Specifications for Tolerances for Concrete Construction and
Materials and Commentary.
2. ACI 207.1 – Guide to Mass Concrete.
3. ACI 301 – Specification for Structural Concrete.
4. ACI 304.6R-00 – Guide for Measuring, Mixing, Transporting, and Placing Concrete.
5. ACI 305R-10 – Specification for Hot Weather Concreting.
6. ACI 306R-10 – Specification for Cold Weather Concreting.
7. ACI 308.1 – Standard Specification for Curing Concrete.
8. ACI 309 – Guide for Consolidation of Concrete.
9. ACI 315 – Details and Detailing of Concrete Reinforcement.
10. ACI 318 – Building Code Requirements for Structural Concrete.
7-2
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
1.3 Definitions
A. Construction Joint: A construction joint is defined as a planned joint where two placements of
concrete meet, across which development and maintenance of bond are required, through
which any reinforcement that may be present is not interrupted. Unless otherwise indicated on
Drawings, construction joints in water-bearing members shall be provided with a water stop
and/or sealant groove of the shape indicated.
B. Control Joint: Control joints serve to provide for volumetric shrinkage of monolithic concrete
thus preventing the formation of objectionable shrinkage cracks elsewhere in the concrete. A
control joint is defined as a planned joint where two placements of concrete meet, across which
no bond is achieved, and through which some or all reinforcement that may be present is not
interrupted. Unless otherwise indicated or specified, control joints in water-bearing members
shall be provided with a water stop and/or sealant groove of the shape indicated.
C. Contraction Joint: A contraction joint is defined as a planned joint where two placements of
concrete meet, across which no bond is achieved and through which no reinforcement passes.
Contraction joints serve to provide for volumetric shrinkage of monolithic concrete and
movement between monolithic units at established joints, thus preventing the formation of
objectionable shrinkage cracks elsewhere in the concrete. Unless otherwise indicated or
specified, contraction joints in water-bearing members shall be provided with a water stop
and/or sealant groove of the shape indicated.
7-3
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
D. Expansion or Isolation Joints: Expansion or isolation joints are defined as a planned joint that
separates two adjacent concrete placements to allow the concrete to expand freely. Typically, a
space is provided between the two placements by placing a filler joint material against the first
pour, which acts as a form for the second pour.
E. Mass Concrete Vertical Joints: A planned vertical joint, oriented upstream-to- downstream,
extending the width of an individual placement block between two mass concrete placements.
F. Mud Mat: An unreinforced pad of concrete (minimum thickness shown on Drawings) placed on
roughened foundation soils.
G. Abrupt Surface Irregularities: Offsets and fins in formed concrete surfaces resulting from
displaced, mismatched, or misplaced forms, sheathing, or liners or from defects in forming
materials. Abrupt irregularities shall be measured within one inch of the irregularity.
H. Gradual Surface Irregularities: Irregularities in formed concrete surfaces resulting from warping
and similar uniform variations from planeness or true curvature. Gradual surface irregularities
shall be measured by determining the gap between concrete and near-surface along a five-foot
straightedge, measured between contact points.
1.4 Submittals
A. All proposals and submissions by the Contractor and all responses by the Engineer shall be in
writing. Acceptance of the Contractor's proposals and submissions by the Engineer shall not
relieve the Contractor of his responsibility for the Work as defined by the contract.
B. Contractor submissions to the Engineer shall include qualifying documentation for all materials
and products including:
1. The Contractor shall submit the proposed concrete mix design, mill certificates for cement
and supplementary cementing materials at least 4 weeks prior to construction for
approval.
2. Proposed concrete mix proportions including supporting trial mix results and certification
that the mix proportions will produce concrete of the specified quality and yield,
anticipated slumps for each proposed mix before and after the addition of
superplasticizer.
3. Documentation that the plant, equipment, and all materials to be used in the concrete
comply with the requirements of ACI 301.
4. Mill certificates for reinforcing steel.
5. Reinforcing bar detail lists and placing drawings shall be submitted to the Engineer for his
records.
6. Description of the proposed concrete batching plant and conveying systems, including
capacity, admixture provision batching system, cold weather capabilities, hot weather
capabilities, and quality control procedures.
7. Note that submissions to the Engineer and reviews of submissions by the Engineer shall
be completed prior to placing any concrete or doing any concrete work. The Contractor
shall schedule the submissions to allow for at least two weeks for review by the Engineer.
C. Water-Reducing Admixture; Water-Reducing High Range Admixture (Superplasticizer);
7-4
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
Accelerating Admixtures.
1. Manufacturer.
2. Proposed dosage, and timing of addition for each class of concrete, as applicable.
3. Type of admixture (retarding, accelerating, normal set).
D. Concrete Placement Plan: Submit a plan detailing the approach and schedule for formwork,
concrete mix specification and testing, and concrete delivery, placement, curing, protection,
and finishing for review and approval by the Engineer prior to initiation of concrete work. The
Plan shall include:
1. The overall schedule of concrete placement including sequence and timing of formwork
and placement, stripping, finishing and joint construction.
2. Rate of concrete placement and management of resulting traffic loads.
3. Conveyance plan, including belts, conveyors, concrete pumps, etc.
4. Method and equipment used to prepare Mass Concrete vertical joints.
5. Consolidation plan, including specifications of proposed vibratory and other equipment.
6. Curing medium and methods to be used in conformance with applicable standards.
7. Cold-weather placement plan including proposed materials, methods, and protection and
conforming to the requirements of applicable standards.
8. Hot-weather placement plan including proposed materials, methods, and protection and
conforming to the requirements of applicable standards.
E. Concrete Materials Statement: Submit materials and mix proportions (including admixtures)
proposed for each specified class of concrete and grout at least 30 days prior to initiation of
work using that class of concrete. Statement shall include results of mix designs and laboratory
tests including:
1. Concrete supplier proposed and location of plant or plants at which the concrete will be
batched.
2. Mix Designation and Identification.
3. Mix proportions based on SSD Aggregates and one cubic yard.
4. Moisture content of the aggregates as used in trials and corrections for the aggregate
weights used.
5. Specific gravity and absorption of the aggregates.
6. Admixture source and dosage.
7. Yield and wet unit weight.
8. Strength results and unit weights of cylinders.
9. Strength requirements – Both the design strength and the required average strength with
the applicable ASTM C-94 over design factor.
10. Cement and fly ash source.
7-5
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
11. Aggregate source, gradation and quality (include results of ASTM C1260).
12. Mix temperature.
13. Slump – design and actual.
14. Air Content – design and actual.
15. For mixes with a high-range, water reducer present, the slump and air content at 15-to-
20-minute time increments.
F. Concrete Materials Statement shall be accompanied by test reports from an accredited
laboratory which shows that the proposed materials and proportions yield concrete of the
quality required by this Section. No substitution shall be made in the source or type of materials
used in the work without additional tests to demonstrate that the quality of the substituted
materials and new concrete is satisfactory.
G. Water stops:
1. Shop drawings showing locations, sizes, types, joint details and pre-molded connections.
2. Manufacturer’s product data for water stops and for joining water stops.
H. Delivery Tickets: Ready-mixed concrete producer shall furnish duplicate delivery tickets. The
Contractor shall retain one ticket and submit another ticket to CQA Manager or Engineer at the
time of concrete delivery. Delivery tickets shall indicate the delivery date, batch time, truck
number, total revolutions, type of concrete, class, cubic yards, slump, cement and fly ash
content, number of admixtures, air content and amount of water.
I. Project Record Documents: Accurately record actual locations of embedded utilities and
components concealed from view in finished construction.
1.5 Qualifications
A. Field quality testing personnel shall be certified for appropriate ACI and ASTM testing methods.
7-6
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
1.8 Responsibilities
A. The Contractor shall submit three sets of shop drawings he has reviewed and approved to the
Design Engineer for review and comment. Submittals shall indicate bending diagrams;
assembly diagrams, splicing and laps of rebar; shapes; dimensions and details of bar
reinforcing; and accessories. Any fabrication and procurement of material done before approval
of the drawings and data shall be at the Contractor's risk.
B. The evaluation of concrete quality shall be the responsibility of the Contractor and shall be
carried out as outlined in Drawing Plan.
C. The Contractor shall provide a full-time coordinator who shall be always present during
concrete work and who shall be thoroughly trained and experienced in placing the types of
concrete specified and who shall direct all the work performed under this specification. The
coordinator shall have the authority to request that mixing trucks return to the batch plant if
delivery times are exceeded or to interrupt work if any other quality issues are not being met.
D. At the sole discretion of the CQA Manager or Engineer, the CQA Manager or Engineer may
reject delivered concrete if its parameters or field-tested quality does not meet specifications.
The rejected concrete will be at the Contractor’s expense.
E. The Contractor shall, at the start and during Work where appropriate, meet with the CQA
Manager or Engineer for the review of the following:
1. Proposed equipment and methods for storing constitutive components, mixing, and
conveying concrete. The Contractor shall provide documentation that the concrete
supplier meets industry certification.
2. Contractor's Quality Control Plan: The concrete supplier shall implement a Quality Control
7-7
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
Plan to ensure that the Owner's and Contractor's performance requirements will be met.
3. Inspection and testing of cement, aggregate, water, admixtures, reinforcement, and
storage of these materials.
4. Proposed form material, form ties, and form release materials. The Contractor shall
provide calculations for all concrete formwork and shoring, sealed by a Professional
Engineer.
5. Concrete mix designs regarding strength, performance, shrinkage, porosity, durability,
and suitability for Project requirements. The concrete supplier shall submit documentation
to the satisfaction of the Owner demonstrating that the proposed mix design(s) will
achieve the required strength, durability, and performance requirements.
6. Proposed methods of placing concrete are contained in the Concrete Placement Plan.
7. Proposed methods and materials for supporting and securing reinforcement items to be
cast-in and formwork including details of the reinforcement chairs and spacers.
8. Proposed details and positions of construction and crack control joints.
9. The inspection by the Engineer of formwork, reinforcement, cast-in items, and preparation
of existing concrete. Inspection by the Engineer of formwork shall be for conformance
with the project documents, but not for structural strength and stability, which is the sole
responsibility of the Contractor.
10. Sampling and testing of concrete and inspection of concrete placement procedures.
11. Preparation of existing concrete for bonding to new concrete.
12. Proposed curing methods, stripping times and hot and cold weather protection and
concreting procedures.
F. The Contractor shall submit test results to the Engineer for review within 5 working days of the
testing place.
G. The Contractor shall keep all records of the following:
1. Temperature of the plastic concrete and strength tests.
2. A certificate of accuracy of the scales at the batch plant.
3. Ambient air temperature and concrete temperature at the time of concrete placement.
4. Delivery tickets: The Contractor shall ensure that the records indicate where the delivered
concrete was used so that remedial action can be taken if it is subsequently determined
that the concrete is unsuitable for use.
7-8
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
samples may be collected and tested when the quality is suspected to be deficient by visual
observation and/or field testing.
D. The slump test shall conform to ASTM C 143, "Standard Testing Method for Slump of Portland
Cement Concrete". Tests shall be performed on the first truck delivering concrete for any pour
and include the collection of concrete cylinders. Additional sample collection and testing should
occur near the middle 1/3 of first and each subsequent 100 cubic yard concrete placement or
as specified by the CQA Manager or Engineer.
PART 2 PRODUCTS
2.1 Concrete Formwork:
A. The Contractor who places the concrete (the Concrete Contractor) is responsible for the
adequacy of all formwork and falsework including metal deck formwork and satisfying all codes
and regulations governing formwork and falsework.
B. All form lumber in contact with exposed concrete shall produce a smooth, hard, uniform texture
on the concrete. It may be plywood, tempered concrete-form-grade hardboard, metal, plastic,
or other acceptable material capable of producing the desired finish.
C. Form ties shall be a type which does not leave an open hole through the concrete, and which
permits neat and solid patching at every hole. Wire ties and wood spreaders shall not be used.
When forms are removed, all metal shall be not less than two inches from the surface.
Alternative forming systems may be used subject to advance approval by the Engineer.
D. All other materials not specifically described, but required for proper completion of concrete
formwork, shall be as selected by the Contractor subject to advance approval by the Engineer.
Rust-stained steel formwork is not acceptable.
E. The design and construction of all required forms shall be sufficiently tight to prevent leakage of
mortar and shall be able to prevent excessive deflection when filled with wet concrete. Design
loads and pressures shall conform to those stipulated in "Guide to Formwork for Concrete
Recommended Practice for Concrete Formwork", American Concrete Institute Publication ACI
347 and ACI 347R.
F. All required cast-in-place concrete shall be formed to the shapes, sizes, lines, and dimensions
indicated on the Drawings. The Contractor shall exercise particular care in the layout of forms
to avoid the necessity for cutting of concrete after it is in place. Proper provisions shall be made
for all openings, offsets, recesses, anchorage, blocking, and other features of the work as
shown or required. The Contractor shall perform all forming required for work of other trades
and shall do all cutting and repairing of forms required to permit such installation.
Reinforcement and other such items required to be anchored in the concrete shall be set
before the concrete is placed.
7-9
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
G. The forms shall be braced and tied together to maintain position and shape and to ensure the
safety of personnel. Bracing and supporting members of ample size and strength shall be
constructed to safely carry, without excessive deflection, all dead and live loads to which they
may be subjected. The Contractor shall provide metal spreader ties that give positive tying and
accurate spreading. Forms shall be constructed straight, true, plumb, and square.
7-10
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
concrete surface.
2. Symmetrically arrange hangers supporting forms from structural steel members to
minimize twisting or rotation of members.
3. Penetration of structural steel members is not permitted.
2.3 Cement
A. ASTM C150, Type I or II, low alkali containing less than 0.60 alkalis. Cement used throughout
the work shall be uniform in color.
2.4 Pozzolan
A. ASTM C618, Class F, fly ash having the following properties:
1. Loss on ignition limited to a maximum of 2.5 percent.
2. Contain less than 4 percent sulfur trioxide by weight.
B. Pozzolan shall be furnished from the same source and supplier for all concrete and that is used
in the submitted mix designs. Pozzolan from another source other than that used in the
approved mix designs will be rejected.
C. Pozzolan color shall not alter the resulting concrete from the normal gray color and
appearance.
2.5 Aggregates
A. Aggregates shall conform to the requirements of ASTM C33. Local aggregates not complying
with ASTM C33, but which have shown by test and actual service to produce concrete of
adequate strength and durability may be submitted for approval.
B. Aggregates shall be nonreactive for alkali-aggregate reactivity (AAR) and shall be washed
before use. Aggregates shall not be sourced from quarries where potential alkali reactivity
expansion of aggregates, as determined by ASTM C1260, exceeds 0.10 percent at 16 days.
C. Do not use aggregates containing soluble salts or other substances which cause stains on
exposed concrete surfaces.
D. Aggregates for all concrete shall be from the same quarry used to develop concrete mixes.
E. Fine aggregates and coarse aggregates shall be regarded as separate ingredients.
F. Fine Aggregate:
1. Hard, dense durable particles of either sand or crushed stone that are regularly graded
from coarse to fine, free from loam, clay, lumps and foreign material.
2. Gradation shall conform to ASTM C33.
3. Fine aggregate shall not exceed 40 percent by weight of the combined aggregate total.
4. The fineness modulus of the fine aggregate shall not be less than 2.3 or more than 3.1,
nor vary by more than 0.20 from the value assumed in selecting proportions of the
concrete. If this value is exceeded, the fine aggregate is rejected unless suitable
adjustments are made in proportions of the fine and coarse aggregate.
7-11
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
G. Coarse Aggregate:
1. Clean, uncoated, processed aggregate free from clay, mud, loam, and other foreign
material. Aggregate may be crushed natural rock, crushed stone, or washed natural or
crushed gravel. Use of pit run gravel is not permitted.
2. Gradation for coarse aggregate used in structural concrete shall conform to ASTM C33
using FDOT No. 57 aggregate.
2.6 Water
A. Clean, potable and free from oil, salt, acid, alkali, organic matter, or other deleterious
substances.
2.7 Admixtures
A. Water Reducing Admixtures (WRA): Conform to ASTM C494, Type A. Use a water-reducing
admixture to increase the workability of the mix, if necessary.
B. Set Retarders: ASTM C494, Type B, shall not be used in concrete, unless otherwise authorized
in writing by the Engineer.
C. Water Reducing Admixtures and Set Retarders: ASTM C494, Type D. Use only if authorized by
the Engineer.
D. High Range Water Reducing Admixtures: Conform to ASTM C494, Type F. Use only if
authorized by the Engineer.
E. High Range Water Reducing Admixtures and Retarders: ASTM C494, Type G shall not be
used in concrete only if authorized in writing by the Engineer.
F. Accelerating Admixtures: ASTM C494, Type C or E shall not be used in concrete only if
authorized in writing by the Engineer.
7-12
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
B. Normal-Density Fine Aggregate for the concrete mixes shall conform to Table 7-2. The fineness
modulus of the sand shall be not less than 2.5 nor more than 2.9.
No. 4 100
No. 8 85-100
No. 16 55-80
No. 30 30-55
No. 50 15-30
No. 100 2-10
C. All concrete, unless otherwise specifically permitted by the Engineer, shall be transit-mixed in
accordance with ASTM C 94.
7-13
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
B. Hydrophilic Water stop: The water stop shall be a combination of chloroprene rubber and
chloroprene rubber modified to impart hydrophilic properties. The water stop shall have a delay
coating to inhibit initial expansion due to moisture present in fresh concrete. Minimum tensile
strength shall be 350 psi for hydrophilic rubber and 1300 psi for chloroprene rubber as tested in
accordance with ASTM D412. Minimum elongation shall be 600% for hydrophilic rubber and
400% for chloroprene rubber as tested in accordance with ASTM D412. Minimum Shore A
hardness shall be 52+/-5 for hydrophilic rubber and 50+/-5 for chloroprene rubber as tested in
accordance with ASTM D2240. Minimum tear resistance shall be 50 lb/in for hydrophilic rubber
and 100 lb/in for chloroprene rubber as tested in accordance with ASTM D624.
C. Expansion Anchors: Stainless steel, expansion type, minimum 2500-lb allowable tension load,
unless otherwise designated on Drawings.
D. Curing and Sealing Compound: Liquid membrane-forming compound for curing concrete,
ASTM C309, clear type.
E. Fiber Expansion Joint Filler (Fiber PJF): Resilient bituminous type, non-extruding, ASTM
D1751, 1/2-inch thick (unless otherwise shown), of depth shown on Drawings.
F. Joint Sealant: Two-part polysulfide sealant complying with Federal Specifications TT-S-
00227E, type II. Color to match concrete.
G. Bond Breaker: Asphalt impregnated felts, 15 pounds, polyethylene tape, coated paper, metal
foil, or other approved material.
H. Aluminum embedments of any kind are prohibited.
PART 3 EXECUTION
3.1 Preparation
A. Verify lines, levels, and centers before proceeding with formwork. Verify dimensions agree with
Drawings.
B. When formwork is placed after reinforcement resulting in insufficient concrete cover over
reinforcement, request instructions from CQA Manager or Engineer before proceeding.
C. Deliver reinforcing bars to the job site cut to exact length, bent, securely bundled, and tagged
with metal tags corresponding to the bar schedules and diagrams.
D. Store bars and bar mats at a minimum height of six inches off the ground and protect from
mechanical injury, surface deterioration, and moisture.
E. Reinforcement must be free from loose rust and scale, dirt, oil, or other deleterious coating that
could reduce the bond with the concrete.
F. If concrete placement is delayed for a considerable number of days after reinforcement is
placed in a position such that reinforcement is corroding, protect reinforcement by covering it
with canvas or other satisfactory covering, or if directed by CQA Manager or Engineer, paint
reinforcement with a coat of neat cement grout. Any bars having loose scaly rust shall be
cleaned before concrete is placed.
G. Ensure that transport, storage and assembly of concrete reinforcing does not damage prepared
foundations, adjacent concrete or formworks, or allow contamination of adjacent streams,
7-14
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
7-15
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
4. Carefully verify horizontal and vertical positions of forms. Correct misaligned or misplaced
forms before placing concrete.
5. Complete wedging and bracing before placing concrete.
C. Provide for openings, offsets, sinkages, keyways, recesses, moldings, rustications, reglets,
chamfers, blocking, screeds, bulkheads, anchorages and inserts, and other accommodations
for required features.
D. Arrange and assemble formwork to permit dismantling and stripping. Do not damage concrete
during stripping.
7-16
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
7-17
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
Q. Concrete shall be consolidated with a vibrator, and then push-floated with a bullfloat, as
necessary.
R. When concrete is to be placed by pump, properties shall be measured at discharge from the
hose. The sand content of the pump mix, as a ratio by weight of total aggregate shall not be
increased more than 3% from the conventionally placed concrete.
3.5 Consolidation
A. Consolidate concrete, as per the requirements of the approved Concrete Placement Plan.
B. Consolidate concrete immediately after it is placed in the work with internal type mechanical
vibrators capable of transmitting vibration to the concrete at frequencies not less than 6000
impulses per minute.
C. Employ sufficient number of vibrators so that, at the required rate of placement, vibration is
maintained throughout the entire volume of each layer of concrete and complete consolidation
is secured.
D. Location, manner, and duration of application of vibrators shall be such as to secure maximum
consolidation of the concrete without causing segregation of the mortar and coarse aggregate,
and without causing water or cement paste to flush to the surface.
E. Vibration shall be applied vertically or near vertical in the freshly deposited concrete by
inserting and removing the vibrator at points uniformly spaced and not farther apart than twice
the radius over which the vibration is visibly effective. The vibrator shall extend into the
previously placed layer of fresh concrete, at all points, to ensure an effective bond between
layers.
F. Vibration shall not be applied directly to reinforcement steel or forms, nor to concrete that has
hardened to the degree that it does not become plastic when vibrated.
G. The use of vibrators to transport concrete in the forms or conveying equipment will not be
permitted. Vibration shall be supplemented by spading and hand tamping as necessary to
ensure smooth and dense concrete along form surfaces, in corners, and around embedded
items and water stops.
H. Close attention and additional effort will be necessary to adequately consolidate concrete
adjacent to construction joints, at vertical joints in Mass Concrete, sloping surfaces, and around
embedded items.
7-18
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
7-19
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
3.9 Welding
A. Welding of reinforcement bars will be permitted only where indicated on approved Shop
Drawings or as authorized by the CQA Manager or Engineer.
B. Welding shall be performed in accordance with AWS D1.4 except where otherwise specified or
indicated.
C. Welded crossing reinforcement bars installed to aid assembly shall not be permitted, except as
7-20
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
7-21
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
may submit alternate, additional, or elimination of joint locations for CQA Manager or
Engineer’s approval.
C. Where a feather edge would be produced at a construction joint, as in the top surface of a
sloping wall, an insert form shall be used so that the resulting edge thickness on either side of
the joint is not less than six inches.
D. Provide roughened surface in construction joints in walls, and between walls and footing.
E. Place construction joints perpendicular to the main reinforcement. Continue reinforcement
across construction joints.
F. Surfaces of concrete to be joined shall be clean, rough, and moist when new-cast-in-place
concrete is applied. Clean joint surfaces to remove all unsatisfactory concrete, laitance,
coatings, stains, or debris by washing and scrubbing with a wire brush or wire broom or by
other means approved by the CQA Manager or Engineer.
G. Prepare surfaces of existing or hardened concrete by wet or dry sandblasting, water blasting
with approved equipment, bush hammering, grinding, or other approved method. Clean
surfaces with air/water jets and allow to dry thoroughly; drying may be accomplished by air jets.
Compressed air used in cleaning and drying operations shall be free from oil or other
contaminating materials.
H. Joints shall be thoroughly moistened prior to placing concrete. Surfaces shall be kept moist for
at least one hour prior to placement of new concrete. The new concrete shall be placed directly
on the cleaned and washed surface.
I. Steel tying and form construction adjacent to concrete in place shall not be started until the
concrete has cured at least 12 hours.
7-22
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
3.15 Waterstops
A. Install waterstops in accordance with manufacturer’s recommendations.
B. Embed half of the PVC water stop on each side of the joint. Waterstops shall be carefully and
correctly positioned during installation to eliminate faulty installation that may result in joint
leakage. All waterstops shall be installed to form a continuous watertight diaphragm in each
joint.
C. Support and protect waterstops during construction.
D. Any waterstop punctured or damaged shall be replaced or repaired at the Contractor's
7-23
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
expense.
E. Splice PVC waterstops together using approved splicing procedures to form a continuous
watertight diaphragm in accordance with the following:
1. All splices shall be made on a bench in a temporary shop provided at the site of
installation or manufacturer's plant.
2. Miter guide and portable power saw shall be used to cut the ends to be joined to ensure
good alignment and contact between joined surfaces. Continuity of the characteristic
features of the cross section of the water stop (ribs, tabular center axis, protrusions and
the like) shall be maintained across the splice.
3. Splice PVC water stops by heat sealing adjacent surfaces in accordance with the
manufacturer’s recommendations. Do not expose water stop to direct flame which could
cause charring.
4. Waterstops shall be reformed at splices with a remolding iron with ribs or corrugations to
match the pattern of the water stop.
5. The spliced area, when cooled and bent by hand in as sharp an angle as possible, shall
show no sign of separation.
F. The concrete shall be thoroughly consolidated in the vicinity of the water stop.
G. Suitable guards shall be provided to protect exposed projecting edges and ends of partially
embedded water stops from damage when concrete placement has been discontinued.
H. Hydrophilic Waterstops:
1. Utilize the adhesive recommended by the manufacturer to attach hydrophilic waterstop to
the concrete surface.
2. Cut ends of hydrophilic waterstop square and fit together snug without use of overlaps.
3. Apply sealant or adhesive at splices as recommended by the manufacturer.
3.16 Chamfering
A. Place chamfers at exposed joints, edges and external corners, unless otherwise designated, to
produce uniformly straight lines and tight edge joints. Extend terminal edges to the required
limit and miter chamfer strips at changes in direction.
B. Unexposed corners may be formed either square or chamfered
C. Chamfered joints shall not be permitted where earth or rock fill is placed in contact with
concrete surfaces.
D. Chamfered joints shall be terminated twelve inches outside the limit of earth or rock fill so that
the end of the chamfers will be clearly visible.
7-24
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
C. Do not allow excess form release agent to accumulate in forms or contact existing concrete
against which new concrete will be placed. Remove surplus coating on form surfaces and
coating on reinforcing steel and construction joints before placing concrete.
D. Do not apply form release agent where concrete surfaces are indicated to receive special
finishes or applied coverings that are affected by agent. Soak inside surfaces of untreated
forms with clean water. Keep surfaces coated prior to placement of concrete.
7-25
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
Element Time
Walls, Slabs, and Footings and Other Elements – with side or vertical 7 days
load
Walls, Slabs, Footings, and Other Elements – with no side or vertical loading:
Concrete supporting not more than 20 feet of wall in place above it 3 days
E. Evidence that concrete has gained sufficient strength to permit removal of forms shall be
determined by tests on control cylinders in accordance with the following:
1. Control cylinders shall be stored in the structure or as near the structure as possible, so
they receive the same curing conditions and protection methods as given those portions
of the structure they represent.
2. Control cylinders shall be removed from the molds at an age of no more than 24 hours.
3. All control cylinders shall be prepared and tested in accordance with applicable standards
and shall be tested within 4 hours after removal from the site.
7-26
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
F. Form removal shall be scheduled so that all necessary repairs can be performed as specified in
the Section - Cast-in-Place Concrete.
G. Loosen forms carefully. Do not wedge pry bars, hammers, or tools against finished concrete
surfaces scheduled for exposure to view. Perform formwork removal in a manner that will
prevent damage to concrete and ensure the complete safety of the structure.
H. Where forms are removed prior to 7 days of age, the age of stripped concrete shall be at least
7 days before any load is applied other than the weight of the wall itself and the forms and
scaffolds for succeeding lifts.
I. Store removed forms in a manner that surfaces to be in contact with fresh concrete will not be
damaged. Discard damaged forms.
7-27
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
3. The required color uniformity class is CU2 in accordance with ACI 347.3R. Color
consistency between adjacent placements and layer lines shall be mostly uniform.
Concrete source materials and form-facing material shall be of consistent type, grade,
and source to avoid causing deviations in appearance. Rust and dirt stains are
unacceptable.
4. The required surface irregularity class is SI3 in accordance with ACI 347.3R. Maximum
gradual deviation over a distance of 5 feet, or abrupt deviation is 1/4 inch.
5. Deflection of formwork structure shall be limited to L/360 (span/360). The required
construction and facing joint class is CJ4 in accordance with ACI 347.3R. The offset of
surfaces between two adjacent placements shall not exceed 1/8 inch.
6. The required form facing category is class FC2 in accordance with ACI 347.3R. Holes
greater than 3/16 inch are acceptable if patched, sanded, and sealed or ground to match
adjacent form surface. Holes less than 3/16 inch are acceptable without patching,
provided form surface is not damaged or torn around the holes. Vibrator burns, concrete
remnants (hardened concrete on the form face) and swelling at fastener or tie holes are
unacceptable.
7. The required surface void ratio class is SVR3 in accordance with ACI 347.3R. Void area
shall not exceed 0.6% of the test area. The maximum void area of pores of the surface
occurring within a 24-inch by 24-inch square sample test area is 3.5 square inches. The
maximum void average diameter is 3/8 inch. Voids with an average diameter of less than
3/32 inch are excluded from the calculated void area.
8. Rub all exposed finish concrete surfaces with a medium coarse carborundum stone using
water for lubrication and cleaning.
9. Rubbing shall be started immediately after the forms are removed, patching is finished,
and the patching mortar has set thoroughly.
10. Continue rubbing until all form marks, projections and irregularities have been removed
and a uniform surface has been obtained.
11. After rubbing is completed, the surface shall be washed to remove loose powder and
shall be left free from unsound patches, paste, powder, and objectionable marks.
E. Finishing of exposed finished surfaces shall be completed on the same workday the forms are
removed.
F. Related Unformed Surfaces: At top of walls, horizontal offsets, and similar unformed surfaces
occurring adjacent to formed surfaces, strike off and finish with texture matching adjacent
formed surfaces. Continue final surface treatment of formed surfaces uniformly across adjacent
unformed surfaces, unless otherwise shown.
7-28
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
3.23 Patching
A. Minor Areas:
1. The Contractor shall chip away defective areas to a depth of about 1 inch, leaving edges
perpendicular to the surface. The area to be patched and space of at least 6 inches wide
around it shall be thoroughly wet to prevent water from being absorbed out of the mortar.
2. Bonding agent as approved by CQA Manager or Engineer shall be applied to the area to
be patched. The patching mortar shall be applied after the bond becomes tacky.
3. Patching mortar shall consist of one part cement to two and one-half parts (1:2-1/2) sand.
With a bonding agent added the mortar shall be wetted to a consistency as dry as
possible within the requirements of handling and placing. The mortar shall be thoroughly
compacted by ramming it into place.
4. The patch shall be screed off to leave the patch slightly higher than surrounding surfaces.
It shall be left undisturbed for a period of one to two hours to permit initial shrinkage,
before performing final finishing.
5. The patch shall be finished to match adjacent surfaces and kept wet for at least seven
days. The Contractor shall provide and install all required protective covering.
6. Major Defective Areas: If the defects are serious or affect the strength of the structure, or
if patching does not satisfactorily restore the quality and appearance of the surface, the
CQA Manager or Engineer may require the concrete be completely removed and
replaced in accordance with the provisions of this section, all at no additional cost to the
Owner.
7-29
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
PART 4 SCHEDULES
4.1 Variations from Specified Lines, Grades, and Dimensions
A. Variation of controlling dimensions for each structure from the specified position in the plan
from the reference line:
Overall dimensions: ± 1 inch
B. Variation from specified curved profile for the labyrinth crest surface:
For crest of labyrinth:± 1/4 inch
C. Variation from plumb, specified batter, or specified curved profile for lines and surfaces of walls,
vertical joint grooves, and arises for exposed construction:
When overall height of the line or surface is:
10 feet or less ± 1/2 inch
More than 10 feet ± 3/4 inch
For any two successive intermediate points on the line or surface separated by:
10 feet ± 1/2 inch
10 feet or more ± 3/4 inch
D. Variation in thickness of slabs, walls, footings, and similar members from that specified:
1/4 inch, +1/2 inch
E. Variation in the location from the specified position in the plan of sleeves, floor openings, and
walls openings:
± 1/2 inch
7-30
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 7 Concrete February 9, 2024
7-31
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 8 Decant Structures February 9, 2024
PART 1 GENERAL
1.1 Scope
A. Summary of Work: The Contractor shall furnish all labor and equipment required to install the
steel discharge pipes in accordance with the provisions and requirements of these
specifications, to the lines and grades shown on the Drawings. This work item includes but is
not limited to, any excavation and preparation of the foundation soils, dewatering, construction
of concrete foundations, and required assembly of the spillway discharge pipes. The Contractor
shall safely execute the Work and meet all applicable MSHA and OSHA requirements. The
Owner will provide the decant riser structures and their erection under a separate contract. The
Contractor shall construct the reinforced concrete decant riser structure foundation slabs. The
Contractor shall coordinate his spillway culvert work schedule with that of the decant riser
installer.
8-1
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 8 Decant Structures February 9, 2024
PART 2 PRODUCTS
2.1 Pipe
A. Discharge piping through the dams shall be carbon steel 0.50” wall thickness, spiral welded
seam, API 5L steel line pipe meeting PSL-1 Grade B (35 ksi minimum yield strength).”
B. Vertical “Downcomer” pipe segments shall be carbon steel (standard) 0.375” wall thickness and
shall conform to ASME B31.3 Metallic Piping Systems.
PART 3 EXECUTION
3.1 Spillway Structure
A. The spillway structures shall conform to the Drawings with the following provisions for site
preparation procedures, backfilling, and pipe support, which are illustrated in detail on the
Drawings.
8-2
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 8 Decant Structures February 9, 2024
B. Welders shall be certified for the procedures and positions to be used. Certifications of welding
shall be performed by an independent testing laboratory and shall also be in effect at the time
of work. Weld electrodes shall be the exact type recommended by the pipe manufacturer.
C. Spillway discharge pipes are to be laid at the specified lines and grades and supported a
minimum of 8 inches above the prepared soil bed. The culverts are to be anchored with soil
anchors and straps spaced along their entire length to prevent any movement during the
placement of concrete and backfilling. Two seep shields shall be installed on each discharge
pipe as shown in the Drawings.
D. The soil bed for spillway installation must be firm, unyielding under equipment traffic, and
maintained free of standing water or deleterious soils. The side slopes of the excavation should
be flat enough to be stable and meet current OSHA regulations. The side slopes shall also be
4H:1V, or flatter. The width of the excavation should be sufficient to allow for proper compaction
and vehicular traffic including concrete trucks.
E. Wood forms shall be used to contain the concrete cradle. Trenches for laying of forms shall be
backfilled with compacted overburden spoil fill as shown on the Drawings.
F. In casting the cradle, concrete with a 28-day design compressive strength of 2500 psi and with
a maximum aggregate size of 3/4-inch is to be initially placed from one side of the culvert pipe
only, vibrated and forced under the pipe to the opposite side. When a sufficient amount of
concrete has passed beneath the culvert into the opposite side, pouring and vibrating may be
continued from the other side. The concrete should extend up from the bottom of the culvert a
distance equal to one-half the diameter of the culvert, in two separate lifts as shown on the
Drawings. Under no condition shall the second lift be poured before the first lift has attained its
initial set.
G. The concrete cradle is to extend along the horizontal length of the spillway discharge culvert
from the riser structure to the outermost edge of the embankment.
H. Backfill at the spillway is to be consistent with the section of the dam being built. Backfill soils
are to be compacted to the same requirements as specified for the embankment materials.
8-3
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 8 Decant Structures February 9, 2024
coating.
C. Dry film thickness must meet these specifications. All painting systems shall be available for
inspection by the Owner’s Engineer or representative. Any coating system found to be deficient
in film thickness, have holidays, runs, drips, etc. shall be recoated at the request of the
Engineer at no additional charge to the Owner.
3.3 Installation
A. Except as otherwise specified, all ductile iron pipe shall be installed in accordance with
ANSI/AWWA C-600. Great care shall be taken during loading, transportation and unloading to
prevent injury to the pipe or coating. Under no circumstances shall pipe be dropped. All pipe
and fittings shall be carefully examined before laying and no piece shall be installed which is
found to be defective. Any damage to the pipe shall be repaired as directed by the CQA
Manager or Engineer.
B. If any defective pipe is discovered after it has been laid, it shall be removed and replaced with a
sound pipe in a satisfactory manner by the Contractor, at his own expense.
C. All pipe and fittings shall be thoroughly cleaned before laying and shall be kept clean until they
are used in the completed work and when laid shall conform to the lines and grades shown.
D. Pipes shall be installed with bell ends in the direction of laying. No pipe shall be laid upon a
foundation in which frost exists.
E. Blocking of pipelines laid in the ground will not be permitted unless the pipe is to be laid with a
concrete cradle or encasement. Open ends of pipes shall be kept plugged with a bulkhead
during construction. Sufficient backfill shall be placed or other precautions shall be taken to
prevent flotation or movement.
8-4
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 8 Decant Structures February 9, 2024
8-5
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 9 Grout-Filled Erosion Control Mat February 9, 2024
PART 1 GENERAL
1.1 Scope
A. Summary of Work: The Contractor shall furnish all labor and equipment required to install the
grout-filled erosion control mat, also designated as fabric-formed or filter point mat, in
accordance with the provisions and requirements of this specification, to the lines and grades
shown on the Drawings. This work item includes but is not limited to, any excavation and
preparation of the foundation soils, dewatering, construction of concrete foundations, and
required assembly of the grout-filled erosion control mat.
9-1
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 9 Grout-Filled Erosion Control Mat February 9, 2024
16. ASTM D 4632-08 – Standard Test Method for Grab Breaking Load and Elongation of
Geotextiles.
17. ASTM D 4751-04 – Standard Test Method for Determining Apparent Opening Size of a
Geotextile.
18. ASTM D 4759 – Practice for Determining the Specification Conformance of Geotextiles.
19. ASTM D 4833-07 – Standard Test Method for Index Puncture Resistance of
Geomembranes and Related Products.
20. ASTM D 4873 – Standard Guide for Identification, Storage, and Handling of Geotextiles.
21. ASTM D 4884 – Test Method for Seam Strength of Sewn Geotextiles.
22. ASTM D 5199 – Test Method for Measuring Nominal Thickness of Geotextiles and
Geomembranes.
23. ASTM D 5261 – Test Method for Measuring Mass per Unit Area of Geotextiles.
9-2
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 9 Grout-Filled Erosion Control Mat February 9, 2024
B. The compressive strength test shall conform to ASTM C 39, "Standard Test Method for
Compressive Strength of Cylindrical Concrete Specimens".
C. A minimum of three standard cylinders shall be molded and tested for each pour where 25
cubic yards, or any fraction thereof, is placed in one day. A minimum of three additional
cylinders shall be molded and tested for each additional 50 cubic yards, or fraction thereof,
placed in the same day.
D. The Contractor must perform one of the cylinder tests at 7 days and two at 28 days. The test
results shall be the average of the two 28-day cylinders.
PART 2 PRODUCTS
2.1 Erosion Control Mat
A. The erosion control mat shall be Filter Band (FB) type and have a finished average thickness of
6 inches, a nominal mass per unit area of 68 lb/ft2, and a deeply textured surface appearance
with alternating concrete tubes. The shear resistance of the concrete lining shall be 30 lb./ ft2.
B. The erosion control mat shall be composed of synthetic yarns formed into a woven fabric.
Yarns used in the manufacture of the fabric shall be composed of polyester. Forms shall be
woven with a minimum of 50% textured yarns (by weight). Partially oriented (POY), draw-
textured, and/or staple yarns shall not be used in the manufacture of the fabric. Each layer of
fabric shall conform to the physical, mechanical, and hydraulic requirements listed in Table 9-1.
The fabric forms shall be free of defects or flaws, which significantly affect their physical,
mechanical, or hydraulic properties.
C. The erosion control mat shall consist of double-layer woven fabric joined together by spaced,
interwoven Erosion control mat to form a concrete lining with a deeply cobbled surface
appearance. Erosion control mat shall be formed by interweaving the double-layer fabric to
form water permeable drains and attachment points for the control of concrete lining thickness.
The interweaving of the fabric layers shall form an area of double density, high strength, single-
layer fabric with an area of and a perimeter of 63 in2 and a perimeter of 11 inches. All erosion
9-3
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 9 Grout-Filled Erosion Control Mat February 9, 2024
control mat fabric shall be cross shaped and shall have twill weave centers designed to
function as drains to relieve hydrostatic uplift pressure.
9-4
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 9 Grout-Filled Erosion Control Mat February 9, 2024
D. Mill widths of fabric shall be a minimum of 84 inches. Each selvage edge of the top and bottom
layers of fabric shall be reinforced for a width of not less than 1.35 inches by adding a minimum
of 6 warp yarns to each selvage construction. Mill width rolls shall be cut to the length required,
and the double-layer fabric separately joined, bottom layer to bottom layer and top layer to top
layer, by means of sewing thread, to form multiple mill width panels with sewn seams on not
less than 80 inches centers.
E. All factory-sewn seams shall be downward facing as shown on the Drawings. All seams sewn
in the factory shall be not less than 90 lbf/in when tested in accordance with ASTM D 4884. All
sewn seams and zipper attachments shall be made using a double line of U.S. Federal
Standard Type 401 stitch. All stitches shall be sewn simultaneously and be parallel to each
other, spaced between 0.25 inches to 0.75 inches apart. Each row of stitching shall consist of 4
to 7 stitches per inch. Thread used for seaming shall be nylon and/or polyester.
F. Baffles shall be installed at predetermined mill width intervals to regulate the distance of lateral
flow of fine aggregate concrete. The baffle material shall be nonwoven filter fabric. The grab
tensile strength of the filter fabric shall be not less than 90 lbf when tested in accordance with
ASTM D 4632.
G. The erosion control mats shall be kept dry and wrapped such that they are protected from the
elements during shipping and storage. If stored outdoors, they shall be elevated and protected
with a waterproof cover that is opaque to ultraviolet light. The erosion control mat shall be
labeled as per ASTM D 4873, “Guide for Identification, Storage and Handling of Geosynthetic
Rolls.”
H. The Contractor shall submit a manufacturer’s certificate that the supplied erosion control mat
meets the criteria of these Specifications, as measured in full accordance with the test methods
and standards referenced herein. The certificates shall include the following information about
each erosion control mat delivered:
1. Manufacturer’s name and current address; Product name.
2. Style and Product code number; Form number(s).
3. Composition of yarns; and Manufacturer’s certification statement.
9-5
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 9 Grout-Filled Erosion Control Mat February 9, 2024
D. Water for mixing shall be clean and free from injurious amounts of oil, acid, salt, alkali, organic
matter or other deleterious substances.
E. Pozzolan, if used, shall conform to ASTM C 618, Class C, F, or N.
F. Plasticizing and air entraining admixtures, if used, shall conform to ASTM C 494 and ASTM C
260, respectively.
2.3 Geotextile
A. The geotextile shall be a 100-mil thick, 10 oz/yd2, non-woven, needle punched fabric
constructed from 100% polypropylene, or 100% polyester (polyethylene terephthalate base
resin). The geotextile shall be uniform and homogeneous in appearance and composition, and
shall be free from tears, cuts, or any defect that may affect serviceability. The geotextile shall
be supplied in rolls having a minimum width of 15 feet and a minimum length of 300 feet.
B. The geotextile shall exhibit the following minimum properties as shown in Table 9-2.
Table 9-2: Property Requirements of Geotextile
PART 3 EXECUTION
3.1 Site Preparation
A. Areas on which fabric forms are to be placed shall be constructed to the lines, grades,
contours, and dimensions shown on the Drawings. All obstructions such as roots and projecting
stones shall be removed. Where such areas are below the allowable grades, they shall be
9-6
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 9 Grout-Filled Erosion Control Mat February 9, 2024
brought to grade by placing compacted layers of select material. The thickness of layers and
the amount of compaction shall be as specified by the CQA Manager or Engineer. Where
required by the Specifications, soft and otherwise unsuitable subgrade soils shall be identified,
excavated, and replaced with select materials in accordance with the Specifications.
B. Excavation and preparation of aprons as well as anchor, terminal, or toe trenches shall be done
in accordance with the lines, grades, contours, and dimensions shown on the Drawings.
C. Immediately prior to placing the fabric forms, the prepared area shall be inspected by the CQA
Manager or Engineer, and no forms shall be placed thereon until the area has been approved.
3.2 Installation
A. Erosion Control Mat
1. The Erosion control mat shall be placed on the graded surface approved by the Engineer
and/or Engineer’s Representative.
2. The Erosion control mat shall be placed over the geotextile and within the limits shown on
the Drawings. Anchoring of the erosion control mat shall be accomplished using anchor,
terminal, and toe trenches to meet the manufacturer’s requirements.
3. Adjacent erosion control mat shall be joined before filling with fine aggregate concrete by
field sewing or zippering the two bottom layers of fabric together and the two top layers of
fabric together. All field seams shall be made using two lines of U.S. Federal Standard
Type 101 stitches. All sewn seams shall be downward facing, and all zipper seams shall
be fastened per the manufacturer’s requirements.
4. Immediately prior to filling with fine aggregate concrete, the assembled fabric forms shall
be inspected by the Engineer and/or Engineer’s Representative, and no fine aggregate
concrete shall be pumped therein until the erosion control mat seams have been
approved. At no time shall the unfilled erosion control mat be exposed to ultraviolet light
(including direct sunlight) for a period exceeding five days.
5. Care shall be exercised during installation of the erosion control mat so as not to damage
the underlying geotextile. The Contractor shall protect the weep holes from filling with soil
or other foreign matter throughout construction and shall maintain and/or restore the
open and clean condition of the weep holes. Any damage to the erosion control mat or
geotextile shall be repaired by the Contractor at his own expense.
B. Fine Aggregate Concrete Placement
1. Following the placement of the erosion control mat, small slits shall be cut in the top layer
of the erosion control mat to allow the insertion of the filling pipe at the end of the fine
aggregate concrete pump hose. These slits shall be of the minimum length to allow
proper insertion of the filling pipe. Fine aggregate concrete shall be pumped between the
top and bottom layers of fabric, filling the forms to the recommended thickness and
configuration.
2. Fine aggregate concrete shall be injected in such a way that the erosion control mat is
fully inflated but is not overinflated to the point of rupturing. Any damage to the erosion
control mat caused by overinflation shall be repaired to the satisfaction of the Engineer,
including removal and replacement, at the Contractor's expense.
9-7
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 9 Grout-Filled Erosion Control Mat February 9, 2024
3. Holes in the erosion control mat left by the removal of the filling pipe shall be temporarily
closed by inserting a piece of nonwoven fabric or similar material. The nonwoven fabric
shall be removed when the concrete is no longer fluid and the concrete surface at the
hole shall be cleaned and smoothed by hand. Foot traffic on the erosion control mat shall
be restricted to an absolute minimum for one hour after filling.
4. After the fine aggregate concrete has set, all anchor, terminal, and toe trenches shall be
backfilled and compacted, as specified by the Engineer and/or Engineer’s
Representative.
5. After the fine aggregate concrete has set, the surface of the erosion control mat shall be
cleaned via pressure washing or similar method to remove grout from the filter
bands/points. The filter points shall be free of any residual caking or clogging from grout
bleed.
C. Geotextile
1. Construct the surface underlying the geotextiles smooth and free of ruts or protrusions,
which could damage the geotextiles.
2. Install geotextiles in accordance with Manufacturer's written recommendations.
3. Hand place geotextile. No equipment will be permitted to traffic in direct contact with the
geotextile.
4. Lay geotextile smooth to be free of tensile stresses, folds, and wrinkles.
5. Overlap all geotextile seams by a minimum of 18 inches.
6. Protect geotextiles from clogging, tears, and other damage during installation.
7. Use adequate ballast (e.g., sandbags) to prevent uplift by wind.
8. Do not use staples or pins to hold the geotextile in place.
9. Do not leave geotextile uncovered for more than 14 days.
9-8
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 9 Grout-Filled Erosion Control Mat February 9, 2024
9-9
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 10 Seeding and Mulching February 9, 2024
PART 1 GENERAL
1.1 Scope
A. All finished downstream and upstream embankment slopes, toe roads and hydraulic return
ditch slopes shown on the Drawings shall be grassed as protection against surface erosion.
B. A 6-inch-thick layer of overburden cap soil material favorable to plant growth shall be placed on
any exposed sand tailings slopes, which are to be conditioned, seeded and mulched to
establish permanent erosion control.
1.3 Submittals
A. The Contractor shall provide necessary documents/certifications to the Owner confirming that
all materials supplied for the project meet the requirement of these Specifications.
B. Submit Product Data for seed mix, lime, fertilizer, mulch, and other products to be used.
C. Submit a Manufacturer's Certificate certifying that products meet or exceed specified
requirements.
D. Submit soil testing results for topsoil, including recommended application rates for lime and
fertilizer.
E. Submit a soil conditioning and seeding plan for a test plot. The test plot shall confirm a suitable
soil conditioning and seeding plan for erosion control within the project.
10-1
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 10 Seeding and Mulching February 9, 2024
B. All seed shall be delivered in original, unopened containers bearing manufacturer’s analysis of
contents. Seed shall be guaranteed 95 percent pure and have a minimum germination rate of
85 percent, within 1 year of test.
1.6 Responsibilities
A. The Contractor shall seed within the areas as shown in the Drawings and other areas
designated by the Owner/CQA Manager or Engineer.
B. Seeding of blended grasses shall consist of ground preparation, furnishing, and sowing
approved seed, mulching, furnishing, and spreading two applications of an approved
commercial fertilizer. A single application of an approved commercial fertilizer may be
considered acceptable, pending approval by the Owner.
C. All seeding operations shall be performed in accordance with the provision of these
Specifications.
D. A test plot on a 2.5 (horizontal) to 1 (vertical) slope shall be established by the Contractor to
demonstrate vegetation can be established to provide sufficient erosion control. The vegetative
coverage and established erosion control shall be approved by the Owner and Engineer.
E. The Contractor shall guarantee germination of 85 percent of all grasses.
F. The Contractor shall furnish invoices for all materials received on site to the CQA Manager or
Engineer as verification of the minimum application rate of materials.
G. The Contractor shall not perform fertilizing, seeding, and mulching operations when wind
velocities exceed 15 miles per hour.
PART 2 PRODUCTS
2.1 General
A. The Contractor shall be responsible for calculation of the required quantity and volume of each
material based on Drawings, test results, estimates of wastage during delivery, stockpiling,
haulage and placement, experience with similar materials, and other factors as identified by the
Contractor.
B. The Contractor shall be responsible for all costs associated with delays or material quantity or
volume shortfalls due to miscalculation or required rework resulting from not meeting material
or placement specifications.
C. The Contractor shall be responsible for establishing and implementing a suitable vegetative
plan for developing vegetative coverage and provide permanent erosion control.
10-2
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 10 Seeding and Mulching February 9, 2024
2.2 Materials
A. Overburden Cover Soil:
1. Utilizing designated stockpiles from disturbed areas on-site, the Contractor shall ensure
that sufficient quantities exist to allow placement of a minimum of six inches (after
compaction) of topsoil over all graded earthen areas and over any other areas to be
seeded.
2. If sufficient quantities of topsoil do not exist on-site or are not available as a result of the
Contractor’s operations, the Contractor shall, at no additional cost to the Owner, import
topsoil to achieve the specified coverage and thickness. Imported topsoil shall meet the
requirements of this Section.
3. Topsoil shall be a friable loam containing a large amount of humus and shall be original
surface soil of good rich, uniform quality, free from any material such as hard clods, stiff
clay, hardpan, partially disintegrated stone, lime, cement, cinders, slag, concrete,
bitumen or its residue, boards, stocks, chips, or other undesirable material harmful or
unnecessary to plant growth.
4. Topsoil shall be free from perennial weeds and shall not contain objectionable plant
material, toxic amounts of either acid or alkaline elements, or vegetable debris
undesirable or harmful to plant life.
5. Topsoil shall be natural topsoil without admixture of subsoil material, and shall be
classifiable as loam, silt loam, clay loam, sandy loam, or a combination thereof.
6. The pH of topsoil shall range from 5.5 to 7.0.
B. Fertilizer: Commercial fertilizer shall contain a labeled mix of (16-8-8) and contain the minimum
percentages (respectively) of (1) total nitrogen, (2) available phosphoric acid, and (3) water-
soluble potash. At least 50% of the nitrogen shall be from a slow-release source. Fertilizers
containing ammonium nitrate is not acceptable.
C. Seed Quality: Fresh, clean, new-crop seed labeled in accordance with the U.S. Department of
Agriculture Rules and Regulations, Federal Seed Act in effect on the date of bidding. Provide
seed of species, proportions, and minimum percentages of purity, germination, and maximum
percentage of weed seed as specified. Approval of all seed for use shall be based on the
accumulative total of PLS specified for each phase of work.
10-3
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 10 Seeding and Mulching February 9, 2024
D. Seed:
Table 10-1: Seed Mix Requirements by Type
2.3 Delivery
A. Furnish seed in sealed standard containers labeled with the producer’s name and seed
analysis. Remove from the site seed, which has become wet, moldy, or otherwise damaged in
transit.
PART 3 EXECUTION
3.1 Site Preparation
A. Any growth, rocks, or other obstructions, which might interfere with tilling, seeding, or later
maintenance operations, shall be removed and disposed of properly. Remove stones over
2 inches in any dimension and sticks, roots, rubbish, and other extraneous matter.
B. Areas to be seeded are to be graded to a rough texture capable of holding seed over sloped
surfaces. Roll and rake, remove ridges and fill depressions, to meet finish grades. Limit fine
grading to areas, which can be planted in the immediate future.
C. Moisten prepared areas before planting if the soil is dry. Water thoroughly and allow the surface
to dry before planting.
D. If prepared areas are eroded or otherwise disturbed after fine grading and prior to planting, they
shall be restored to specified condition prior to planting.
E. Immediately upon completion of construction, the grass shall be planted in all disturbed areas
and as designated in the Drawings. The method of planting shall be either hydroseeding or dry
seeding.
10-4
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 10 Seeding and Mulching February 9, 2024
C. The Contractor shall compact the overburden cap soil layer by tracking it with a minimum of two
passes of a CAT D-6 Dozer, or larger.
D. The finished surface of the overburden cap soil shall be free of stones, sticks, or other material
greater than 1 inch in any dimension.
E. The final surface of the overburden cap soil shall be graded in accordance with the Drawings.
F. The Contractor shall obtain the Engineer's acceptance of the final grade upon completion of
placing the overburden cap soil.
3.3 Fertilizing
A. The Contractor shall use a spreading device capable of uniformly distributing the fertilizer at a
rate of 600 pounds per acre.
B. The Contractor shall apply fertilizer in accordance with the manufacturer's instructions.
C. The fertilizer shall be applied after smooth raking of the overburden cap soil and within 48
hours of seeding.
D. The fertilizer shall be thoroughly mixed into 4 inches of overburden cap soil.
E. The Contractor shall lightly water the fertilized area immediately following application to aid the
dissipation of the fertilizer.
3.4 Seeding
A. The Contractor shall not use seed that is wet, moldy, or otherwise damaged.
B. The Contractor shall not conduct seeding operations, including fertilizing, seeding, and
mulching, when wind speeds exceed 15 miles per hour.
C. The Contractor shall employ satisfactory methods of sowing using power-driven drills or
seeders, mechanical hand seeders, or other approved equipment.
D. The Contractor shall stop work when satisfactory results cannot be obtained because of
drought, excessive moisture, or other factors. Resume work only when favorable conditions
develop.
E. After fertilizing and while the soil is loose and adequately moist to induce growth, uniformly
distribute seed and immediately mix into the seedbed to a depth of 1/2-inch using an approved
mechanical seed spreader.
3.5 Mulching
A. The Contractor shall immediately protect seeded areas against erosion by mulching.
B. Spread mulch as a continuous blanket using an application rate of two (2) tons per acre.
C. Only use undeteriorated mulch that can be readily cut into soil.
D. The mulch shall be free of Cogen grass and other nuisance species.
E. The Contractor shall protect seeded areas against traffic by erecting barricades and placing
warning signs.
F. Immediately following mulch spreading, the Contractor shall anchor the mulch using a rolling
10-5
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 10 Seeding and Mulching February 9, 2024
coulter or a wheatland land packer having wheels with V-shaped edges or similar equipment,
and in accordance with the requirements of Section 570 of the FDOT Standard Specifications
for Road and Bridge Construction.
10-6
SFM-11 CSA Above-Grade Embankment Construction Specifications Project No. 21471829-016-SPC-0
SECTION 11 Measurement and Payment February 9, 2024
PART 1 GENERAL
1.1 Scope
A. Measurement and Payment Terms provide as separate bid documents by the Owner.
11-1
wsp.com