A. DOCKING
1. Vessel arrived and Anchored at IMC Shipyard Anchorage on 16 th Oct 2022, 1206 Hrs
2. Transit Draft (FW): 6.60 mtr (F) / 7.60 mtr (A)
3. V/L Condition : In Ballast
4. Last Cargo: Palm Oil
5. COT Condition: All Gas free, no slops on board.
6. Last Port: Zhangjiagang, China
7. Next Port: TBC
8. Security Level: 1 (One)
1812 : SBE
1900 : Anchor up
2306 : Anchor down
2324 : FWE
1400-1430: Sample for 1st PCR test collected from all crew
Shifting Xiushandong Anchorage to Xiushanshan Anchorage
1448 : SBE
1512 : Anchor up
1700 : Anchor down
1718 : FWE
1225-1245: Sample for 2nd PCR test collected from all crew
14-Oct-2022: 3rd PCR test & Shifting Xiushanshan Anchorage to Xiazhimen Outer
anchorage
0930-1000: Sample for 3rd PCR test collected from all crew
1100 : SBE
1130 : Anchor up
1554 : Anchor down
1612 : FWE
0500 : SBE
0530 : Anchor up
0920 : POB (01 nos)
1020 : Vessel at Mazhi Anchorage No. 2
1020 : Pilot informs that awaiting confirmation from VTS to drop Anchor.
1020-1055: Vessel awaiting confirmation from VTS to drop Anchor.
1055 : VTS informs no Anchoring instruction, vessel to proceed to outer Anchorage,
Zhoushan
1055 : Vessel under Pilotage, proceeding to outer Anchorage, Zhoushan.
1200 : Pilot away
1730 : Anchor down
1754 : FWE
0700 : SBE
0730 : Anchor up
1036 : POB (01 nos.)
1124 : Tug Master on board (02 nos.)
1125 : Pilot away
1206 : Anchor Down
1224 : FWE
1230 : Tug Master away
0824 : SBE
0815 : Shipyard Pilot on board (01 nos)
0815 : Safety Inspector on board (02 nos.)
0824 ; Fwd and Aft Tug made fast
(No. of Tugs- 02 nos.)
0900 : Anchor up
0912 : First Line Ashore
0912 : FWE
0936 : All fast, Double banked to “REINHOLD SCHULTE , Stbd side alongside, with
moorings (4+2) Fwd and Aft
0936 : Fwd and Aft Tug cast off and away
0940 : Gangway Down
0940 : Shipyard Pilot away
0940 : Safety Inspector away
1318 : SBE
1320 : POB (01 nos)
1335 : Fwd and Aft Tug made fast
(No. of Tugs -03 nos)
1336 : Commence Unmooring
1348 : Completed Unmooring
1415 : Fwd and Tug cast off and Away
1418 : BOW entered Dock
1430 : Stern inside the dock
1450 : Dock gate closed
1455 : Commence pumping out dock water
1500 : Pilot away
1555 : vessel seated on blocks safely
1530 : Completed pumping out dock water
Vessel riding to her Port Anchor BUT 4 shackles on deck, In Position Lat 29 55.95’N, Long.
122 15.18’ E, at “IMC Shipyard Anchorage”, Zhoushan, China.
Vessel all made fast, double-banked to “Reinhold Schulte”, stbd side along side, with
moorings (4+2) Fwd and Aft each, at Berth # 2, IMC Shipyard, Zhoushan, China.
11-Dec-2022
Vessel riding to her Stbd Anchor , BUT 3 shackles in water, In Position Lat 29 56.05’N, Long.
122 15.53’ E, at “IMC Shipyard Anchorage”, Zhoushan, China.
11-Dec-2022
Vessel all made fast, stbd side along side, with moorings (4+2) Fwd and Aft each, at Berth #
2, IMC Shipyard, Zhoushan, China.
14-Dec-2022
ROB @ FWE
VLSFO- 120.82 MT, LSMGO- 7.50 MT, LO- 43534 Ltrs, FW- 470 MT
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909
Vessel riding to her Stbd Anchor BUT 5 shackles outside Hose pipe, In Position Lat 30
08.79’N, Long. 122 15.63’ E, at “Xiushandong anchorage 7# , Zhoushan, China”.
Bunker Operation
15-Dec-2022
0730 : Bunker Barge “YI DA 11” stbd side along side
0850 : Hose connected- LSMGO (1 x 6 inches)
0850 : Hose connected- VLSFO (1 x 8 inches)
1010 : Commence bunkering (LSMGO)
1115 : Completed bunkering (LSMGO)
1115 : Commence bunkering (VLSFO)
1245 : Completed bunkering (VLSFO)
1354 : Hose disconnected- LSMGO
1354 : Hose disconnected- VLSFO
1430 : Bunker Barge “YI DA 11” away
Quantity received:
LSMGO: 58.50MT
VLSFO: 391.80 MT
15-Dec-2022
1710 : Traffic boat Zhou Bo 2 alongside
1712 : Traffic boat Zhou Bo 2 sailed
1800 : SBE
ROB @ SBE
DEP FO/DO/LO/FW: 512.62 MT/63.0 MT/ 43536 Ltrs
DEP DRAFT: Fwd-7.50m, Aft- 8.50m
15-Dec-2022
1800 : SBE
1818 : Anchor Up
2236 : Vessel out of ECA Area
2318 : Anchor Down
2342 : FWE
ROB @ FWE
VLSFO- 512.62 MT, LSMGO- 61.20 MT, LO- 43477 Ltrs, FW- 470 MT
Vessel riding to her Stbd Anchor BUT 7 shackles on deck, In Position Lat 29 58.42’N, Long.
123 10.79’ E, at “Outside ECA Area, Outside Port limit Zhoushan, China”.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909
Vessel moored alongside after undocking for continuation of cargo tanks and ballast tanks
coating repairs.
Vessel used shore power during dry-docking period due repairs to AE and economical reasons.
Owners Representative
1. Nishant Mane - Fleet Superintendent
2. Xue Ruhua - Fleet Superintendent
3. Capt. Zhang Jin Gang - Fleet Superintendent
ABS Representative
1. Li Fei - ABS Nantong surveyor
2. Shen Jianping - ABS Nantong surveyor
Shipyard Representative
Hull cleaning/blasting/painting was carried out as per the specification in presence of PPG paint
inspector.
Flat bottom area coated 4900m2. Entire area was high pressure washed and hand scrapped. One
full seal coat applied, as its condition is satisfied
Vertical bottom area coated 4600m2.Entire area was high pressure washed and 25% SA2
blasted. Two touch up and two full coat antifouling was applied.
Topside area coated 2500m2. Entire area was high pressure washed and blasted 12-14mtrs
height. Two touch up and one full coat applied.
SigmaCover 380
SigmaCover 555
SailAdvance RX
C. RUDDER
Remarks: Rudder pintle bushes clearances taken with the help of feeler gauge, found well within
limits.
Installed new inspection hole and plug for Rudder lower pintle nut
D. PROPELLER SHAFT
Wear Down present readings T:56.70 / B:55.60 (T: 56.65 / B: 55.75 - Aug
2020)
Original readings at time of delivery 54.0
Whether Withdrawn For Survey No
Whether Crack-Detected No
Stern Tube Condition Good
(Ferro-form type)
Remarks: Propeller drop measured with poker gauge, found well within limits.
WORKING PROPELLER
Remarks: Non-destructive test (dye check) carried out, found in good condition, propeller polishing
carried out.
E. SEA CHESTS
No of Sea Chest 5
F. CATHODIC PROTECTION
REMARKS: Anode surrounding area was blasted to Sa 2.5 and coated with anode shield epoxy putty.
ICCP System tested & serviced by service engineer in Drydock.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909
H. SEA VALVES
Remarks: 2 NO.S Sea water overboard valves A/C pump and Fire & Foam pump renewed . Other All
valves o’hauled as per the specifications. OWS Overboard valve and Boiler Blowdown overboard
valves and sea chest valves removed from place and Gaskets renewed.
UT gauging carried out on board and following steel platings renewed as per attending ABS CAP
Surveyor recommendations. The water tightness integrity and strength of the renewed tank boundaries
have been verified by hydrostatic testing.
To meet CAP 1 requirement, approximate 15 t steel renewed in different WBTs and on Main deck.
Main Deck
Please refer to CAP report and UT gauging report.
WBT
Pls refer to CAP report and UT gauging report.
K. DECK REPAIR
BALLAST TANK:
Please refer to the attached yard work done list. Partially blasting and recoating in 7W and Power tooling in
other ballast tanks.
PIPELINES:
Please refer to the attached yard work done list. Various pipes line renewed on deck including the hydraulic
pipe, Air pipe, FW pipe, steam pipe. Lagging of steam in FW pipe were renewed.
SAFETY EQUIPMENT:
1. 46 nos. immersion suits and 03 nos. IBC Chemical suits annual servicing carried out by shore
workshop.
2. Fixed CO2 system 101 Cylinders hydro tested by shore workshop.
3. 03 nos. UTI tapes annual servicing and calibration carried out.
4. Wasted fire / foam lines renewed at various location.
5. Wasted angle supports and U-clamps for fire / foam lines renewed at various location.
6. 02 nos. Embarkation ladder stowage angle supports renewed.
7. Various sprinklers nozzles renewed in fwd / aft paint locker, Chemical sample locker and IG
room.
8. Various gas detectors, one compound pressure gauge calibration.
9. Pressure and temperature calibrator serviced and calibrated.
10. Fixed Foam system 5 Yearly test and inspection done.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909
11. Fire control station and fittings general service carried out;
12. Incinerator refractory patch up work carried out.
13. OWS chamber new relief valve fitted.
1. Brake lining renewed for all windlass and testing done for all winches and both the windlass.
2. Windlass Port side hydraulic motor overhauled
3. STBD windlass were removed from place to yard work shop. Gear case box removed, bearing and
bushes renewed, shaft reconditioned and winch assembly installed back in place.
4. Windlass Port and Stbd side hydraulic brakes overhauled, Control block inlet and outlet hydraulic
pipes renewed. hydraulic inlet valves renewed
5. Both the Anchors & Anchor cables cleaned and shackles marked
6. Windlass and moor winches gear box inspection carried out and gear oil renewed.
NAVIGATION BRIDGE:
MISCELLANEOUS JOBS:
1. All PV valves were overhauled and tested.
2. All Cranes Load tested. Midship crane & both provision crane wire renewed. / limit switches for
midship crane renewed.
3. Whole of main deck area under manifold including longitudinal and transverse frames hydro
blasted cleaned and painted.
4. The supports on gangway and Gangway platform renewed.
5. Accommodation and funnel areas high pressure washed, power tooled and painted.
6. Electrical cables supporting clamps and support bases renewal on main deck and accommodation
outside.
7. 8 nos of Overhauling of Manifold Valves
8. Fwd and Aft tank cleaning heater cleaned and repaired at Yard.
9. 24 nos Tank cleaning machines overhauled by yard and shore work shop;
10. 2nd off cabin bathroom tiles Renewed .
11. Curtains and Sofa covers renewed in Crew smoke room and various cabins.
12. Manifold and catwalk gratings renewed at various places.
13. Butterworth side plating renewed for various cargo tanks
14. Various steps and catwalk gratings renewed
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909
15. Hydraulic branch pipelines on deck renewed for 1W,2W,3W,4W,5W,6S,7W,&8W cargo tanks,
flanges in good condition reused.
16. Fire line renewed renewed at various locations.
17. Main & return stream line and expansion joints renewed at various locations.
18. HFO & LSMGO defective pipe lines renewed
19. Various cabins and bridge wooden fittings repaired inside accommodation,
20. New PA system & talkback system installed.
21. 2 nos. additional light for anchor station installed on forward mast.
L. ENGINE
MAIN ENGINE
10. ME pneumatic control system valves and lubricator actuators overhauled by JUNMA
11. ME chain guide bars AFT 4 no.s and FWD moment compensator 2no.s renewed by JUNMA.
BOILERS
1. Both Boilers main steam valves and mountings overhauled and both sides gaskets renewed;
2. Both Aux. boilers and E.G.B safety valves overhauled.
3. Port and Starboard boilers water and exhaust side cleaned.
4. Both aux. Boilers and EGB survey carried out by ABS surveyor.
26. Bilge overboard and boiler blowdown valve removed from place , overhauled and fitted back in
place after survey,
27. Various tanks inside ER cleaned for Special survey.
GENERATORS
HEAT EXCHANGERS
1. FO Sludge Tank
2. Bilge Water Tank
3. ME LO Settling Tank
4. Boiler Water Tank
5. LT Expansion Tank
6. HT Expansion Tank
7. Incinerator SD Tank
8. Incinerator Sludge Tank
9. Waste Oil Tank
10. ME Scavenge Box Drain Tank
11. LSFO Centre Tank
12. FOT port tank
13. FOT stbd tank
14. ME Cofferdam cleaning and inspection
15. DO Storage Tank (port)
16. ME L.O sump tank
17. F.O drain tank
18. L.O sludge tank
19. F.O service tank
20. F.O settling tank.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909
1.Accommodation AC plant no 2 unit evaporator unit renewed. System pressure and vacuum tested.
2. Accommodation AC condenser end covers renewed.
3. ECR Ac condenser end cover renewed.
M. ELECTRICAL EQUIPMENT
Below motors overhauled by yard and bearings renewed, dynamic balancing done where applicable
N. MISCELLANEOUS
SURVEYS
The 4th intermediate Survey carried out and certificates issued by the ABS Class Surveyor.
CAP 1 Survey carried out and completed on board, reports submitted to ABS Houston office for review and
assignment of CAP rating. EST 15T of steel renewed as per UT gauging carried out on board under ABS
Surveyor guidance.