Professional Documents
Culture Documents
VMC650 Operation manual
VMC650 Operation manual
MODEL :
SER.NO.:
DAT E :
This machine tool is a vertical machining center with high rigidity; the
Z three-axis control; it can process all kinds of complex small and medium-sized
This machine tool is used for single-piece and mass production of various
mold manufacturing process. Ideal machine tool for various complex cavities.
Using this machine tool can simplify the process, improve work efficiency, and
According to the characteristics of our machine tool, it has a very long life,
but its faults must be paid attention to and eliminated. Therefore, before
operation, be sure to read the manual carefully to ensure safe operation and
Please count the accessories according to the packing list and check if there
2. Lifting installation:
2.1 There are two eyebolts on the base of the machine tool and the top of
the column, which can be lifted by inserting the steel rope. When lifting, use
2.2 There are anchor screw holes on the base of the machine tool. The
machine tool must be installed on a solid concrete foundation, and the level of
each point must be ensured. After the anchor bolts are tightened, the
2.3 When the machine tool leaves the factory, the limit position of each
motion axis, the screw nut clearance, and the screw in each direction have
the machine tool and cause damage to the machine tool or personal injury.
Figure 2-1 Lifting diagram
3. Specifications and parameters of the machine tool:
Specifications Units VMC650
T slot(number-width-pitch) 3-18x125
24/24/20
X/Y/Z rapid traverse speed m/min
(Optional:48/48/36 )
Max.tool weight kg 8
4.1 The main transmission system adopts the frequency conversion speed
regulation system to realize the stepless speed regulation of the main shaft, and
The feed motions of the machine tool in X, Y, and Z directions are all directly
The tool of this machine tool is replaced by pneumatic tool changer, and the
top of the spindle hole at the front of the spindle box is equipped with a
This machine tool adopts centralized automatic oil supply lubrication, and
the centralized lubricating oil pump regularly supplies oil. Each lubrication point
① After the machine tool is installed, first raise the spindle box up a bit,
remove the support bar that supports the spindle, clean the anti-rust grease,
and check whether each part is damaged or abnormal. Add No. 68 rail oil to the
lubrication pump. After the lubrication points are fully lubricated, the machine
can be tested.
② Before the machine is put into use for the first time, the lubricator in the
pneumatic system needs to be filled with about 1/2 the volume of the oil cup
(for the cylinder piston). It is recommended to use ISOVG32 or the same grade
oil to avoid damage to the machine tool accuracy and cause damage to the
This machine tool has been debugged before leaving the factory and
passed the inspection, and the user does not need to readjust it. When the
machine tool has been working for a long time, due to various reasons, the
backlash of the lead screw, the positioning accuracy of the machine tool, and
the repeat positioning accuracy are out of tolerance. At this time, the following
Move the moving part to the middle position of the stroke, loosen the
fixing screw of the motor, remove the motor, loosen the screw 1 (3 pieces) on
the precision lock nut 2, and lock the precision lock nut 2, and then lock the
After locking the precision locking nut 2, tighten the locking screw 1 (3
pieces) to achieve the pre-tension of the ball screw, as shown in Figure 6-1.
图5-1 润滑系统示意图
function of the CNC system. For the specific operation method, please refer to
In order to ensure the accuracy and life of the machine tool for a long time,
attention must be paid to the cleaning and lubrication of all parts of the
machine tool, especially the linear guide rails in all directions of the machine
tool. Although the all-directional screw is protected by the guide rail guard, it
should be cleaned frequently to keep the guide rail clean, and the lubrication of
the guide rail should be observed frequently, and the blockage should be dealt
with immediately. Keep the guide rails and lead screws sufficiently lubricated to
avoid abrasion. You should also pay attention to the oil storage in the
The machine passes the inspection and is allowed to leave the factory.
SER.NO.:
INSPECTORS:
DATE:
Totally enclosed
6 1 set on the machine
protection
Certificate of
15 1 box
Compliance
CNC system
16 1 box
operation