PBPLUS OIL AND GAS LEARNING HUB

operation
of
the Daniel senior orifice fitting Training

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB
Call or WhatsApp 08152043309

TABLE OF CONTENT
1. Introduction to Differential Pressure Flow Measurement Principle
(Bernoulli's principle explained)
2. Orifice Plate Flanged Connection Installation
3. Component parts of the DOF
4. Standard Procedure for inserting an Orifice Plate in the DOF
5. Standard Procedure for the removal of the plate from the DOF
6. Video Demonstration

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB
operation
of
the Daniel senior orifice fitting

LEARNING OBJECTIVE
At the end of this training all participant should:
❖ Understand the principle behind Flow measurement by differential pressure
❖ List different differential pressure flow measurement devices
❖ Know the component parts of the DOF
❖ Demonstrate the ability to safely operate the Daniel Senior Orifice Fitting DOF
❖ Understand the advantages of the DOF

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB
operation
of
the Daniel senior orifice fitting
The Concept of Differential Pressure Flow Measurement

Rivers flow from places of


higher potential to a place of
lower potential.

No differential pressure NO
FLOW

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB
Call or WhatsApp 08152043309

Volumetric Flowrate and Bernolis Principle


The volumetric flow rate of the fluid can be determined by measuring the differential
pressure across a flow element.

The differential pressure can be caused by a restriction in the flow path

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB
operation
of
the Daniel senior orifice fitting
Bernoulli’s Principle
Bernoulli’s principle states that an increase in the speed of a fluid occurs simultaneously with a
decrease in pressure or a decrease in the fluid’s potential energy.

Explanation:
If the fluid is flowing through a horizontal pipe of
varying cross-sectional area, for example, the
fluid speeds up in constricted areas so that the
pressure the fluid exerts is least where the cross
section is smallest

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB
Call or WhatsApp 08152043309

Other Flow Restriction


Devices

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB

The Daniel Senior Orifice Fitting


The Daniel Senior Orifice Fitting is a dual-chamber
device that reigns as the most widely used means of
measurement for natural gas. ... The Senior Orifice
Fitting saves users time and money by providing a fast,
safe and simple method of changing orifice plates under
pressure without flow interruption.

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB

The Senior Daniel Orifice Fitting


The operator has always faced the challenge of removing
the orifice plate from the process for inspection,
changing the size during operation. This has always lead
to the shut down of the process.

The Senior Daniel orifice fitting has solved this long


time challenge. The senior Daniel orifice plate does not
require shutting down the process.
Just follow the Procedure as spelt out in this training

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB

Can we do it without process


interruption?

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB

The Daniel Senior Orifice Fitting components


1. The equalizing valve
2. The slide valve
3. lower plate carrier shaft
4. upper plate carrier shaft
5. The bleeder
6. The vent valve
7. The clamping bar
8. Clamping bar screw
9. Sealing bar
10. Sealing bar gasket
11. Plate carrier

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB

Procedure for installing an orifice plate


❖ Slip the Orifice plate into the grove in the plate carrier ❖ Open slide valve
❖ Insert the plate carrier into the upper chamber ❖ Rotate the upper plate carrier shaft
❖ Rotate the upper plate carrier shaft until the plate ❖ Rotate the lower plate carrier shaft
carrier touches the slide valve ❖ Close the slide valve
❖ Insert the sealing bar gasket ❖ Close the equalizing valve
❖ Insert the sealing bar ❖ Open the bleeder valve
❖ Insert the clamping bar ❖ Close the bleeder valve
❖ Tighten the clamping bar screw
❖ Close bleeder or vent valve
❖ Open equalizing valve

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB

Procedure to remove the orifice plate.

❖ Open equalizing valve


❖ Open slide valve
❖ Rotate the lower plate carrier shaft
❖ Rotate the upper plate carrier shaft
❖ Close slide valve
❖ Close equalizing valve
❖ Open the bleeder or vent valve

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB

Procedure to remove an orifice plate

❖ Loosen top plate clamping bar screw


❖ Remove top plate clamping bar

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB

❖ Remove the sealing bar


❖ Remove the sealing bar gasket
❖ Remove the plate carrier

www.pbplusoilandgas.com
PBPLUS OIL AND GAS LEARNING HUB

Call or WhatsApp

08152043309

THE END