IMC Ship Management Pte. Ltd.

3 Anson Road, #06-01 Springleaf Tower,


Singapore 079909

MARITIME VANESSA DRYDOCKING REPORT


(18/Oct/2022 – 14/Dec/2022)

DATE 14-DEC-2022
SHIP’S NAME MARITIME VANESSA
END OF VOYAGE NO 20220006VC
LAST PORT OF CALL Zhangjiagang, China
NEXT PORT OF CALL Dalian, China
SHIPYARD IMC Shipyard, Zhoushan, China
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

A. DOCKING

1) Vessel arrival drydock timings

1. Vessel arrived and Anchored at IMC Shipyard Anchorage on 16 th Oct 2022, 1206 Hrs
2. Transit Draft (FW): 6.60 mtr (F) / 7.60 mtr (A)
3. V/L Condition : In Ballast
4. Last Cargo: Palm Oil
5. COT Condition: All Gas free, no slops on board.
6. Last Port: Zhangjiagang, China
7. Next Port: TBC
8. Security Level: 1 (One)

06-Oct-2022: Arrival Outer Anchorage, Zhoushan, China

1212 : SBE/ EOSP


1354 : Anchor Down
1418 : FWE

11-Oct-2022: Shifting Xiazhi Outer Anchorage to Xiushandong Anchorage

1812 : SBE
1900 : Anchor up
2306 : Anchor down
2324 : FWE

12-Oct-2022: 1st PCR test

1400-1430: Sample for 1st PCR test collected from all crew
Shifting Xiushandong Anchorage to Xiushanshan Anchorage
1448 : SBE
1512 : Anchor up
1700 : Anchor down
1718 : FWE

13-Oct-2022: 2nd PCR test

1225-1245: Sample for 2nd PCR test collected from all crew

14-Oct-2022: 3rd PCR test & Shifting Xiushanshan Anchorage to Xiazhimen Outer
anchorage

0930-1000: Sample for 3rd PCR test collected from all crew
1100 : SBE
1130 : Anchor up
1554 : Anchor down
1612 : FWE

15-Oct-2022: Shifting Xiazhimen Outer anchorage to Mazhi Anchorage to


Xiazhimen Outer anchorage
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

0500 : SBE
0530 : Anchor up
0920 : POB (01 nos)
1020 : Vessel at Mazhi Anchorage No. 2
1020 : Pilot informs that awaiting confirmation from VTS to drop Anchor.
1020-1055: Vessel awaiting confirmation from VTS to drop Anchor.
1055 : VTS informs no Anchoring instruction, vessel to proceed to outer Anchorage,
Zhoushan
1055 : Vessel under Pilotage, proceeding to outer Anchorage, Zhoushan.
1200 : Pilot away
1730 : Anchor down
1754 : FWE

16-Oct-2022: Shifting Xiazhimen Outer anchorage to IMC Shipyard Anchorage

0700 : SBE
0730 : Anchor up
1036 : POB (01 nos.)
1124 : Tug Master on board (02 nos.)
1125 : Pilot away
1206 : Anchor Down
1224 : FWE
1230 : Tug Master away

18-Oct-2022: Shifting IMC Shipyard Anchorage to IMC Shipyard Berth # 2

0824 : SBE
0815 : Shipyard Pilot on board (01 nos)
0815 : Safety Inspector on board (02 nos.)
0824 ; Fwd and Aft Tug made fast
(No. of Tugs- 02 nos.)
0900 : Anchor up
0912 : First Line Ashore
0912 : FWE
0936 : All fast, Double banked to “REINHOLD SCHULTE , Stbd side alongside, with
moorings (4+2) Fwd and Aft
0936 : Fwd and Aft Tug cast off and away
0940 : Gangway Down
0940 : Shipyard Pilot away
0940 : Safety Inspector away

19-Oct-2022: Shifting IMC Shipyard Berth # 2 to Berth # 3

1325 : Shipyard Pilot on board (01 nos)


1342 : Fwd, Aft and Centre Tug made fast
(No. of Tugs- 03 nos.)
1342 : Commence Unmooring
1348 : Completed Unmooring @ Berth # 2
1400 : First Line Ashore @ Berth # 3
1412 : All fast Stbd side alongside, with moorings (4+2) Fwd and Aft
1412 : Fwd, Aft and Centre Tug cast off and away
1415 : Shipyard Pilot away
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

29-Nov-2022: Shifting IMC Shipyard Berth # 3 to Dock

1318 : SBE
1320 : POB (01 nos)
1335 : Fwd and Aft Tug made fast
(No. of Tugs -03 nos)
1336 : Commence Unmooring
1348 : Completed Unmooring
1415 : Fwd and Tug cast off and Away
1418 : BOW entered Dock
1430 : Stern inside the dock
1450 : Dock gate closed
1455 : Commence pumping out dock water
1500 : Pilot away
1555 : vessel seated on blocks safely
1530 : Completed pumping out dock water

08-Dec-2022: Undocking- Shifting Dock to IMC Shipyard Anchorage


Cold Movement
0800 : SBE
0800 : Commence flooding Docks
0830 : POB (01 nos)
0848 : Vessel afloat
0948 : Completed Flooding
1000 : Dock Gate opened
1000 : Commence unmooring
1000 : Tugs SBE
(No. of Tugs -03 nos)
1010 : Aft Tug made fast
1020 : Commence moving out of dock
1024 : Stern out of dock
1030 : Bow out of dock
1035 : 2nd Tug made fast at Stbd quarter
1036 : Completed Unmooring, All lines on board
1042 : Aft Tug cast off and away
1048 : Anchor Down
1054 : Fwd and Stbd quarter Tug cast off and away
1054 : All three Tugs away

Vessel riding to her Port Anchor BUT 4 shackles on deck, In Position Lat 29 55.95’N, Long.
122 15.18’ E, at “IMC Shipyard Anchorage”, Zhoushan, China.

08-Dec-2022: Shifting IMC Shipyard Anchorage to Berth # 2


Cold Movement
1142 : Fwd and Aft Tug made fast
(No. of Tugs -03 nos)
1206 : Anchor up
1218 : Commence mooring
1242 : Completed mooring, All Fast.
1242 : Fwd and Aft Tug cast off and Away
1242 : Pilot away
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

Vessel all made fast, double-banked to “Reinhold Schulte”, stbd side along side, with
moorings (4+2) Fwd and Aft each, at Berth # 2, IMC Shipyard, Zhoushan, China.

11-Dec-2022

Shifting Berth # 2 to IMC Shipyard Anchorage


0812 : SBE
0800 : POB (01 nos)
1000 : Fwd and Aft Tug made fast
(No. of Tugs - 02 nos)
0812 : Commence Unmooring
0824 : Completed Unmooring, All lines on board
0836 : Anchor Down
0836 : Fwd and Aft Tug cast off and Away

Vessel riding to her Stbd Anchor , BUT 3 shackles in water, In Position Lat 29 56.05’N, Long.
122 15.53’ E, at “IMC Shipyard Anchorage”, Zhoushan, China.

11-Dec-2022

Shifting IMC Shipyard Anchorage to Berth # 2


0936 : Fwd and Aft Tug made fast
(No. of Tugs - 02 nos)
0942 : Anchor up
1000 : Commence mooring
1012 : Completed mooring, All Fast.
1012 : Fwd and Aft Tug cast off and Away
1012 : Pilot away
1012 : FWE

Vessel all made fast, stbd side along side, with moorings (4+2) Fwd and Aft each, at Berth #
2, IMC Shipyard, Zhoushan, China.

14-Dec-2022

Departure IMC Shipyard Berth # 2


0930 : Dock POB (01 nos.)
0942 : SBE
0942 : Fwd and Aft Tug made fast
(No. of Tugs -02 nos.)
0942 : Commence unmooring
0954 : Completed Unmooring, All lines on board
0954-1018: Departure Dock Sea Trial carried out
1006 : Fwd and Aft Tug cast off and away
1018 : Sea POB (01 nos.)
1030 : Dock Pilot Away, Superintendent, SRM, Owner Representative Away
1130 : Sea Pilot Away
1806 : Anchor Down
1824 : FWE

ROB @ FWE
VLSFO- 120.82 MT, LSMGO- 7.50 MT, LO- 43534 Ltrs, FW- 470 MT
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

Vessel riding to her Stbd Anchor BUT 5 shackles outside Hose pipe, In Position Lat 30
08.79’N, Long. 122 15.63’ E, at “Xiushandong anchorage 7# , Zhoushan, China”.

Bunker Operation

15-Dec-2022
0730 : Bunker Barge “YI DA 11” stbd side along side
0850 : Hose connected- LSMGO (1 x 6 inches)
0850 : Hose connected- VLSFO (1 x 8 inches)
1010 : Commence bunkering (LSMGO)
1115 : Completed bunkering (LSMGO)
1115 : Commence bunkering (VLSFO)
1245 : Completed bunkering (VLSFO)
1354 : Hose disconnected- LSMGO
1354 : Hose disconnected- VLSFO
1430 : Bunker Barge “YI DA 11” away

Quantity received:
LSMGO: 58.50MT
VLSFO: 391.80 MT

15-Dec-2022
1710 : Traffic boat Zhou Bo 2 alongside
1712 : Traffic boat Zhou Bo 2 sailed
1800 : SBE

ROB @ SBE
DEP FO/DO/LO/FW: 512.62 MT/63.0 MT/ 43536 Ltrs
DEP DRAFT: Fwd-7.50m, Aft- 8.50m

15-Dec-2022
1800 : SBE
1818 : Anchor Up
2236 : Vessel out of ECA Area
2318 : Anchor Down
2342 : FWE

ROB @ FWE
VLSFO- 512.62 MT, LSMGO- 61.20 MT, LO- 43477 Ltrs, FW- 470 MT

Vessel riding to her Stbd Anchor BUT 7 shackles on deck, In Position Lat 29 58.42’N, Long.
123 10.79’ E, at “Outside ECA Area, Outside Port limit Zhoushan, China”.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

ROB at time of delivery asf: ROB at time of Re-delivery asf:


VLSFO: 120.82 MT VLSFO: 505.0 MT
LSMGO: 97.15 MT LSMGO: 61.2 MT
LO: 42668 L LO: 43471 L

3) If vessel moored alongside after undocking, please explain.

Vessel moored alongside after undocking for continuation of cargo tanks and ballast tanks
coating repairs.

4) Vessel docked without own power due to:

Vessel used shore power during dry-docking period due repairs to AE and economical reasons.

SURVEYORS AND OWNER’S REPRESENTATIVE PRESENT

Owners Representative
1. Nishant Mane - Fleet Superintendent
2. Xue Ruhua - Fleet Superintendent
3. Capt. Zhang Jin Gang - Fleet Superintendent

ABS Representative
1. Li Fei - ABS Nantong surveyor
2. Shen Jianping - ABS Nantong surveyor

Shipyard Representative

1. Xiong Sheng - Business Manager


2. Hejing - Ship Repair Manager

B. HULL CLEANING / BLASTING / PAINTING

Hull cleaning/blasting/painting was carried out as per the specification in presence of PPG paint
inspector.

Flat bottom area coated 4900m2. Entire area was high pressure washed and hand scrapped. One
full seal coat applied, as its condition is satisfied

Vertical bottom area coated 4600m2.Entire area was high pressure washed and 25% SA2
blasted. Two touch up and two full coat antifouling was applied.

Topside area coated 2500m2. Entire area was high pressure washed and blasted 12-14mtrs
height. Two touch up and one full coat applied.

36 Months paint specification used


IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

COATINGS USED ARE AS FOLLOWS:

SigmaCover 380
SigmaCover 555
SailAdvance RX

C. RUDDER

Type Semi- Balanced


Upper Pintle Clearance 1.45 mm
(Max limit 5.96 mm)
Lower Pintle Clearance 1.75 mm
(Max limit 5.96 mm)
Condition GOOD
Whether Lifted NO
Repair Done No
Whether Anodes Renewed YES
Whether Pintle Bushes Remetalled NO

Remarks: Rudder pintle bushes clearances taken with the help of feeler gauge, found well within
limits.
Installed new inspection hole and plug for Rudder lower pintle nut

D. PROPELLER SHAFT

Survey Date of Withdrawal 08/2020

Wear Down present readings T:56.70 / B:55.60 (T: 56.65 / B: 55.75 - Aug
2020)
Original readings at time of delivery 54.0
Whether Withdrawn For Survey No
Whether Crack-Detected No
Stern Tube Condition Good
(Ferro-form type)

Remarks: Propeller drop measured with poker gauge, found well within limits.

Stern tube aft seals vacuum test carried out, satisfactory.


IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

WORKING PROPELLER

Dye Check on blade edges, hub.

Material/Type Ni Al Bronze(Trade name Cu3)


Condition of Blades Good
Extent of Damage, If Any None
Whether Changed No
Repair Effected No
Whether Seals Renewed No
Rope Guard Repaired, Removed and Refitted
Sacrificial Anodes Replaced Yes

Remarks: Non-destructive test (dye check) carried out, found in good condition, propeller polishing
carried out.

E. SEA CHESTS

No of Sea Chest 5

Grating opened, blasted, painted YES


Anodes Renewed YES
No and Size of Zinc Anodes 4 X 12

Remarks: Old anodes found in wasted condition. All anodes renewed.

F. CATHODIC PROTECTION

Blasting 2 m dia around anodes. Application of coating.

Type/ Brand ICCP/JOTUN


Total No. of Anode 4 Permanent Anodes were renewed
and Reference anodes inspected.
Whether Cathodic Reaction Taking Place Yes

REMARKS: Anode surrounding area was blasted to Sa 2.5 and coated with anode shield epoxy putty.
ICCP System tested & serviced by service engineer in Drydock.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

G. ANCHORS & CABLES

Whether Ranged YES


Whether shackles pins backed out & 1st NO
two length reversed to chain locker
Original size of Chain 73
Wear Down Limit (Allowable 64.24mm) 70.0 mm Port side./68.0 mm Stbd side. (Avg)
Mean Wear Down Port/Stb Chain 10%
Condition of Anchors GOOD
Condition of Cables GOOD
Cable Chain renewed, (Specify) YES, 1 Nos. Port Chain and 2Nos.
Starboard Chain
Repairs Done NO
Location of Spare Anchor Forecastle deck Stbd side

Remarks: Anchors & cables high pressure washed, cleaned.


Lengths Starboard side anchor chains No.1,2 were renewed at this time.
Lengths Port side anchor chains No.1, were renewed at this time.

H. SEA VALVES

Sea valves Overhauled YES


Nos of valves overhauled All ship side valves
Sea Valves Coated with Apexior no.3 Yes

Remarks: 2 NO.S Sea water overboard valves A/C pump and Fire & Foam pump renewed . Other All
valves o’hauled as per the specifications. OWS Overboard valve and Boiler Blowdown overboard
valves and sea chest valves removed from place and Gaskets renewed.

I. HULL DAMAGE REPAIRS

UT gauging carried out on board and following steel platings renewed as per attending ABS CAP
Surveyor recommendations. The water tightness integrity and strength of the renewed tank boundaries
have been verified by hydrostatic testing.

To meet CAP 1 requirement, approximate 15 t steel renewed in different WBTs and on Main deck.

Main Deck
Please refer to CAP report and UT gauging report.

WBT
Pls refer to CAP report and UT gauging report.

J. CARGO TANKS and BALLAST TANKS


IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

3 cargo tanks ( 9w, 7s ) full re-coated.


6 cargo tanks (1P, 3P, 3S , 5S , Slop P & Slop S) partially coated.
8 cargo tanks (2S, 4P, 4S, 6P, 6S,7P, 8P & 8S) Power tooling & coated.

K. DECK REPAIR

JOBS CARRIED OUT BY SHIP YARD DURING DRY-DOCK.

BALLAST TANK:

Please refer to the attached yard work done list. Partially blasting and recoating in 7W and Power tooling in
other ballast tanks.

PIPELINES:

Please refer to the attached yard work done list. Various pipes line renewed on deck including the hydraulic
pipe, Air pipe, FW pipe, steam pipe. Lagging of steam in FW pipe were renewed.

LOAD TEST, SERVICES & INSPECTIONS BY SERVICE ENGINEERS:

1. S-VDR Annual survey carried out.


2. S-VDR master unit battery and FFC battery renewed.
3. Both SART’s battery renewed.
4. Echo Sounder battery renewed.
5. FBB defective Antenna renewed. Master cabin FBB repaired.
6. LRIT Software updated and damaged cable replaced.
7. S-Band Radar transmission assembly unit, IF Board, hard disk replaced and software upgraded.
8. No. 1 VHF Antenna renewed, No. 2 VHF mother board renewed.
9. Connections made for Magnetic compass input to Auto Pilot.
10. EPIRB 5 yearly shore-based maintenance carried out.
11. VSAT system repairs carried out.
12. Talkback system renewed.
13. PA system repaired.
14. Several bridge window glass rubber packings renewed.
15. Both accommodation ladders repaired & load test done.
16. Both lifeboat davit falls renewed and 5 yearly Dynamic load test carried out.
17. Both lifeboat remote wires renewed.
18. Immersions suits and IBC Chemical suits annual servicing carried out.
19. Fixed CO2 system cylinders (101 Cylinders) hydro-tested and annual servicing carried out shore
persons.
20. Galley CO2 system annual inspection carried out by shore personnel’s
21. Fixed foam system tried out and 5 yearly inspection carried out.
22. MOT ladders repaired and load tested.
23. ODME and OWS 15 PPM monitor calibrated
5. SAAB Technician attended and carried out servicing and calibration of COT level/Pressure
/Temp gauging system on board.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

6. All draft gauge valves were overhauled.


7. ICCP and MGPS service engineer attendance and system checks carried out. Renewed ICCP
permanent anodes 4 no.s and MGPS anodes for all three sea chests.
8. ME service engineer. Renewed 6 no.s chain guide bars.
9. Wisdom marine service engineer Rectified fault of Control position and ME cyl. lubrication alarm
10. Cargo hose pressure tested.
12. High level alarm sys Service carried out.
13. Fire detection and alarm sys was installed to cover BWTS room.
15. IGG service engineer attendance upgraded IGG control module both in CCR and IGG room.
Replaced IP converter for fuel control. IGG tried out and tested.
16. Steering gear was inspected by maker service engineer. Renewed upper gland seals and
overhauled control block for no.2 steering gear.
17. Fixed tank cleaning machine overhauling
18. ME pneumatic control system service carried out, Overhauled ME all pneumatic system, main
staring air valve and lubricators actuators for all 6 units.
19. Both tank cleaning heater repair carried out.
20. Auto pilot was repaired by maker engineer
21. Lonkong marine service engineer attendance Boiler water level controller transmitter renewed for
Auxiliary boiler no.1, feed water controller adjusted. Temperature controllers for ME jacket
water, F.O service tank, ME L.O and FWG overhauled.
22. Fire detection system smoke detectors and manual call point at various places renewed, and fault
rectification carried out.
23. Kongsberg technician attendance, renewed telegraph power and indicator cards. ME remote
control system checked and AMS checks carried out.

LIFE BOAT & LIFE RAFT:

1. Both lifeboat davit falls and remote wires renewed


2. 04 nos. Life raft cradles renewed.
3. Both lifeboats 5 yearly servicing / inspection carried out.
4. Both lifeboats davit falls renewed and load tested.
5. Lifeboat air bottles annual inspection done.
6. Various minor repairs to both life boats

SAFETY EQUIPMENT:

1. 46 nos. immersion suits and 03 nos. IBC Chemical suits annual servicing carried out by shore
workshop.
2. Fixed CO2 system 101 Cylinders hydro tested by shore workshop.
3. 03 nos. UTI tapes annual servicing and calibration carried out.
4. Wasted fire / foam lines renewed at various location.
5. Wasted angle supports and U-clamps for fire / foam lines renewed at various location.
6. 02 nos. Embarkation ladder stowage angle supports renewed.
7. Various sprinklers nozzles renewed in fwd / aft paint locker, Chemical sample locker and IG
room.
8. Various gas detectors, one compound pressure gauge calibration.
9. Pressure and temperature calibrator serviced and calibrated.
10. Fixed Foam system 5 Yearly test and inspection done.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

11. Fire control station and fittings general service carried out;
12. Incinerator refractory patch up work carried out.
13. OWS chamber new relief valve fitted.

ANCHOR, WINDLASS & WINCHES:

1. Brake lining renewed for all windlass and testing done for all winches and both the windlass.
2. Windlass Port side hydraulic motor overhauled
3. STBD windlass were removed from place to yard work shop. Gear case box removed, bearing and
bushes renewed, shaft reconditioned and winch assembly installed back in place.
4. Windlass Port and Stbd side hydraulic brakes overhauled, Control block inlet and outlet hydraulic
pipes renewed. hydraulic inlet valves renewed
5. Both the Anchors & Anchor cables cleaned and shackles marked
6. Windlass and moor winches gear box inspection carried out and gear oil renewed.

NAVIGATION BRIDGE:

1. Various antenna mountings re-fabricated by Yard.


2. Various navigation light fittings re-fabricated on main mast.
3. New Stevenson Screens fixed on both side bridge wings.
4. Panama Canal shelter re-fabricated.
5. Steel work on bridge wings.

MISCELLANEOUS JOBS:
1. All PV valves were overhauled and tested.
2. All Cranes Load tested. Midship crane & both provision crane wire renewed. / limit switches for
midship crane renewed.
3. Whole of main deck area under manifold including longitudinal and transverse frames hydro
blasted cleaned and painted.
4. The supports on gangway and Gangway platform renewed.
5. Accommodation and funnel areas high pressure washed, power tooled and painted.
6. Electrical cables supporting clamps and support bases renewal on main deck and accommodation
outside.
7. 8 nos of Overhauling of Manifold Valves
8. Fwd and Aft tank cleaning heater cleaned and repaired at Yard.
9. 24 nos Tank cleaning machines overhauled by yard and shore work shop;
10. 2nd off cabin bathroom tiles Renewed .
11. Curtains and Sofa covers renewed in Crew smoke room and various cabins.
12. Manifold and catwalk gratings renewed at various places.
13. Butterworth side plating renewed for various cargo tanks
14. Various steps and catwalk gratings renewed
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

15. Hydraulic branch pipelines on deck renewed for 1W,2W,3W,4W,5W,6S,7W,&8W cargo tanks,
flanges in good condition reused.
16. Fire line renewed renewed at various locations.
17. Main & return stream line and expansion joints renewed at various locations.
18. HFO & LSMGO defective pipe lines renewed
19. Various cabins and bridge wooden fittings repaired inside accommodation,
20. New PA system & talkback system installed.
21. 2 nos. additional light for anchor station installed on forward mast.

CARGO GEAR REPAIRS / SURVEYS / REMARKS

1. All cranes load tested


2. All tank dome packing’s renewed
3. All butterworth dome packing renewed
4. Provision crane Port and Stbd hoisting and slewing Hydraulic motors, Luffing cylinder
overhauled. Port provision crane Control block overhauled.

WORK CARRIED OUT BY SHIP STAFF

1. ECDIS No. 2 Display renewed.


2. 1S,2P & 5P cargo tank power tooling & coating
3. Wasted sprinkler nozzles renewed in Paint lockers, Chemical sample locker and IG room.
4. Various fire / foam line isolation valves freed and greased.
5. Fire/Foam isolation valves freed and greased.
6. Fire hydrant leaks arrested.
7. Damaged fire hose boxes renewed as required.
8. Leaking fire hoses repaired / replaced with new ones.
9. Chipping , cleaning and painting of Fresh water tank.
10. Chipping , cleaning and painting of Aft peak tank.
11. Chipping and painting of No. 1 & No.5Void spaces.
12. De-rusting & painting of both lifeboat davit, fwd and main mast .
13. De-rusting & Painting of full accommodation area.
14. Renewal of steam Inlet & outlet valves for heating system of cargo tank.
15. Chipping & Painting of all Butterworth cover , coming & tank dome coming.
16. Renewal of All pressure gauges of manifold.
17. De-rusting of various pipeline & painting.
18. De-rusting of main deck & manifold area.
19. Annex 1 & Annex 2 valves to be de rusted & painted .
20. Roof Area above paint store de rusted & paint
21. WBT vent chipping & painting
22. Both Windlass chipping & painting.
23. Void space vent renewal.
24. Cleaning LSMGO tank, DO (p) tank , ME Lo settling tank and various other E/R tanks.
25. Complete chipping and painting of the Cascade tank, M/E air cooler casing, HT & LT
expansion tanks.
26. M/E Jacket water cooler, FWG and various heaters/coolers.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

27. Various motors overhauls.


28. Various defective valves replacement.
29. Various machinery overhauls.
30. Rectification of various faults.
31. Overhauling of various engine room pumps.
32. Fabrication of various pipe lines.
33. Both auxiliary boilers smoke side, water side and furnace side cleaning. Refractory repaired for
both boilers.
34. EGB smoke side and water side cleaning.
35. Major overhauling of FOPX no.1 purifier.
36. AE 1,2 &3 air coolers cleaned.
37. Rectifications of fuel leakages at various places.
38. All three sea chests strainer body de-rusted and painted.
39. Void space for speed Doppler log transducer cleaned de-rusted and painted.
40. Both main air reservoir cleaned, safety valve pressure tested.
41. OWS filters renewed, chamber drain stub pieces renewed and both chambers cleaned.
42. MGPS control module replaced with spare new module.
43. Deck and engine broken light fittings at various places renewed.
44. Engine room funnel top, EGB platform, boiler platform, LT coolers bottom platform and
various other places cleaned, de-rusted and painted.
45. Engine room tank top cleaned ,de rusted and painted.
46. Main engine all 6 units cylinder head studs removed, dye checked and fitted back with new O-
rings.
47. Slop P, Slop S and COT 1P cargo pumps removed and fitted back, renewed upper wear rings,
framo seal element and o-rings.
48. Installed insulation putty at various places of cable penetration area.
49. Captain’s eye installation on bridge carried out.
50. Batteries renewed for emergency generator room, fire control system and nor control system 1.

L. ENGINE

MAIN ENGINE

MANUFACTURER & TYPE: MAN B&W 6S60MC

1. All fuel pump plunger barrel renewed


2. Main Engine scavenge air cooler chemical cleaned.
3. Unit Nos. 1-6 M/E cylinder Covers, Piston rods, valves & gear removed to workshop,
dismantled, cleaned, inspected, assembled, and pressure tested. Cylinder head Gaskets and O-
rings renewed, Stuffing box overhauled, all pistons dismantled, cleaned, dye tested, assembled
and pressure tested, all liner jackets removed O-rings renewed and pressure tested.
4. All Six cylinders heads sent to outside workshop for reconditioning ;
5. Piston crown 2nos, piston skirt 6 nos, Fuel pump housing 4 nos, Exhaust valve seat and spindle
6 nos, exhaust air spring housing 4 nos reconditioned. by Longkong.
6. ME Turbocharger overhauled by Kemklen, bearings renewed.
7. M/E Crankshaft deflection taken.
8. M/E jacket water preheater cleaned and pressure tested
9. All units exhaust valves overhauled by shipyard.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

10. ME pneumatic control system valves and lubricator actuators overhauled by JUNMA
11. ME chain guide bars AFT 4 no.s and FWD moment compensator 2no.s renewed by JUNMA.

BOILERS

MANUFACTURER & TYPE EXHAUST GAS ECONOMISER – 1 SET

AUX BOILER – AALBORG, 2 SETS

1. Both Boilers main steam valves and mountings overhauled and both sides gaskets renewed;
2. Both Aux. boilers and E.G.B safety valves overhauled.
3. Port and Starboard boilers water and exhaust side cleaned.
4. Both aux. Boilers and EGB survey carried out by ABS surveyor.

AUXILIARIES & PIPELINES

1. LT cooler #1 SW outlet pipe


2. LT cooler #1 SW inlet pipe
3. LT cooler #2 SW outlet pipe
4. LT cooler #2 SW inlet pipe
5. #1 Ref sw pp discharge pipe
6. GS pp discharge pipe
7. FWG sw outlet pipe
8. STP to discharge pump pipe section
9. FWG ejector pp inlet pipe
10. Aircon sw pp discharge pipe
11. Aircon sw pp inlet pipe
12. MCSW pumps common discharge pipe section
13. MCSW pp discharge pipe to LT cooler
14. LT cooler sw to overboard pipe
15. FWG ejector pp discharge pipe
16. Scrubber outlet pipe
17. FWG sw inlet pipe
18. #1 reefer condenser sw outlet pipe
19. Aircon condenser sw inlet pipe
20. Aircon condenser sw inlet pipe
21. #2 reefer condenser sw outlet pipe
22. #2 reefer condenser sw intlet pipe
23. Modification for gray water line
24. Deck seal pumps discharge line complete
25. All overboard valves inside ER and both ballast pumps sea chest valves serviced, cleaned,
surveyed and painted with epoxy paint.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

26. Bilge overboard and boiler blowdown valve removed from place , overhauled and fitted back in
place after survey,
27. Various tanks inside ER cleaned for Special survey.

GENERATORS

1. Diesel Generator 1,2 &3 air coolers cleaned.


2. DG #2 & #3 cooling water line thermostatic valves renewed.
3. DG#3 sump oil renewed.
4. All 3 governors were overhauled by yard

HEAT EXCHANGERS

1. Atmospheric condenser cleaning and pressure testing.


2. ME jacket water heater cleaning and pressure testing.

AUTOMATION AND CONTROLS

1. Nakakita temperature controllers overhauled and adjusted by Lonkong marine.

CLEANING OF ENGINE ROOM TANKS

Following Tanks cleaned

1. FO Sludge Tank
2. Bilge Water Tank
3. ME LO Settling Tank
4. Boiler Water Tank
5. LT Expansion Tank
6. HT Expansion Tank
7. Incinerator SD Tank
8. Incinerator Sludge Tank
9. Waste Oil Tank
10. ME Scavenge Box Drain Tank
11. LSFO Centre Tank
12. FOT port tank
13. FOT stbd tank
14. ME Cofferdam cleaning and inspection
15. DO Storage Tank (port)
16. ME L.O sump tank
17. F.O drain tank
18. L.O sludge tank
19. F.O service tank
20. F.O settling tank.
IMC Ship Management Pte. Ltd.
3 Anson Road, #06-01 Springleaf Tower,
Singapore 079909

REFRIGERATED CARGO MACHINERY


(COMPRESSORS, EVAPORATORS, PIPELINES ETC.)

1.Accommodation AC plant no 2 unit evaporator unit renewed. System pressure and vacuum tested.
2. Accommodation AC condenser end covers renewed.
3. ECR Ac condenser end cover renewed.

M. ELECTRICAL EQUIPMENT

Below motors overhauled by yard and bearings renewed, dynamic balancing done where applicable

1. ER VENT FAN MOTOR ( 4 No.) 19 KW AND BALANCING OF FANS


2. POWER PACK MOTOR ( 3,4,5) 380 KW
3. DHF FAN MOTOR (2 No.) 35KW
4. AUX BLR FD FAN MOTOR(2No.)42 KW AND BALANCING OF FANS
5. MAIN AIR COMP. MOTOR (2 No) 34 KW
6. UTILITY AIR COMP MOTOR(1 No) 55KW
7. CONTROL AIR COMPRESSOR(1NO)
8. MSW PP MOTOR (2 No.) 35KW
9. MAIN ENGINE AUX BLOWER (2 No.)
10. BOSUN STORE EXH FAN MOTOR (1 No.) 4.5 KW
11. PAINT STORE EXH FAN MOTOR (1 No.) 4.5 KW
12. MIDSHIP DECK STORE EXH FAN MOTOR (1 No.) 2.5 KW
13. DHF ROOM EXH FAN MOTOR (1 No.) 2.5 KW
14. IGG BLOWER MOTOR.(1,2) AND BALANCING OF FAN
15. GALLEY EXH FAN MOTOR (1 No.) 2.5 KW
16. HOSE HANDLING CRANE MOTOR (1 No.) 25KW
17. HYDRAULIC PUMP ROOM EXH FAN MOTOR(1 No.) 1.5 KW
18. SUPPLY FAN FOR HYDRAULIC POWER PACK (1 No.) 22 KW
19. LIFEBOAT DAVIT (PORT & STBD) (2 NOs) 22 KW
20. SPARE AC COOLING WATER P/P MOTOR (ABB), 18 KW
21. A/E FO BOOSTER P/P #2 MOTOR
22. LO PURIFIER PP MOTOR #1
23. EMCY FIRE PUMP MOTOR
24. MSB and ESB cleaning and testing, All ACB safeties tested.

N. MISCELLANEOUS

SURVEYS

The 4th intermediate Survey carried out and certificates issued by the ABS Class Surveyor.

CAP 1 Survey carried out and completed on board, reports submitted to ABS Houston office for review and
assignment of CAP rating. EST 15T of steel renewed as per UT gauging carried out on board under ABS
Surveyor guidance.