Professional Documents
Culture Documents
Calculadora del costo total de propiedad (TCO) _ Microsoft Azure
Calculadora del costo total de propiedad (TCO) _ Microsoft Azure
Calcule los ahorros de costos que puede realizar migrando sus cargas de trabajo a Azure
Savings from running workloads in Azure accrue over time. The following shows how those
savings add up over years.
1.4M
1.2M
1M
800K
600K
400K
200K
USD 1,502,919
Total cost USD 727,689
Total cost
Chatee con el personal de ventas
5% 0%
70% Data 15% 1% 9% 61% Data 0% 20% 19%
Compute center Networking Storage IT Labor Compute center Networking Storage IT Labor
600K
400K
400K
200K
200K
USD 1,502,919
Cost over 3 year(s) USD 727,689
Cost over 3 year(s)
Hardware cost
Virtual Machines cost
Virtual machine density -
Number of virtual cores that 3
can be created per physical Number of hours per month 730
core
F8sv2 Standard (8 core, 16 GB SKU# AAD-
Cost per 4 proc 32 core, 2000 RAM) Windows (Azure Hybrid 10155
GB RAM virtualization server USD 98,785.00 Benefit)
for Windows Number of virtual machines 50
Number of servers needed Total virtual machine cost per USD 5,059.50
for 50 virtual machine(s) - 8 2 month
core, 16 GB RAM
F8sv2 Standard (8 core, 16 GB SKU# AAD-
Cost per 2 proc 32 core, 1000 RAM) Linux 10188
GB RAM virtualization server USD 35,365.00 Number of virtual machines 20
for Linux Total virtual machine cost per USD 2,023.80
Number of servers needed month
for 20 virtual machine(s) - 8 1
core, 16 GB RAM F8sv2 Standard (8 core, 16 GB SKU# AAD-
RAM) Linux 10188
Cost per 4 proc 32 core, 2000 Number of virtual machines 50
GB RAM virtualization server USD 98,785.00 Total virtual machine cost per USD 5,059.50
for Linux month
Number of servers needed
for 50 virtual machine(s) - 8 2
core, 16 GB RAM
Total Azure Virtual Machines
cost USD 437,140.80
Cost per 1 proc 1 core, 0.75 GB
RAM virtualization server for USD 1,173.00
Windows NOTE: For Azure compute costs, one 3 year
Number of servers needed Reserved VM in use.
for 1 virtual machine(s) - 4 1
core, 1 GB RAM
SQL Database cost
Total cost for virtualization
server(s) USD 431,678.00
General Purpose Single Gen5 2 USD 0.13972
Cost of maintaining vCores (Azure Hybrid Benefit) /hr
virtualization server(s) - 20% of USD 86,335.60 SKU# AAD-
cost of virtualization server(s) 17823
Instance Count 1
Total cost of maintaining
server(s) over three year(s) USD 259,006.80 Cost Per Month USD 102.00
Total hardware cost over three Total SQL Database cost over USD 3,672.00
USD 690,684.80 three year(s)
year(s)
Electricity cost
Virtualization cost
Chatee con el personal de ventas
Virtualization software license USD 10,144.00
cost
Per virtual machine, per month,
cost to load balance, backup USD 26.52
and patch virtual machines
Number of virtual machines 121
Virtual machine management
cost per month USD 3,208.92
Storage cost
Networking cost
Azure networking cost
Storage cost
Azure storage cost
Hardware
Page Blob storage
Local Disk/SAN-HDD
Cost per GB USD 0.20
Storage (RAID 10 Usable storage volume in GB 30,720
61,440 Chatee con el personal de ventas
configuration) volume in GB Storage cost per GB/month USD 0.045
g )
Annual storage cost per usable
Total storage procurement volume USD 16,588.80
USD 12,288.00
cost
IT labor cost
Azure IT labor cost